Summer Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpm65

PDD ARE 5.0 Project Development and Documentation Exam Questions and Answers

Questions 4

A significant advantage of glass-fiber-reinforced concrete panels over architectural precast concrete panels is which one of the following?

Options:

A.

Increased strength

B.

Increased quality control

C.

Decreased weight

D.

Decreased fabrication time

Buy Now
Questions 5

In winter conditions, when the outdoor air is below freezing and the indoor humidity is maintained at 40 percent relative humidity for 24 hours a day, ice forms on the exterior surface of the stone facing.

Which of the following elements is missing from the building wall section?

Options:

A.

Vapor barrier

B.

Wall insulation

C.

Air space

D.

Rain screen

Buy Now
Questions 6

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

PDD Question 6

The owner is concerned about elevated noise levels in the Tap Room when fully occupied. The current design utilizes a 2 x 2 acoustic ceiling tile system installed above the fans. An acoustical engineer recommends noise mitigation through limiting reverberation time (RT) to 2.0 seconds or less in the space. This can be achieved by the provided ceiling material options and their corresponding area.

What should the architect recommend that will minimize additional project costs while providing the recommended acoustical solution?

Options:

A.

Retain current ceiling cloud layout and a 2 x 2 acoustic ceiling tile system but remove the fans.

B.

Revise design using only one ceiling cloud and cementitious wood fiber panel system (1" in thickness).

C.

Revise design using only one ceiling cloud and cementitious wood fiber panel system (2" in thickness).

D.

Retain current ceiling cloud layout and a 2 x 2 acoustic ceiling tile system and add acoustical sound board above.

Buy Now
Questions 7

Which document is the most appropriate location for specifying the finish material for casework?

Options:

A.

Construction Drawings

B.

Outline Specifications

C.

Project Manual – Division 06

D.

General Conditions

Buy Now
Questions 8

Where is the proper place to put a vapor barrier in a cold climate?

Options:

A.

On the exterior between the metal siding and the sheathing

B.

On the exterior between the framing and the sheathing

C.

On the interior between the gypsum wallboard and the framing

D.

In the cavity of the framing space

Buy Now
Questions 9

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

PDD Question 9

Refer to the exhibit.

Which hardware set should be specified for door number 27?

Options:

A.

Hardware set 1.0

B.

Hardware set 2.0

C.

Hardware set 3.0

D.

Hardware set 4.0

Buy Now
Questions 10

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

The owner requests that the metal panel skin be changed to EIFS.

Which of the following architectural sheets require changes to the notes and/or details? Check the three that apply.

Options:

A.

A-00

B.

A-02

C.

A-03

D.

A-04

E.

A-06

F.

A-07

Buy Now
Questions 11

PDD Question 11

Refer to the exhibit.

Which of the following examples of wood paneling depicts the method of "slip matching" between adjacent wood veneers?

Options:

A.

A

B.

B

C.

C

D.

D

Buy Now
Questions 12

Which of the following metals is best suited for embedments in concrete or masonry?

Options:

A.

Stainless steel

B.

Bronze

C.

Aluminum

D.

Cast iron

Buy Now
Questions 13

PDD Question 13

PDD Question 13

An architect is designing a school building that features a flat roof with a low parapet wall in a wet climate region. The client wants to minimize maintenance requirements and focus on keeping water from the walls.

What parapet coping detail would be most appropriate for the architect to select for this project?

Options:

A.

A

B.

B

C.

C

Buy Now
Questions 14

PDD Question 14

Refer to the exhibit.

What is the horizontal member indicated by the arrow in the wall-floor assembly?

Options:

A.

Fire block

B.

Girt

C.

Lateral shear plate

D.

Ledger

Buy Now
Questions 15

PDD Question 15

Refer to the exhibit.

An architect is working on an airport lounge project. The 9,000 SF floor plan includes an open, double-height space. Due to area limitations, all program requirements cannot fit within the 9,000 SF floor plan. A mezzanine level with one exit is being proposed to solve this programming constraint. There are adequate exits available on the main floor plan to pick up the additional occupant load from the mezzanine.

Which method of mezzanine construction should the architect design?

Options:

A.

2,500 SF open lounge area for 20 people

B.

2,750 SF enclosed business center for 15 people

C.

3,250 SF open dining area for 30 people

Buy Now
Questions 16

An architect is designing a sub-surface drainage system that outfalls into a site retention pond. The recommended shape, size, and slope of the drainage lines need to be determined for primarily which of the following purposes?

Options:

A.

To minimize the desired flow

B.

To maximize the desired flow

C.

To obtain the desired velocity

D.

To increase the desired velocity

Buy Now
Questions 17

PDD Question 17

Refer to the exhibit.

What is an accurate description of the air distribution system shown?

Options:

A.

Ducted supply and return air is utilized.

B.

Supply air is delivered at a low velocity.

C.

The system is inefficient in summer months.

D.

The system prohibits individual comfort control.

Buy Now
Questions 18

During plan review of an office building, the reviewer informs the architect of new regulations that require storage rooms greater than 150 sf be 1-hour fire rated. The proposed design has three 200 sf storage rooms that must meet the fire protection requirements. The architect needs to recommend how to meet this requirement with minimal effect on cost, time, and program.

Options:

A.

Construct storage rooms using rated concrete masonry.

B.

Construct storage rooms using metal studs and Type X gypsum board.

C.

Make four 150 sf storage rooms and redistribute throughout the building.

D.

Make six 100 sf storage rooms and redistribute throughout the building.

Buy Now
Questions 19

Specifications and details for repointing deteriorated masonry joints in historic soft-brick buildings should result in which one of the following?

Options:

A.

The duplication of original mortar strength

B.

An increased mortar strength over the original mortar

C.

A bond between the existing masonry and the new mortar that is stronger than the brick

D.

Deeper joint profiles

Buy Now
Questions 20

What is the primary purpose of shop drawings?

Options:

A.

Define design intent

B.

Replace construction drawings

C.

Document record drawings

D.

Illustrate fabrication and installation methods

Buy Now
Questions 21

Which of the following must be considered in the proper selection of thermal insulation and moisture control assemblies for a building? (Check all that apply)

Options:

A.

Interior climate of the space

B.

Exterior climate of the building location

C.

Type of HVAC system to be used

D.

Thermal resistance properties of the materials

E.

Orientation of the building

F.

Compatibility of the materials with adjacent materials

Buy Now
Questions 22

PDD Question 22

Refer to the exhibit.

An architect reviews the construction manager's construction estimate for a typical precast wall system with aluminum storefront windows.

Click on the component in the axonometric detail that is missing from the system estimate.

PDD Question 22

Options:

Buy Now
Questions 23

PDD Question 23

Refer to the exhibit.

What is the purpose of the flexible connection in the fan coil shown?

Options:

A.

To provide a field point of connection of the ductwork to the fan coil unit

B.

To insulate against heat transfer from the fan coil unit

C.

To minimize sound transfer

D.

To transition from the fan coil unit flange to the desired duct size

Buy Now
Questions 24

Which of the following siding types should only be applied vertically?

Options:

A.

Plain bevel

B.

V-shiplap

C.

V-groove tongue and groove

D.

Board and batten

Buy Now
Questions 25

An architect is rehabilitating a historic federal landmark that requires repairs to a garden wall. The existing brick appears to be in good condition; the mortar shows significant signs of deterioration.

Which strategy should the architect propose to repair the damaged wall?

Options:

A.

Carefully remove all mortar and repoint all joints to achieve a uniform appearance.

B.

Completely remove deteriorated mortar with electric saws prior to repointing.

C.

Remove loose mortar by hand raking the joints prior to repointing.

Buy Now
Questions 26

PDD Question 26

Refer to the exhibit.

For a plywood panel carrying the grade stamp shown, which of the following is the maximum recommended span for use in a floor system?

Options:

A.

15 in

B.

16 in

C.

32 in

D.

108 in

Buy Now
Questions 27

A project located in a rural area without municipal sewer access will most likely require:

Options:

A.

Grease interceptor

B.

Septic tank and leach field

C.

Ejector pump

D.

Oil-water separator

Buy Now
Questions 28

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

The owner has revised the pro forma and directed the architect to add two additional Type B units to the design. A code review for the project indicates that the building occupancy is R-2.

What should the architect do to meet the owner's required revisions?

Options:

A.

Change the 2nd Floor Unit 1BR-SW into two studios and change the 10th Floor Unit 2BR-E to two 1-bedroom units.

B.

Change the 10th Floor Unit 2BR-E to two 1-bedroom units and change the 7th Floor Unit 2BR-E to two 1-bedroom units.

C.

Change the 5th Floor Unit 2BR-E to two 1-bedroom units and change the 2nd Floor Laundry to a 1-bedroom unit.

Buy Now
Questions 29

The design of a 10-story residential building features a curtain wall system on all four elevations. Due to diurnal temperature swings in the area, the curtain wall will need a thermal break to prevent the transfer of heat into the building.

Click on the thermal break in the pressure-plate mullion detail.

PDD Question 29

Options:

Buy Now
Questions 30

PDD Question 30

Refer to the exhibit.

For which of the following connections could diagonal bracing be eliminated?

Options:

A.

A

B.

B

C.

C

D.

D

Buy Now
Exam Code: PDD
Exam Name: ARE 5.0 Project Development and Documentation Exam
Last Update: Aug 14, 2025
Questions: 100

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now PDD testing engine

PDF (Q&A)

$36.75  $104.99
buy now PDD pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 15 Aug 2025