Weekend Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

ISTQB-CTFL ISTQB Certified Tester Foundation Level (CTFL v4.0) Questions and Answers

Questions 4

Which ONE of the following is a CORRECT example of the purpose of a test plan?

Options:

A.

A test lead decides to write a detailed test plan so that in future, in case of project failure responsibilities could be assigned to the right person

B.

A test manager should always create a very simple test plan because the purpose of test plan is to ensure that there is documentation for the purpose of audits.

C.

A test plan is a good document to have for the agile projects because it helps the test manager assign tasks to different people

D.

A test manager decides to create a one page test plan for an agile project for communicating the broad activities and explaining why detailed test cases will not be written as mandated by the test policy.

Buy Now
Questions 5

The following chart represents metrics related to testing of a project that was competed. Indicate what is represented by tie lines A, B and the axes X.Y

ISTQB-CTFL Question 5

A)

ISTQB-CTFL Question 5

B)

ISTQB-CTFL Question 5

C)

ISTQB-CTFL Question 5

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 6

Which or the following would be a key difference between a peer review of code and static analysis of code using a tool?

Options:

A.

A peer reviews finds defects while static analysis finds failures.

B.

Static analysis targets the code technically whereas Peer review is applicable to further aspects.

C.

Peer reviews cannot find missing requirements whereas static analysis can

D.

A peer reviews find failures while static analysis finds defects.

Buy Now
Questions 7

Which of the following statements about reviews are TRUE?

I. In walkthroughs the review meeting is typically led by the author.

II Inspection is characterized by an open-ended review meeting

III Preparation before the review meeting is part of informal reviews

IV Management rarely participates in technical review meetings

Options:

A.

II, Ill

B.

I, II

C.

I, IV

D.

III, IV

Buy Now
Questions 8

Which review type, also known as a “buddy check”, is commonly used in Agile development?

Options:

A.

Inspection.

B.

Walkthrough.

C.

Technical review.

D.

Informal review.

Buy Now
Questions 9

Which sequence of state transition stated in the answer choices is correct in accordance with the following figure depicting me life-cycle of a defect?

ISTQB-CTFL Question 9

Options:

A.

S0->S1->S2->S3->S4

B.

S0->S1->S2->S3->S5^>S1

C.

S0->S1->S2->S3->S5->S1->S2->S3

D.

S0->S1->S2->S3->S5->S3->S4

Buy Now
Questions 10

Which of the following are the phases of the ISTQB fundamental test process?

Options:

A.

Test planning and control, Test analysis and design, Test implementation and execution, Evaluating ex t criteria and reporting. Test closure activities

B.

Test planning, Test analysis and design. Test implementation and control. Checking test coverage and reporting, Test closure activities

C.

Test planning and control, Test specification and design. Test implementation and execution, Evaluating test coverage and reporting, Retesting and regression testing, Test closure activities

D.

Test planning. Test specification and design. Test implementation and execution. Evaluating exit criteria and reporting. Retesting and test closure activities

Buy Now
Questions 11

Which type of software development product can undergo static testing?

Options:

A.

Any software development product can undergo static testing, including requirements specifications, design specifications and code.

B.

Static tests should be performed on the installation and user guide documents as these documents are used by the end user.

C.

Static testing is done only on the code as part of the "code review" sessions Other documents are reviewed, but not by static testing.

D.

Static testing is done only on the requirements You need to execute the software in order to find defects in the code.

Buy Now
Questions 12

As the last stage of a test cycle of an embedded device, you are performing exploratory testing. You observed that some character. (A, X and Z) sent via a serial port to the device do not get registered on the device whereas they should be. You suspect that this could be due to a wrong configuration of the "bit parity" parameter.

Which of the following items of an incident report would you be UNABLE to write down based on this information?

Options:

A.

Expected result

B.

Test case identifier

C.

Test setup details

D.

Actual result

Buy Now
Questions 13

You are testing a room upgrade system for a hotel. The system accepts three differed types of room (increasing order of luxury): Platinum. Silver and Gold Luxury. ONLY a Preferred Guest Card holder s eligible for an upgrade.

Below you can find the decision table defining the upgrade eligibility:

What is the expected result for each of the following test cases?

Customer A: Preference Guest Card holder, holding a Silver room

Customer B: Non Preferred Guest Card holder, holding a Platinum room

Options:

A.

Customer A; doesn't offer any upgrade; Customer B: offers upgrade to Gold luxury room

B.

Customer A: doesn't offer any upgrade; Customer B: doesn't offer any upgrade.

C.

Customer A: offers upgrade to Gold Luxury room; Customer B: doesn't offer any upgrade

D.

Customer A: offers upgrade to Silver room; Customer B: offers upgrade to Silver room.

Buy Now
Questions 14

Which of the following statements best describes the way in which decision coverage is measured?

Options:

A.

Measured as the number of statements executed by the tests, divided by the total number of executable statements in the code.

B.

Measured as the number of lines of code executed by the tests, divided by the total number of lines of code in the test object.

C.

Measured as the number of decision outcomes executed by the tests, divided by the total number of decision outcomes in the test object.

D.

It is not possible to accurately measure decision coverage.

Buy Now
Questions 15

Which of the following statements best describe Behavior-Driven Development (BDD)?

Options:

A.

A collaborative approach that allows every stakeholder to contribute to how the software component must behave.

B.

Expresses the behavior of an application with test cases written in Given When Then format.

C.

Is used to develop code guided by automated test cases.

D.

A psychological technique in which the team's behavior in agile teams is evaluated.

Buy Now
Questions 16

Consider the following defect report for an Exam Booking System

Defect ID: ST1041 | Title: Unable to cancel an exam booking | Severity: Very High | Priority: Very High | Environment: Windows 10, Firefox

Description: When attempting to cancel an exam booking using the cancel exam feature, the system does not cancel the exam even though it shows a message that the exam has

been cancelled.

Which ONE of the following indicates the information that should be added to the description for reproducing the defect easily?

Options:

A.

Providing better severity and priority. It is not clear why this is a high severity problem as the exams can be booked without any problem.

B.

Providing exact steps that lead to this defect. It is not clear from the description if this is a problem for any scheduled exam or for a specific user.

C.

The defect Id used is alphanumeric in nature. It should be a number only.

D.

Repeating the test case with different browsers and logging a separate defect for each one of them

Buy Now
Questions 17

Which of the following answers describes a reason for adopting experience-based testing techniques?

Options:

A.

Experience-based test techniques provide more systematic coverage cnteria than black-box and white-box test techniques

B.

Experience-based test techniques completely rely on the tester's past experience for designing test cases.

C.

Experience-based test techniques allow designing test cases that are usually easier to reproduce than those designed with black-box and white-box test techniques.

D.

Experience-based test techniques tend to find defects that may be difficult to find with black-box and white-box test techniques and are often useful to complement these more systematic techniques.

Buy Now
Questions 18

A state transition diagram describes a control system’s behavior in different operational modes. The initial state is “NORMAL MODE”.

Which ONE of the following test cases covers an INVALID sequence?

Options:

A.

NORMAL MODE → DIAGNOSTIC MODE → DEGRADED MODE → EMERGENCY MODE → DIAGNOSTIC MODE → NORMAL MODE → DIAGNOSTIC MODE

B.

NORMAL MODE → DEGRADED MODE → NORMAL MODE → DIAGNOSTIC MODE → DEGRADED MODE → EMERGENCY MODE → DIAGNOSTIC MODE

C.

NORMAL MODE → DIAGNOSTIC MODE → DEGRADED MODE → EMERGENCY MODE → DIAGNOSTIC MODE → NORMAL MODE → DEGRADED MODE

D.

NORMAL MODE → DIAGNOSTIC MODE → NORMAL MODE → DIAGNOSTIC MODE → EMERGENCY MODE → DIAGNOSTIC MODE → NORMAL MODE

Buy Now
Questions 19

Which test approach will best fit a new project, with little documentation and high probability for bugs?

Options:

A.

Exploratory testing

B.

Requirements based testing

C.

Metric based approach

D.

Regression testing

Buy Now
Questions 20

Which ONE of the following options explains a benefit of independent testing the BEST?

Options:

A.

The testers can be isolated from the development team and thus avoid acquiring the same bias as the developers.

B.

Independent testers may lack information regarding the test object.

C.

Independent testers are likely to recognize different types of failures compared to developers.

D.

Developers may lose a sense of responsibility for the quality of the product they develop.

Buy Now
Questions 21

You are testing the latest version of an air-traffic control system prior to production deployment using exploratory testing. After following an unusual sequence of input steps, the system crashes. After the crash, you document a defect report with the following information:

•Title: System crashes unexpectedly during input.

•Brief summary: System crashes when an unusual sequence of inputs is used.

•Version: V1.001

•Test: Exploratory testing prior to production deployment

•Priority: Urgent

•Risk: High

•References: Screenshot of crashed application

What critical Information Is missing from this report?

Options:

A.

Conclusions, recommendations, and approvals.

B.

Change history.

C.

Description of the defect to enable reproduction.

D.

Status of defect

Buy Now
Questions 22

Select the roles required in a formal review:

Options:

A.

Author, Management, Facilitator, Review Leader, Reviewers, Scribe

B.

Author, Tester. Facilitator. Review Leader. Reviewers. Scribe

C.

Author, Business analyst. Facilitator, Review Leader. Reviewers. Scribe

D.

Author. Developer, Facilitator. Review Leader. Reviewers. Scribe

Buy Now
Questions 23

ST is a Software Testing organization which utilizes a testing knowledge base. Access to ST knowledge base can be either full or limited. Access level is determined based on ST certification and testing experience as follows:

1. If ST certified, with less than 5 years testing experience - allow limited access

2. If ST certified, 5-10 years of testing experience - allow full access

3. If not ST certified with 5-10 years of testing experience - allow limited access.

What would be the results for:

A - ST certified. 12 years of testing experience

B - Not ST certified. 7 years of testing experience

C - Not ST certified. 3 years of testing experience

Options:

A.

A - unknown

B - limned access

C- unknown

B.

A - full access

B - limited access

C - unknown

C.

A - full access

B - limited access

C - limited access

D.

A - unknown

B - full access

C - unknown

Buy Now
Questions 24

Which ONE of the following statements BEST applies to checklist-based testing?

Options:

A.

Checklists should contain general guidelines to ensure that all aspects of the software are covered.

B.

Checklists should contain specific test conditions that can be individually and directly checked.

C.

Checklists should primarily consist of automated test cases to maximize efficiency.

D.

Checklists should be used exclusively for functional testing, as they are unsuitable for non-functional testing.

Buy Now
Questions 25

Which ONE of the following activities TYPICALLY belongs to the planning phase of the review process?

Options:

A.

A separate defect report is created for each identified defect so that corrective actions can be tracked.

B.

Each reviewer conducts an individual review to identify anomalies, recommendations, and questions.

C.

The purpose and scope of the review are defined, as well as the work product to be reviewed and the exit criteria.

D.

The reviewers analyze and discuss the anomalies found during the review in a joint meeting.

Buy Now
Questions 26

Which of the following would be the LEAST likely to be used as the basis for a test exit criteria?

Options:

A.

Test schedules

B.

Cost of testing performed so far

C.

Confidence of testers in tested code

D.

Number of unfixed defects

Buy Now
Questions 27

Which of the following is NOT a product risk?

Options:

A.

Poor software usability

B.

Failure-prone software is delivered

C.

Problems in defining the right requirements

D.

Software does not perform the intended functions

Buy Now
Questions 28

Calculate the measurement error SD for the following estimates done using three point estimation technique-Most optimistic effort (a) -120 person days Most likely effort (m) -180 person days Most pessimistic effort (b) - 240 person days

Options:

A.

180

B.

120

C.

197

D.

20

Buy Now
Questions 29

Which of the following is a role that is usually responsible for documenting the findings (e.g., action items, decisions, recommendations) made by the review team as part of a typical formal review?

Options:

A.

Review leader

B.

Facilitator.

C.

Recorder.

D.

Moderator

Buy Now
Questions 30

Which of the following statements about the testing quadrants is TRUE?

Options:

A.

The higher the number of the testing quadrant, the more important the tests associated with this quadrant are

B.

Automated acceptance tests produced during BDD and ATDD are classified in quadrant 02.

C.

Exploratory tests are classified in quadrant Q3, and they are usually included in a continuous integration process.

D.

Automated unit tests produced during TDD are classified in quadrant Q4 as they are technology facing.

Buy Now
Questions 31

Which of the following BEST matches the descriptions with the different categories of test techniques?

1.Test cases are based on the test basis which may include the requirements, use cases and user stories

2.Test cases are based on the test basis which may include the software architecture or code

3.Test cases can show deviations from the requirements

4.These test techniques are applicable to both functional and non-functional testing

5.Tests are based on knowledge of developers, users and other stakeholders

Black - Black-box test techniques

White * White-box test techniques

Experience - Experience-based test techniques

Options:

A.

Black -1,3.4 White - 2 Experience - 5

B.

Black - 2, 3 White -1 Experience - 4, 5

C.

Black -1,2 White - 3, 4 Experience - 5

D.

Black - 2, 3 White -1,5 Experience - 4

Buy Now
Questions 32

Which of the following is a typical product risk?

Options:

A.

Poor usability of the software

B.

A problem in the code developed by a 3rd party

C.

Low quality of the configuration data, test data and tests

D.

Problem in defining the right requirements

Buy Now
Questions 33

Which of the following statements best describes how configuration management supports testing?

Options:

A.

Configuration management helps reduce testing effort by identifying a manageable number of test environment configurations in which to test the software, out of all possible configurations of the environment in which the software will be released

B.

Configuration management is an administrative discipline that includes change control, which is the process of controlling the changes to identified items referred to as Configuration Items'

C.

Configuration management is an approach to interoperability testing where tests are executed in the cloud, as the cloud can provide cost-effective access to multiple configurations of the test environments

D.

Configuration management helps ensure that all relevant project documentation and software items are uniquely identified in all their versions and therefore can be unambiguously referenced in test documentation

Buy Now
Questions 34

Which of the following statements contradicts the general principles of testing?

Options:

A.

Most defects are found in a small subset of a system's modules.

B.

If new defects are to be found we should run the same test set more often.

C.

Testing is better if it starts at the beginning of a project.

D.

How testing is done, is based on the situation in a particular project.

Buy Now
Questions 35

Which of the following statements is CORRECT about the value added by a tester to release planning?

Options:

A.

The tester estimates the testing effort for individual iterations

B.

The tester writes acceptance criteria

C.

The tester breaks down user stories into smaller testing tasks

D.

The tester assesses the testability of the user stories

Buy Now
Questions 36

You are testing the download process of a mobile phone application.

For which to the following capabilities to the system you need to design a nonfunctional test?

Options:

A.

It was easy to locate, download and install the application

B.

The application was correctly downloaded

C.

The application created an installation log file in a given folder

D.

The application installed only after the user's approval

Buy Now
Questions 37

During iteration planning, a scrum team uses an estimation technique called planning poker to estimate the effort required to deliver a critical user story. In advance of the estimation session, the team agreed on some ground rules to limit the number of poker rounds and save time.

The team agreed on the following:

1. They will use the following progression for estimation: Extra-small, Small, Medium, Large, Extra-large, and Extra-extra-large.

2. If estimation values differ significantly, the highest score will be used for estimation purposes.

The result of the first round of planning poker:

Team MemberEstimation

BusinessLarge

DevelopmentExtra-extra-large

TestingExtra-extra-large

Which of the following options best represent the team’s next actions?

Options:

A.

The fact that all estimations are high indicate that the user story is not well understood or should be broken down into multiple smaller stories.

B.

The pre-agreed rules state that the highest score should be used for estimation, resulting in the user story being categorised as Extra-extra-large.

C.

Since the business representative is likely to have the most informed view of the requirement, the user story is categorised as a Large.

D.

the team discusses the differences in the estimates and repeats the poker round until an agreemet is reached.

Buy Now
Questions 38

The following part of a business process flow is specified; REPEAT (book a bill) UNTIL (User presses Cancel). How many test cases are necessary in order to achieve 100% branch coverage of the process flow?

Options:

A.

4

B.

1

C.

2

D.

Infinite

Buy Now
Questions 39

Which of the following is the main difference between quality assurance (QA) and quality control

Options:

A.

A is the responsibility of everyone on a project, while QC is the responsibility of a dedicated team.

B.

A is a process-oriented approach, while QC is a product-oriented approach.

C.

A is focused on implementation, while QC is focused on improvement.

D.

A is preventive, while QC is corrective.

Buy Now
Questions 40

A test manager decided to skip static testing since he believes bugs can be found easily by doing dynamic testing. Was this decision right or wrong?

Options:

A.

The decision was wrong. Ensuring quality mandates that static testing is performed after performing the dynamic testing.

B.

The decision was right. Static testing is usually redundant if a product is planned to go through a full-cycle of dynamic testing.

C.

The decision was right. Most of the bugs are easier to identify during the dynamic testing.

D.

The decision was wrong. Static testing can find defects early in the development process, reducing the overall cost of testing and development

Buy Now
Questions 41

Use Scenario 1 “Happy Tomatoes” (from the previous question).

When running test case TC_59, the actual result for t = 35 degrees Celsius is OUTPUT = X instead of the expected output.

Which information should NOT be included in the defect report?

Options:

A.

Identification of the test object and test environment

B.

A concise title and a short summary of the defect being reported

C.

Description of the structure of the test team

D.

Expected results and actual results

Buy Now
Questions 42

A software module to be used in a mission critical application incorporates an algorithm for secure transmission of data.

Which review type is most appropriate to ensure high quality and technical correctness of the algorithm?

Options:

A.

Walkthrough

B.

Informal Review

C.

Technical Review

D.

Management Review

Buy Now
Questions 43

In which of the following cases you would NOT execute maintenance testing?

Options:

A.

Retirement of the software or system

B.

Modifications to a released software or system

C.

Migration of the system data to a replacement system

D.

Update to the Maintainability requirements during the development phase

Buy Now
Questions 44

From a testing perspective, configuration management

Options:

A.

Allows the expected results to be compared with the actual results.

B.

Allows the tracking of all changes to versions of the testware.

C.

Includes all activities that direct and control an organisation with regard to quality

D.

Focuses on configuring static analysis tools to choose the most suitable breadth and depth of analysis.

Buy Now
Questions 45

Which of the following BEST describes exploratory testing?

Options:

A.

Exploratory testing is a suitable test technique which may replace both black-box and white-box test techniques

B.

Exploratory testing is a valid and useful black-box test technique since it focuses on test cases related to the architecture and design of a system

C.

Exploratory testing requires both solid specifications and much project time available for test execution

D.

Exploratory testing may be used within defined time periods, during which the tester may follow a test charter as a guide

Buy Now
Questions 46

Which of the following statements about retrospectives is TRUE?

Options:

A.

Only developers and testers should be involved in retrospectives, as involving people in other roles is very likely to prevent developers and testers from having open and constructive discussions that really help identify process improvements.

B.

Retrospectives can be very effective in identifying process improvements and can also be very efficient and cost-effective especially since, unlike reviews, they do not require any follow-up activities

C.

On Agile projects, well-conducted retrospectives at the end of each iteration can help the team reduce and sometimes even eliminate the need for dairy stand-up meetings.

D.

During retrospectives, in addition to identifying relevant process improvements, participants should also consider how to implement these improvements and retain them based on the context of the project, such as the software development lifecycle.

Buy Now
Questions 47

A software company decides to invest in reviews of various types. The thought process they have is that each artifact needs to be reviewed using only one of the review methods depending on the criticality of the artifact.

Options:

A.

The thought process is incorrect. The whole company should adopt same standard for review of all artifacts.

B.

The thought process is correct. The whole company should decide or the review method based on their CMM level.

C.

The thought process is incorrect. Same artifact can be reviewed using different review methods

D.

The thought process is correct. It wastes time to review same artifact using efferent review methods

Buy Now
Questions 48

Which ONE of the following is a characteristic of exploratory testing?

Options:

A.

Effectiveness depends on the individual testers' skills

B.

Usually conducted when there is sufficient time for testing

C.

Testing without defined time-boxes

D.

Test cases are written once the specifications become available

Buy Now
Questions 49

Consider the following user story and its acceptance criteria:

User Story:

As a member of the "Agnotoly" association, I want to be able to pay the association’s dues through an automatic payment method so that I can forget about payment deadlines.

Acceptance Criteria:

    The member can only pay with ‘Agnesis Master’ credit card.

    The member must register their cell phone number.

    The member must register the credit card in the payment system.

    The member must select a payment method (monthly or annual).

    The member must accept the terms and conditions for the selected method.

    If terms and conditions are accepted, the system sends an OTP (one-time password) to the member’s phone for verification.

    The payment method is registered only after OTP verification.

    Once the payment method is registered, the system will charge on the first business day of the following month.

Test Cycle Results:

    Members successfully paid dues using the credit card.

    Payments were processed monthly and for over a year.

Which ONE of the following options identifies the acceptance criteria that has NOT been fully covered?

Options:

A.

Acceptance criteria 8 has not been fully covered during the above test cycle.

B.

Acceptance criteria 4 has not been fully covered during the above test cycle.

C.

All acceptance criteria have been fully covered during the above test cycle.

D.

Acceptance criteria 6 has not been fully covered during the above test cycle.

Buy Now
Questions 50

You are testing an e-commerce system that sporadically fails to properly manage customers' shopping carts. You have stressed the urgency of this situation to the development manager and development team and they recognize the priority of resolving the underlying defect. The development team is waiting for more information, which you will include in your defect report. Given the following items of information they are included in a typical defect report:

1. The expected results

2. The actual results

3. The urgency and priority to fix this

4. The date and author of the defect report

5. A description of the defect in order to reproduce, including screenshots and database dumps

Which of these items will be MOST useful to the developers to help them identify and remove the defect causing this failure?

Options:

A.

1, 2, 5

B.

1, 2, 3, 4, 5

C.

1, 2, 4

D.

3, 4

Buy Now
Questions 51

A mid-size software product development company has analyzed data related to defects detected in its product and found out that detects fixed in earlier builds are getting re-opened after a few months.

The company management now seeks your advice in order to reverse this trend and prevent re-opening of defects fixed earlier.

What would be your FIRST recommendation to the company?

Options:

A.

Automate existing test suits so that lesser time is spent on execution of each test, and more tests can be executed m the available time thus leading to a lower probability of defects slipping by

B.

Verify existing regression test suite are adequate, and augment it, if required, in order to ensure that defects fixed earlier get re-tested in each subsequent build

C.

Analyze the product modules containing maximum defects, and get them thoroughly tested and defects fixed as a one-time activity

D.

If required, tram the teams responsible for development and testing of the modules containing maximum number of defects, and if this does not help, replace them with more knowledgeable people

Buy Now
Questions 52

Which of the following is not an example of a typical content of a test completion report for a test project?

Options:

A.

The additional effort spent on test execution compared to what was planned

B.

The unexpected test environment downtime that resulted in slower test execution

C.

The residual risk level if a risk-based test approach was adopted

D.

The test procedures of all test cases that have been executed

Buy Now
Questions 53

Which of the following BEST matches the attributes with a level of testing?

I. Stubs and drivers are often used

II The lest environment should correspond to the production environment

III Finding defects is not the main focus

IV Testing can be based on use cases

V Testing is normally performed by testers

VI Testing for functional and non-functional characteristics

Options:

A.

Component - VI

Integration - IV

System -1

Acceptance - 111

B.

Component - IV

Integration -1

System - VI

Acceptance - V

C.

Component-I

Integration - V

System - II

Acceptance - IV

D.

Component - V

Integration - II

System - IV

Acceptance - VI

Buy Now
Questions 54

A system computes prices for bus tickets. The price depends on

- the passenger type (baby, child, adult, senior citizen, student, military)

- the travelling type (as single or in a group)

- the distance (zone 1. 2. 3)

- the kind of transport (ordinary, express)

Which of the following test techniques is the most appropriate one for testing the price computation?

Options:

A.

Statement coverage

B.

State transition testing

C.

Equivalence partitioning

D.

Use case testing

Buy Now
Questions 55

You are a tester working on a critical project. Based on the risk analysis you execution? Priority 1 is the highest and Priority 3 is the lowest priority.

ISTQB-CTFL Question 55

Options:

A.

D-C- B-A

B.

D-B-A-C

C.

C-B-A-D

D.

D-A-B-C

Buy Now
Questions 56

The following 4 equivalence classes are given:

Which of the following alternatives includes correct test values for x. based on equivalence partitioning?

Options:

A.

-100; 100:1000; 1001

B.

-500; 0; 100; 1000

C.

-99; 99:101; 1001

D.

-1000; -100; 100; 1000

Buy Now
Questions 57

Which of the following statements about testing in the context of an agile (iterative-incremental) development model is correct?

Options:

A.

Unit test and acceptance test ate the most important tests to make sure that the system works as expected.

B.

Each iteration of testing has to be completely finished before a new Iteration of development starts.

C.

Regression testing is necessary whenever a new Increment Is added to the existing system. D. Only certain types of non-functional and explorative testing are performed.

Buy Now
Questions 58

Which of the following statements about the shift-left approach is FALSE?

Options:

A.

The shift-left approach can only be implemented with test automation

B.

The shift-left approach in testing is compatible with DevOps practices.

C.

The shift-left approach can involve security vulnerabilities

D.

The shift-left approach can be supported by static analysis tools.

Buy Now
Questions 59

Which ONE of the following statements would you expect to be the MOST DIRECT advantage of the whole-team approach?

Options:

A.

Capitalizing on the combined skills of business representatives, testers, and developers working together to contribute to project success.

B.

Reducing the involvement of business representatives because of enhanced communication and collaboration between testers and developers.

C.

Avoiding requirements misunderstandings that may not have been detected until dynamic testing when they are more expensive to fix.

D.

Having an automated build and test process, at least once a day, that detects integration errors early and quickly.

Buy Now
Questions 60

A system has valid input numbers ranging between 1000 and 99999 (both inclusive). Which of the following inputs are a result of designing tests for all valid equivalence classes and their boundaries?

Options:

A.

999.1000.23232.99999.100000

B.

999.1000.50000.100000.100001

C.

999.100000

D.

1000,50000,99999

Buy Now
Questions 61

Determining the schedule for each testing activity and test milestones for a test project, using activity estimates, available resources, and other constraints is a typical task performed during

Options:

A.

Test execution

B.

Test design.

C.

Test analysis.

D.

Test planning

Buy Now
Questions 62

Which of the following statements BEST describes how test cases are derived from a use case?

Options:

A.

Test cases are derived based on non-functional requirements such as usability

B.

Test cases are created using white-box test techniques to execute scenarios of use cases

C.

Test cases are derived based on pair testing between a user and a tester to find defects

D.

Test cases are designed to cover various user behaviors, including basic, exceptional or alternative and error behaviors associated with human users or systems

Buy Now
Questions 63

You need to test the login page of a web site. The page contains fields for user name and password. Which test design techniques are most appropriate for this case?

Options:

A.

Decision table testing, state transition testing.

B.

Equivalence partitioning, Boundary value analysis.

C.

Exploratory testing, statement coverage.

D.

Decision coverage, fault attack.

Buy Now
Questions 64

Which of the following statements is CORRECT?

Options:

A.

Test cases are made up of input values, expected results and actual results developed to cover test objectives

B.

Test cases describe items or events to test that are derived from the test basis during the test analysis activity

C.

Test cases are sequences of actions for test execution specified during the test implementation activity D. Test cases are derived during the test design activity to cover test objectives or test conditions

Buy Now
Questions 65

Which statement best describes the key difference between a mindset for test activities and a mindset for development activities?

Options:

A.

A tester possesses professional pessimism while a developer is concerned with validating the product

B.

A tester is concerned with finding defects while a developer is interested in designing solutions

C.

A tester is interested in building solutions while a developer is concerned with verifying the product

D.

A tester is concerned with verifying the product while a developer possesses professional pessimism

Buy Now
Questions 66

A software application incorrectly provided customers discounts of 50% off their total purchases if the purchases exceeded S100. It was discovered through an audit that the discount should have been only 5% off these purchases. A root cause analysis uncovered that the requirements Incorrectly stated 50% instead of 5% in this scenario.

Which of the following MOST accurately reflects this scenario?

Options:

A.

The audit finding Is the root cause, the incorrect calculation of 50% Is the defect, and the Incorrect requirement Is the effect

B.

The incorrect customer discount is the effect and the reason for the requirement error is the root cause

C.

The incorrect discount is the root cause, requiring a root cause analysis which led to investigating the software code, design, and requirements

D.

A defect in the code is determined to be the root cause of the incorrect calculation

Buy Now
Questions 67

Consider the following user story about an e-commerce website's registration feature that only allows registered users to make purchases ; As a new user, I want to register to the website, so that I can start shopping online"

The following are some of the acceptance criteria defined for the user story

[a] The registration form consists of the following fields: username, email address, first name, last name, date of birth, password and repeat password.

[b] To submit the registration request, the new user must fill in all the fields of the registration form with valid values and must agree to the terms and conditions.

[c] To be valid, the email address must not be provided by free online mail services that allow to create disposable email addresses. A dedicated error message must be presented to inform the new user when an invalid address is entered.

[d] To be valid, the first name and last name must contain only alphabetic characters and must be between 2 and 80 characters long A dedicated error message must be presented to inform the new user when an invalid first name and/or the last name is entered

[e] After submitting the registration request, the new user must receive an e-mail containing the confirmation link to the e-mail address specified in the registration form

Based only on the given information, which of the following ATDD tests is MOST LIKELY to be written first?

Options:

A.

The new user enters valid values in the fields of the registration form, except for the email address, where he/she enters an e-mail address provided by a free online mail service that allow to create disposable email addresses. Then he/she is informed by the website about this issue.

B.

The new user enters valid values in the fields of the registration form, except for the first name, where he/she enters a first name with 10 characters that contains a number. Then he/she is informed by the website about this issue.

C.

The user accesses the website with a username and password, and successfully places a purchase order for five items, paying by Mastercard credit card

D.

The new user enters valid values in all the fields of the registration form, confirms to accept all the terms and conditions, submits the registration request and then receives an e-mail containing the confirmation link to the e-mail address specified in the registration form

Buy Now
Questions 68

Which of the following statements about traceability is FALSE?

Options:

A.

Traceability between test basis items and the test cases designed to cover them, makes it possible to determine which test basis items have been covered by the executed test cases.

B.

Traceability between test basis items and the test cases designed to cover them, enables experience-based test techniques to be applied

C.

Traceability between test basis items and the test cases designed to cover them, enables identification of which test cases will be affected by changes to the test basis items.

D.

Traceability can be established and maintained through all the test documentation for a given test level, such as from test conditions through test cases to test scripts.

Buy Now
Questions 69

Which of the following statements is TRUE'?

Options:

A.

Unlike functional testing, non-fundional testing can only be applied to conventional systems, not artificial intelligence-based system.

B.

Functional testing focuses on what the system is supposed to do, while white-box testing focuses on how well the system does what it is supposed to do

C.

Functional testing can be applied to all test levels, while non-functional testing can be applied only to system and acceptance test levels.

D.

Black-box test techniques and experience-based test techniques may be applicable to both functional testing and non-functional testing

Buy Now
Questions 70

A tester created a decision table(DT) given below. While reviewing the DT some of the actions for the given conditions were found to be incorrect. The user is trying to view the profile, which of the given conditions has CORRECT action(s) listed?

ISTQB-CTFL Question 70

Options:

A.

C1

B.

C4

C.

C3

D.

C2

Buy Now
Questions 71

Match each objective to the correct test level

Objective:

A)Verifying whetherthe functionalandnon-functlonalbehaviorsof the system are as designed andspecified.

B)Verifying whetherthe functionalandnon-functlonalbehaviorsof the interfaces are as designed.

C)Verifying whetherthe functionalandnon-functionalbehaviorsof the components are as designedand specified.

D)Establishing confidence in the quality of the systemas a whole.

Test Level:

1.Component testing.

2.Integration testing.

3.System testing.

4.Acceptance testing.

Options:

A.

A3, B2. C4. D1

B.

A2, B3, Cl, D4

C.

A3. B2. C1. D4

Buy Now
Questions 72

Which of the following statements about estimation of the test effort is WRONG?

Options:

A.

Once the test effort is estimated, resources can be identified and a schedule can be drawn up.

B.

Effort estimate can be inaccurate because the quality of the product under tests is not known.

C.

Effort estimate depends on the budget of the project.

D.

Experience based estimation is one of the estimation techniques.

Buy Now
Questions 73

Metrics can be collected during and at the end of testing activities to assess which of the following?

i. Progress against the planned schedule and budget.

II. Current quality of the test object.

Hi. Adequacy of the test approach.

iv. Effectiveness of the test activities with respect to the objectives.

v. All the above.

Select the correct answer:

Options:

A.

Only i and ii.

B.

Only i and iii.

C.

Only I, ii and iv.

D.

Only v.

Buy Now
Questions 74

A document descnbes the test procedures that have been derived for the identified test sets Among other things, the order in which the test cases in the corresponding test set are to be executed according to the dependencies described by preconditions and postconditions is specified This document is a typical work product produced as part of:

Options:

A.

Test design.

B.

Test analysis

C.

Test Implementation.

D.

Test monitoring and control

Buy Now
Questions 75

A team's test strategy was to invest equal effort in testing each of a system's modules. After running one test cycle, it turned out that most of the critical bugs were detected in one of the system's modules.

Which testing principal suggests a change to the current test strategy for the next test cycle?

Options:

A.

Pesticide Paradox

B.

Early testing

C.

Absence-of-errors fallacy

D.

Defect clustering

Buy Now
Questions 76

For withdrawing money tram an Automated Teller Machine (ATM), the following conditions are required:

- The bank card is valid

- The PIN code is correct

- Money is available in the user's account

The following are some possible interactions between the user and the ATM:

- The entered card is invalid The card is rejected

- The PIN code is wrong The ATM asks for another PIN code

- The requested amount is more than available in the user's account: The ATM asks for another amount

- The requested amount is available in the user's account The ATM dispenses the money

Which test design technique should be used to cover all possible combinations of the in put conditions?

Options:

A.

Use case based testing

B.

Decision table

C.

Boundary value analysis

D.

Equivalence class partitioning

Buy Now
Questions 77

A Test Manager conducts risk assessment for a project. One of the identified risks is: The sub-contractor may fail to meet his commitment". If this risk materializes. it will lead to delay in completion of testing required for the current cycle.

Which of the following sentences correctly describes the risk?

Options:

A.

It is a product risk since any risk associated with development timeline is a product risk.

B.

It is no longer a risk for the Test Manager since an independent party (the sub-contractor) is now managing it

C.

It is a object risk since successful completion of the object depends on successful and timely completion of the tests

D.

It is a product risk since default on part of the sub-contractor may lead to delay in release of the product

Buy Now
Questions 78

Which of the following statements is TRUE?

Options:

A.

User acceptance tests are usually automated and aim to verify the acceptance criteria for user stories

B.

Acceptance criteria for user stories can include details on data definitions, for example by describing the format, allowed values, and default values for a data item

C.

Acceptance criteria for user stones should focus on positive scenarios, while negative scenarios should be excluded

D.

Tests derived from acceptance criteria for user stories are not included in any of the four testing quadrants

Buy Now
Questions 79

Which of the following is a key characteristic of informal reviews?

Options:

A.

Kick-off meeting

B.

Low cost

C.

Individual preparation

D.

Metrics analysis

Buy Now
Questions 80

Which of the following is an example of tasks most associated with the test design activity?

Options:

A.

The project manager updates the project schedule as key test tasks are completed

B.

Test data, derived from production data, is loaded into the test environment

C.

Every day. the tester notes the status of his/her test cases in preparation for daily reports

D.

The identification of test execution and test automation tools

Buy Now
Questions 81

Following a risk-based testing approach you have designed 10 tests to cover a product risk with a high-risk level. You want to estimate, adopting the three-point test estimation technique, the test effort required to reduce the risk level to zero by executing those 10 tests. You made the following three initial estimates:

• most optimistic = 6 person hours

• most likely = 30 person hours

• most pessimistic = 54 person hours

Based only on the given information, which of the following answers about the three-point test estimation technique applied to this problem is true?

Options:

A.

The final estimate is between 22 person hours and 38 person hours

B.

The final estimate is exactly 30 person hours because the technique uses the initial most likely estimate as the final estimate

C.

The final estimate is between 6 person hours and 54 person hours

D.

The final estimate is exactly 30 person hours because the technique uses the arithmetic mean of the three initial estimates as the final estimate

Buy Now
Questions 82

Which of the following statements about TDD, BDD and ATDD is TRUE?

Options:

A.

Refactonng is a practice that is an integral part of TDD and is applied both to tests and to code wntten to satisfy those tests.

B.

ATDD is a black-box test design technique that is applicable exclusively at acceptance test level.

C.

BDD is a developer practice where business stakeholders are not usually involved as the tests are directly written at unit/component test level.

D.

ATDD is the practice of running the automated acceptance tests as part of a continuous integration process.

Buy Now
Questions 83

To be able to define testable acceptance criteria, specific topics need to be addressed. In the table below are the topics matched to an incorrect description. Match the topics (the left column) with the correct description (the right column)

TopicDescription

Options:

A.

How the system performs the specific behaviour.

8: Quality characteristicsB: A sequence of actions between an external actor and the system, to accomplish a specific goal or business task.

B.

ScenariosC: The externally observable behaviour with user actions as input operating under certain configurations.

C.

Business rulesD; Description of the connections between the system to be developed and the outside world.

D.

External interfacesE: Activities that can only be performed in the system under certain conditions defined by outside procedures and constraints.

E.

A to C, B to A, C to B. D to E and E to D

F.

A to E, B to A, C to B, D to C and E to D

G.

A to C, B to A, C to B, D to D and E to E

Buy Now
Questions 84

A bank software has a feature of locking down accounts that have and overdraft higher than $10,000.

Due to a bug in the code, the system locks down accounts once they reached $1000 overdraft.

Based on this context, which of the following is correct statement

Options:

A.

It is an example of a defect that it goes undetected, will cause harm to the end customer and to the company (the bank)

B.

It is an example of a defect, that if goes undetected, will cause harm to the end customer but not to the company (the bank)

C.

It is an example of a defect that if goes undetected, will not cause harm to the end customer, but will cause harm to the company (the bank)

D.

It is an example of a defect that if goes undetected, will not cause any real harm to either the end customer or to the company (the bank)

Buy Now
Questions 85

Which of the following issues cannot be identified by static analysis tools?

Options:

A.

Very low MTBF (Mean Time Between failure)

B.

Potentially endless loops

C.

Referencing a variable with an undefined value

D.

Security vulnerabilities

Buy Now
Questions 86

A requirement specifies that if the total amount of sales (TAS) made during the year by a corporate seller is 300,000€ or more, the bonus that must be paid to the seller is 100% of a certain amount agreed upon at the beginning of the year. The software contains a fault as it implements this requirement with the decision "IF (TAS = 300,000)" instead of "IF (TAS >= 300.000)". The application of the 3-value boundary value analysis to this problem consists of the following three test cases (TAS is an integer variable):

TC1 = 299,999 TC2=300,000 TC=300,001

Which of the following statements is TRUE?

Options:

A.

TC1 would highlight the fault

B.

TC2 would highlight the fault

C.

TC3 would highlight the fault

D.

None of the three test cases would highlight the fault.

Buy Now
Questions 87

What is 'Component Testing'?

Options:

A.

Integration Testing

B.

Functional testing

C.

Experience-based testing

D.

A test level

Buy Now
Questions 88

A test manager has started a cycle of testing for an e-commerce application. The reason for testing is the change in the protocol for connecting to the payment gateway because of new regulations. Which of the following correctly names this type of testing?

Options:

A.

Beta testing

B.

Maintenance testing

C.

System integration testing

D.

Retirement testing

Buy Now
Questions 89

Which of the following characterizations applies to a test tool used for the analysis of a developer's code prior to its execution?

Options:

A.

Tool support for test design and implementation.

B.

Tool support for static testing.

C.

Tool support for test execution and logging.

D.

Tool support for performance measurement and dynamic analysis.

Buy Now
Questions 90

A test engineer finds a defect while testing. After the developer has fixed the defect, the test engineer decides to re-run a complete section of the tests. Which of the following is correct?

Options:

A.

The lest engineer should not re-run the tests, as they have already been run, and results recorded.

B.

The test engineer should not re-run the tests, they should be part of the developer tests.

C.

The test engineer should re-run the tests, in order to ensure that new defects have not been introduced by the fix.

D.

The test engineer should re-run the tests, because the defect shows that the test cases need to be updated.

Buy Now
Questions 91

How can testing contribute to higher quality?

Options:

A.

Testing help to measure the quality of software.

B.

Testing ensures that remaining defects are documented.

C.

Testing removes errors in the software.

D.

Testing eliminates the risk with software.

Buy Now
Questions 92

A possible risk of introducing test automation is:

Options:

A.

the tool may not be fit-for-purpose.

B.

the tool may create additional development dependencies.

C.

the tool may not be compatible with the development platform.

D.

the tool will be owned and maintained by developers and replace testers.

Buy Now
Questions 93

In branch testing, what is the significance of a conditional branch in a software program?

Options:

A.

It indicates a decision point where the program can follow different paths based on specific conditions.

B.

It marks a point where the program's execution will terminate bringing the program to a halt.

C.

It represents a programming error and therefore a conditional branch should be avoided

D.

It signifies a comment or documentation within the code and it doesn't indicate a defect.

Buy Now
Questions 94

Decision table testing is being performed on transactions in a bank’s ATM (Automated Teller Machine) system. Two test cases have already been generated for rules 1 and 4. which are shown below:

ISTQB-CTFL Question 94

Which two of the additional test cases would achieve full coverage of the full decision table (when combined with the test cases that have already been generated for rules 1 and 4)?

Options:

A.

DT1, DT4

B.

DT3, DT4

C.

DT2, DT3

D.

DT1.DT2

Buy Now
Questions 95

Which ONE of the following options BEST describes Behavior-Driven Development (BDD)?

Options:

A.

Expresses the desired behavior of an application with test cases written in a simple form of natural language that is easy to understand by stakeholders—usually using the Given/When/Then format. Test cases are then automatically translated into executable tests.

B.

Defines test cases at a low level, close to the implementation, using unit test frameworks.

C.

Is primarily focused on non-functional testing techniques to ensure system reliability and performance.

D.

Requires testing to be performed after development is completed to validate software functionality.

Buy Now
Questions 96

Which one of the following statements correctly describes the term 'debugging'?

Options:

A.

There is no difference between debugging and testing.

B.

Debugging is a confirmation activity that checks whether fixes resolved defects.

C.

Debugging is the development activity that finds, analyses and fixes defects.

D.

Debugging is of no relevance in Agile development.

Buy Now
Questions 97

A test status report SHOULD:

Options:

A.

Specify the impediments to carrying out the planned test activities in the reporting period and the corresponding solutions put in place to remove them

B.

Be produced as part of test completion activities and report unmitigated product risks to support the decision whether or not to release the product

C.

Always be based on the same template within an organisation, as its structure and contents should not be affected by the audience to which the report is presented.

D.

Specify the lines of communication between testing, other lifecycle activities, and within the organisation that were chosen at the outset of the test project.

Buy Now
Questions 98

Which of the following options cover the test types performed during typical system testing phase:

I. Usability

II Requirements based scenarios

III Testing parts of the code in isolation

IV Correct order of parameters in API calls

Options:

A.

I, Ill

B.

I. II

C.

II. IV

D.

III. IV

Buy Now
Questions 99

Which of the following examples represents System Integration testing?

Options:

A.

Testing an application m development environment which is similar to the production environment

B.

Testing the system based on specifications using simulator for a sub-system

C.

Testing an application's behaviour to check if it fulfils business needs

D.

Testing if e-commerce website works correctly with a third-party payment gateway

Buy Now
Questions 100

Consider the following iteration planning tasks where a tester can provide value:

    Break down user stories into tasks (particularly testing tasks)

    Estimate test effort for all testing tasks

    Identify and refine functional and non-functional aspects of the test object

Which ONE of the following tasks should be ADDED to the above list?

Options:

A.

Determining the test strategy

B.

Participating in the detailed risk analysis of user stories and determining their testability

C.

Planning the testing for the release

D.

Writing testable user stories and acceptance criteria

Buy Now
Questions 101

For the same financial institution in Question 12, with the same requirements and expectations, what would be the most likely investment values used in testing if two-point boundary value analysis is used to design test cases specific to the 13% interest rate equivalence partition?

Options:

A.

R100 000, R100 001, R500 000, R500 001.

B.

R99 999, R100 000, R499 999, R500 000.

C.

R100 000. R500 000.

D.

R99 000, R500 001.

Buy Now
Questions 102

Which of the following definitions is NOT true?

Options:

A.

Test data preparation tools fill databases, create files or data transmissions to set up test data to be used during the execution of tests.

B.

Test execution tools execute test objects using automated test scripts.

C.

Test Management tools monitor and report on how a system behaves during the testing activities.

D.

Test comparators determine differences between files, databases or test results.

Buy Now
Questions 103

Which of the following is a CORRECT statement about how a tester should communicate about defects, test results, and other test information?

Options:

A.

Testers should include personal opinions and judgements in defect reports and review findings

B.

Testers should emphasize the benefits of testing, such as increased quality and reduced risk

C.

Testers should reject all questions about their test findings and information

D.

Testers should take a command-and-control approach with the project team

Buy Now
Questions 104

Which of the following statements about testware are correct?

I When closing the test activities, all the testware resources can be uninstalled and released

II All the testware should be subject to Configuration Management

III. The testware. at the end of the project, should be transferred to the organization responsible for maintenance

IV The developers are responsible for the correct installation of the testware

Options:

A.

II, Ill

B.

I, Ill

C.

I, IV

D.

II, IV

Buy Now
Questions 105

Which of the following BEST distinguishes the terms "validation" and "verification"?

Options:

A.

Verification is confirmation through the provision of objective evidence that the specified requirements have been met while validation is confirmation through the provision of objective evidence that the requirements for a specific intended use have been met

B.

Verification is confirmation through the provision of subjective evidence that the specified requirements have been met while validation is confirmation through the provision of subjective evidence that the designs for a specific intended use have been met

C.

Validation is confirmation through the provision of objective evidence that the specified requirements have been met while verification is confirmation through the provision of objective evidence that the requirements for a specific intended use have been met

D.

Validation is confirmation through the provision of subjective evidence that the specified requirements have been met while verification is confirmation through the provision of subjective evidence that the designs for a specific intended use have been met

Buy Now
Questions 106

Which of the following statements about re-testing and regression testing are TRUE?

I Re-testing should be performed after a defect is fixed.

II Regression testing should always be performed after a defect is fixed.

III. Re-testing and regression testing may be performed at any test level.

IV Regression testing may include functional, non-functional and structural testing.

V. Re-testing should be included in the debugging activity.

Options:

A.

I, III. Iv

B.

II, v

C.

I, Ill

D.

II. IV, V

Buy Now
Questions 107

A software development company invests heavily in tools to support the entire software development lifecycle, including testing. They have a tool that allows automated creation and installation of builds and subsequent execution of various types of automated tests. Which ONE of the following is a CORRECT statement about this type of test tool?

Options:

A.

It is an example of collaboration tool

B.

It is an example of test implementation tool

C.

It is an example of DevOps related tools

D.

It is an example of automated unit testing tool

Buy Now
Questions 108

A test manager defined the following test levels in her test plan; Component, System and Acceptance.

Which Software Development lifecycle is the Test Manager most likely following?

Options:

A.

V-Model

B.

Agile

C.

Waterfall

D.

Prototyping

Buy Now
Exam Code: ISTQB-CTFL
Exam Name: ISTQB Certified Tester Foundation Level (CTFL v4.0)
Last Update: Oct 4, 2025
Questions: 399

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now ISTQB-CTFL testing engine

PDF (Q&A)

$31.5  $104.99
buy now ISTQB-CTFL pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 04 Oct 2025