Pre-Summer Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Questions 4

As time goes by, there is an increase in Customer Services staff asking questions about how their skills development will be supported under the new structure and how they will influence decisions about the projects they will be assigned to work on.

Which is the MOST appropriate response from the Customer Service Director?

Options:

A.

Prepare presentations to all staff outlining the targets for the new structure.

B.

Support line leadership roles on how to include those asking the questions.

C.

Ask for the communications from the change teams to include the questions.

D.

Define the approach and governance for the Customer Services projects.

Buy Now
Questions 5

Which statement should be recorded under the Lessons from previous change initiatives heading?

Options:

A.

UniCo has always been seen in the marketplace as being traditional and cautious.

B.

UniCo has always successfully used customer journey mapping for educating staff in customer needs.

C.

A new software development platform is needed to integrate the new services into operational processes.

D.

The renewal of the lease for the office housing Selco staff is due in fifteen months’ time.

Buy Now
Questions 6

Using the additional information provided for this question in the

Scenario Booklet, answer the following question about using Kotter ' s

eight-processes cyclical model. This model is being used for planning

and leading the change required to rebrand and reposition UniCo in the

market place.

Lines 1 to 4 in the table below consist of an assertion statement and a reason

statement. For each line identify the appropriate option, from options A to E,

that applies. Each option can be used once, more than once or not at all.

AgilePM-Practitioner Question 6

AgilePM-Practitioner Question 6

AgilePM-Practitioner Question 6

Options:

Buy Now
Questions 7

The change management team is creating the change analytics strategy for the change programme.

Below is an extract of recipients, measures and source data that have been proposed.

Answer the following question about the sources of conflict in change

situations.

Column 1 is a list of statements about sources of conflict in change situations.

Column 2 contains the names of the eight sources of conflict identified by Art

Bell and Brett Hart. For each statement in Column 1, select from Column 2 the

source of conflict to which it MOST relates. Each selection from Column 2 can

be used once, more than once or not at all.

AgilePM-Practitioner Question 7

AgilePM-Practitioner Question 7

AgilePM-Practitioner Question 7

Options:

Buy Now
Questions 8

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Are the measures and source data to be monitored by the Human Resources and Facilities Manager likely to have any of the limitations of data analytics?

Options:

A.

No, because reporting on staff data should only be carried out by Human Resources.

B.

No, because internal processes are likely to ensure a good data quality.

C.

Yes, because the volume of the source data is likely to be unmanageable.

D.

Yes, because the source data is unlikely to provide ‘real-time’ accuracy.

Buy Now
Questions 9

The Change Manager has mapped stakeholders onto a Power-Interest

Matrix, with the aim of identifying suitable actions for managing these

stakeholders.

The mapping below shows the current assessment made by the Change Manager.

The ' Interest in your change ' axis indicates a combination of the

stakeholders ' levels of active engagement and their buy-in for the Change

Programme.

AgilePM-Practitioner Question 9

Using the Scenario and the additional information provided for this question in the Scenario Booklet, answer the

following question about Stakeholder mapping and strategy.

Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each line identify the

appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

AgilePM-Practitioner Question 9

AgilePM-Practitioner Question 9

AgilePM-Practitioner Question 9

Options:

Buy Now
Questions 10

The Customer Services Director has announced the new structure at a large presentation for all Customer Services staff. The scale and design of the change have surprised many of the staff.

In the weeks immediately following the Customer Services Director’s initial presentation, there have been rumors of the Help Desk staff talking unhappily in small groups, with blame directed at " the management " for a recent period of poor performance of the department.

Which approach is the MOST appropriate way for the Customer Services Director to create early involvement in the change?

Options:

A.

Target those staff in the Help Desk who are change-averse so that they are the first ones involved in the program.

B.

Delay communications a few weeks so that all staff have time to think for themselves about the benefits of the new structure.

C.

Identify those staff who would be willing to trial new Help Desk processes and work on pilots in the department.

D.

Encourage the Help Desk staff to begin setting goals for themselves under the new structure.

Buy Now
Questions 11

Which 2 actions demonstrate connectivity?

Options:

A.

Arrange a number of briefing sessions for Customer Services staff, over lunch times and in a comfortable setting.

B.

Make short videos available showing how customer service teams from other companies effectively provide services for these types of offerings.

C.

Create a central area on the UniCo internal shared work system for the Change Programme to collaborate and comment on the materials.

D.

Ask the senior leadership to provide examples of other companies undertaking, and successfully overcoming, similar challenges.

E.

Send the plans of the new office layout to the Selco staff showing them where each individual will be located.

Buy Now
Questions 12

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Which 2 statements BEST explain why the CEO is appropriate for the role of Sponsor for the Change Programme?

Options:

A.

Has a reserved, thoughtful leadership style which allows others to establish new behaviors without fear of criticism.

B.

Will provide an alternative view, due to a personal unease that the different direction for UniCo is outside the CEO’s own experience.

C.

Likes to be involved in the operational detail in order to have control of changes as they happen.

D.

Appreciates that expenditure has to happen promptly and assigns budget appropriately to support the change.

E.

Is committed to promoting this change as the future direction and has the authority to make it a priority.

Buy Now
Questions 13

Which 2 actions demonstrate empathy?

Options:

A.

Allow people to think independently and plan for themselves how this Change Programme could be incorporated.

B.

Hold a weekly progress meeting with key UniCo and Selco staff dedicated to the delivery of the new contract.

C.

Provide statistical data on the general trends in the mobile application industry to help people rationalize why this change is necessary.

D.

Reschedule plans to allow extra time for those IT support staff who are finding it difficult to try out the new processes.

E.

Encourage the CEO to discuss their previous concerns about the new company direction with staff who feel uncertain.

Buy Now
Questions 14

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 14

(It is appropriate that the Delivery Team Leaders attend this Project Sprint Planning Event?)

Options:

A.

Yes, because AgilePM mandates joint decision-making between leadership and Delivery Teams.

B.

Yes, because Team Leaders provide real-time insights on progress, risks, and dependencies.

C.

No, because Team Leaders should focus on development work, not planning meetings.

D.

No, because planning should be handled by project leaders, with Team Leaders informed later.

Buy Now
Questions 15

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 15

(Which of the following actions is NOT appropriate when using when using MoSCoW prioritization to manage business expectations related to the ' Hydrotherapy in Mineral-Rich Spring Pools ' Product Goal?)

Options:

A.

Ensure Product Backlog items are MoSCoW prioritized to align with business needs and expectations.

B.

Ensure that Product Backlog item prioritization reflects a balance between business value, technical feasibility, expectations, risk and dependencies.

C.

Review the prioritization of Product Backlog items periodically to maintain ongoing alignment of planned work with evolving business needs and project viability.

D.

Assume that all Must Have requirements and Should Have requirements in the Product Backlog will be delivered as they are part of the Business Case.

Buy Now
Questions 16

(Sukra Aroon wants to ensure alignment between the emerging Spa infrastructure and innovative spa treatments being developed.

Which approach effectively combines Agile Leadership with practical application?)

Options:

A.

Empower Team Leaders to resolve dependencies, escalating major issues to Sukra for a solution-wide view if needed.

B.

Empower Team Leaders to independently handle alignment through informal discussions, documenting key decisions for later review.

C.

Encourage Delivery Teams to define shared acceptance criteria for interdependent deliverables ensuring alignment on needs.

D.

Encourage Delivery Teams to define shared acceptance criteria for interdependent deliverables and Brinda approving.

E.

Hold a joint Retrospective after each Sprint to review alignment and identify remedial actions to ensure alignment.

F.

Hold a joint Retrospective after each Sprint so Team Leaders can share learning and provide feedback.

G.

Use hierarchical reporting where decisions would be documented collaboratively between Brinda Vyas, Mira Bachar, Hira and Sukra Aroon.

Buy Now
Questions 17

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 17

(A treatment plant intended to add chlorine to the natural, pristine, river-sourced mineral water has been proposed as a Must Have requirement for hygiene reasons.

Is this aligned with the business vision?)

Options:

A.

Yes, because water hygiene is critical and regulatory standards may require chlorination to ensure guest safety.

B.

Yes, because all spa pools must be treated with chlorine as alternative purification methods are not as effective.

C.

No, because adding chlorine conflicts with the Eco-Spa ' s commitment to a natural mineral experience, so alternatives hygiene methods should be explored.

D.

No, because hygiene concerns should be addressed post-launch if and when guests raise concerns.

Buy Now
Questions 18

During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,

controlled and evidenced.

Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

AgilePM-Practitioner Question 18

(During the meeting, Mira Bachar shared a query raised by Lee Tan. Lee has questioned how a business case can exist without a detailed understanding of exactly what will be delivered.

Which of the following is an appropriate explanation?)

Options:

A.

In AgilePM, the business case focuses on project goals and benefits, using MoSCoW to ensure value delivery within fixed time and cost. This provides flexibility while maintaining control over investment.

B.

The business case in AgilePM uses incremental funding, adjusting investments as project priorities evolve and allowing the project to remain adaptable while still providing financial predictability.

C.

AgilePM business cases are based on a fixed scope, detailed upfront analysis and estimates. This approach is structured to reduce uncertainty by ensuring all major deliverables are accounted for from the start.

D.

AgilePM maximizes output efficiency, delivering complete, goal-aligned value on an incremental basis.

Buy Now
Questions 19

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 19

(The Wellness Garden (a Should Have) is delayed. Sukra Aroon suggests a workaround, using the River Pool Patio instead, and classifying the Garden as a ' Won ' t Have this time ' .

Is this an appropriate suggestion?)

Options:

A.

Yes, because reclassifying the garden reduces risk while maintaining an outdoor option.

B.

Yes, because unresolved dependencies justify removing requirements to prevent disruption.

C.

No, because a Should Have requirement should NOT be removed unless it threatens the delivery of a Must Have.

D.

No, because workarounds reduce quality and undermine the business case.

Buy Now
Questions 20

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 20

(Hira decides to update the Delivery Plan to prioritize the delivery of the hydrotherapy facilities first for early testing.

Is this action appropriate?)

Options:

A.

Yes, because the Delivery Plan should adapt to real-world conditions.

B.

Yes, because all sequencing changes should be documented in the Delivery Plan.

C.

No, because the Delivery Plan is fixed after the Foundations phase unless a Must Have requirement is at risk.

D.

No, because sequencing should be a collaborative decision, not determined by Hira alone.

Buy Now
Questions 21

(Which 2 statements describe appropriate team behaviour for effective risk management?)

Options:

A.

Team members should adopt a collaborative mindset, sharing responsibility for identifying and mitigating risks.

B.

Hira should have sole responsibility for managing all risks with clear accountability.

C.

Developers should resolve all risks collaboratively and promptly without escalation.

D.

Sukra Aroon should handle all technical risks independently to ensure the solution is fit for purpose.

E.

Risk management should be proactive and part of daily activities, not a separate process.

Buy Now
Questions 22

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

AgilePM-Practitioner Question 22

(Sarah Lark asks Mira Bachar how Spa treatments will remain aligned with the demands of guests post-launch. Mira explained that the Operations Delivery Team will address this in the final Sprint.

Is this approach aligned with AgilePM?)

Options:

A.

Yes, because Delivery Teams should focus on delivery until the final Sprint.

B.

Yes, because realization planning can reasonably happen in the final Sprint.

C.

No, because realization is the Business Visionary ' s responsibility, NOT the Delivery Teams.

D.

No, because realization planning should be part of the business case before development starts.

Buy Now
Questions 23

(To keep Business Sponsor, Sarah, informed, Hira has set up a real-time dashboard displaying project progress, risks, and actions from planning events.

Will this meet Sarah ' s needs?)

Options:

A.

Yes, because she will have access to progress updates, removing all meeting dependency.

B.

Yes, because she can rely solely on the dashboard for all her updates.

C.

No, because dashboards lack the context and detail required for strategic decision-making.

D.

No, because she will need Hira to compile and present the data in a physical report for sharing.

Buy Now
Questions 24

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

' all members of the project understand and accept the DSDM approach ' .

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Buy Now
Questions 25

Answer the following questions about actions to be taken by different

roles.

The Business Sponsor has decided that the new coffee shop insurance

product website pages will include the financial transaction functionality to

support the end-to-end sales process. The Business Sponsor views this as a

valuable sales tool, enabling customers to pay for insurance policies online. If

successful, this new financial transaction functionality is to be made available

across all other insurance products. This is a new Must Have requirement.

All parties are to be invited to a workshop to discuss the additional work

required to deliver the required solution including the new Must Have

requirement. The areas to be discussed include specialist skills required and

possible legal, financial and technical standards to be adhered to.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 actions should the Business Sponsor take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Check the viability of the project, following the inclusion of the new Must

Have requirement.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

E.

Assess the impact of the new Must Have requirement on the original

Business Case.

Buy Now
Questions 26

(New food hygiene laws take effect in six months. Sukra Aroon and Wanida Anong are assessing if kitchen remodeling is needed, which may divert Infrastructure Team resources.)

Options:

A.

Approach-based, because past Project Increment planning failed to account for regulatory change, causing lack of contingency and resource risks.

B.

Approach-based, because Sukra Aroon should have tracked evolving legislation from the start to mitigate the risk.

C.

VUCA-based, because new legislation is an external factor requiring adaptability to respond to unplanned demands.

D.

VUCA-based, because gaps in internal compliance cause uncertainty in responding to changing regulations.

Buy Now
Questions 27

(Three months after launch, Mira Bachar informs Brinda Vyas that Spa usage has fallen below expectations. Guest feedback reveals that many were simply unaware that Spa experiences were available.)

Options:

A.

Approach-based, because realization planning should have included guest communication to effectively communicate the Spa experiences on offer.

B.

Approach-based, because marketing and operations should have collaborated during the Foundations phase to ensure Spa experiences were promoted.

C.

VUCA-based, because guest demographics or preferences change unpredictably making it difficult to predict engagement.

D.

VUCA-based because external uncertainty affects how guests discover new services making it difficult to control.

Buy Now
Questions 28

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Buy Now
Questions 29

Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?

Options:

A.

Try to secure formal agreement as to how many hours per week the

marketing assistants will spend on the project.

B.

Accept that members of the Solution Development Team will be

inconsistent.

C.

Make each Timebox as long as possible to ensure the marketing

assistants have enough time to complete any work allocated to them

within the boundaries of the Timebox.

D.

Schedule the two marketing assistants to work at different times so they

can hand matters over to one another.

Buy Now
Questions 30

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.

D.

Source and hire a web developer with experience in developing online

financial transaction functionality.

E.

Consolidate and circulate an agenda for the workshop.

Buy Now
Questions 31

Answer the following questions about the contents of the DSDM

products.

Each of the following questions includes true statements about the project

but only two statements are appropriate entries for the DSDM product

identified.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 statements represent appropriate entries for the Business Case?

Options:

A.

A list of high-level functional and non-functional requirements that the

project should meet written as User Stories.

B.

Coffee shops that sell Fairtrade products and alcohol from local breweries

out perform other coffee shops in the market.

C.

The Sales Manager has been asked to produce a report within the next

two days showing the number of generic insurance policies sold to coffee

shops over the past three years.

D.

The Sales Manager has calculated that the new coffee shop insurance

product will increase revenues by 10% each week.

E.

Market research shows that the number of coffee shop patrons taking

legal action against retailers has increased by 200% over the past two

years.

Buy Now
Questions 32

Which 2 actions should the Technical Coordinator take to implement the new

Must Have requirement?

Options:

A.

Ensure that the latest version of the website design in the Solution

Architecture Definition is provided to all members of the Solution

Development Team.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

D.

Consolidate and circulate an agenda for the workshop.

E.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

Buy Now
Questions 33

Which 2 actions should the Team Leader take to implement the new Must

Have requirement?

Options:

A.

Consolidate and circulate an agenda for the workshop.

B.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

C.

Discuss the development interfaces and dependencies with the Solution

Development Team to ensure the associated Timebox is appropriate.

D.

Agree to de-scope Should Have and/or Could Have requirements to allow

for the new Must Have functionality.

E.

Source and hire a web developer with experience in developing online

financial transaction functionality.

Buy Now
Questions 34

Which 2 actions should the Workshop Facilitator take to implement the new

Must Have requirement?

Options:

A.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

B.

Consolidate and circulate an agenda for the workshop.

C.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

D.

Assess the impact of the additional development costs on the original

Business Case.

E.

Encourage all parties to contribute, irrespective of their views.

Buy Now
Questions 35

The Web Content Manager has provided the Web Developer with a mock up

of the ' Contact Us ' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads ' Delete ' instead of ' Cancel ' .

What action should the Web Content Manager take?

Options:

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Buy Now
Questions 36

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?

Options:

A.

Refuse to discuss any detailed requirements in the early phases.

B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.

C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.

D.

Capture the Marketing Director ' s requirements in detail but leave the

input of others until later in the project.

Buy Now
Questions 37

(At a Sprint Review, Brinda Vyas realized that guest luxury has been prioritized over sustainability, creating misalignment with the project vision.)

Options:

A.

Approach-based, because Brinda Vyas ' expectations should be clearly communicated, captured and clarified in the Foundations phase.

B.

Approach-based, because the Delivery Team should have continuously validated assumptions about Brinda Vyas ' expectations.

C.

VUCA-based, because customer expectations change in dynamic and unpredictable environments.

D.

VUCA-based, because Agile embraces change, so deviations are normal.

Buy Now
Questions 38

(Hira is considering splitting the Developers into two Delivery Teams: one focused on Spa infrastructure and the other on guest experience. Mira Bachar, the Guest Services Manager, will be the Product Owner for both teams.

AgilePM-Practitioner Question 38

Which one of the following statements support Hira ' s proposed Delivery Team structure?)

Options:

A.

The Guest Experience team can dictate the Infrastructure team priorities, ensuring guest satisfaction.

B.

Each Delivery Team can work independently, delivering valuable increments without needing to coordinate with the other.

C.

Each Delivery Team can refine their own practices without unnecessary distractions from other skill sets.

D.

Collaboration within specialized teams improves communication and commitment to goals.

Buy Now
Questions 39

The Applications Manager, who is already very busy, is proposed as a Change Agent.

Which action by the Change Manager is MOST likely to make this department ' s change agent role effective?

Options:

A.

Provide an anonymous complaints system for use if the team cannot raise concerns directly.

B.

Appoint a junior team member as change agent with the Applications Manager as support ' buddy. '

C.

Train the Application Manager in time management techniques and approaches.

D.

Publish the timetable of the Operational delivery process workstream objectives to staff.

Buy Now
Questions 40

Answer the following questions about using facilitation of a workshop to co-

design organizational change.

When facilitating a workshop to design a process, which recommendation is MOST likely to create a good solution?

Options:

A.

The focus should be on immediate action to reduce the organizational costs.

B.

The workshop should be held off-site to create independent thought.

C.

The participants should cover all elements of the process and its implementation.

D.

Only the senior decision-makers should attend to ensure implementation is viable.

Buy Now
Questions 41

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.

On seeing plans for the office move, the Selco staff are worried that some desk allocations do not have access to natural light. The relocation leadership team held a workshop as soon as the issue was raised and has allocated these desks to be ‘hot-desks,’ not used by staff permanently based in the office.

Is this an appropriate approach to reward the brain in the need for ‘certainty,’ and why?

Options:

A.

No, because a change solution needs to be permanent to achieve ‘certainty.’

B.

No, because the resolution of the issue should be delegated to those affected.

C.

Yes, because loss of ‘certainty’ mostly affects those at lower organizational levels.

D.

Yes, because ‘certainty’ is rewarded when issues can be resolved promptly and openly.

Buy Now
Questions 42

Which Facilities stakeholder is MOST likely to be placed within the ‘external’ segment for the relocation work of the Operational delivery processes workstream?

Options:

A.

The staff who have coordinated the user input on the layout and will be working with the designers to make amendments according to feedback.

B.

The UniCo security staff who will arrange the necessary physical accesses for the staff to gain entry to the new building.

C.

The staff who will be communicating the timetable of activities to integrate Selco staff within the UniCo building.

D.

The staff who have been contracted to move furniture and equipment within agreed timescales.

Buy Now
Questions 43

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying

controls to the end of Development Timebox C.

What action should the Project Manager take when considering the End of Timebox Review?

Options:

A.

Encourage the Marketing Director to attend the End of Timebox Review.

B.

Attend the next Daily Stand-up to raise an issue about the windows.

C.

Prepare a summary of progress against plan, for presentation at the review.

D.

Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.

Buy Now
Questions 44

The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to

simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was

potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a

customer financial transaction.

Answer the following question about the actions to be taken by each role.

Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system. Column 2 lists the key roles. For each action in Column 1,

select from Column 2 the role that should carry out the action.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1

    Advise how the legislation on the transfer of data will affect the requirements

and the system.

    Agree the changes needed to the corporate technical architecture with the

Architecture Angels IT support team.

    Ensure the information security vulnerability is communicated to the AA Head

Office IT Director.

    Evaluate the impact of proposed security controls on the business and decide

on the most suitable solution.

    Reprioritise the requirements on the Prioritised Requirements List associated

with the security issue.

Column 2

    Project Manager

    Business Sponsor

    Business Visionary

    Technical Coordinator

    Business Analyst

    Team Leader

    Business Ambassador

    Solution Developer

AgilePM-Practitioner Question 44

AgilePM-Practitioner Question 44

Options:

Buy Now
Questions 45

What action should the Project Manager take during the Close-Out of Timebox C?

Options:

A.

Remove ' Aspects ' from the supplier list for all future projects.

B.

Carry out final checks to ensure the deliverables of Timebox C meet the expected standards.

C.

Ensure that lessons are learned so that similar issues do not occur in future Timeboxes.

D.

Initiate the work required to complete the windows to the required standard.

Buy Now
Questions 46

Which 2 statements explain why the Timber Tigers ' Site Manager would be an appropriate Solution Developer?

Options:

A.

Accustomed to bringing in contract staff for short periods of time.

B.

Closely manages the building team so that they consistently produce high-quality work.

C.

Is able to represent the team in all daily meetings.

D.

An experienced builder who is good at turning a brief into a practical design.

E.

Is empowered by Timber Tigers ' management to make decisions on the building work.

Buy Now
Questions 47

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are

four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and

to know who should be where. Some of the contractors have started to turn up late to the site.

Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The

Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.

Answer the following questions about motivating the contractor teams according to Agile Project Management.

How should the Project Manager encourage the resources to operate more successfully?

Options:

A.

Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.

B.

Hold a separate Daily Stand-up meeting for contractors only.

C.

Provide a detailed plan of activity for each contractor team.

D.

Schedule the electrical and plumbing teams so that they work on different Timeboxes.

Buy Now
Questions 48

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

At the beginning of Solution Development Timebox A, the Timebox is being

planned in detail. Although Foundations was conducted at a high level, the

Prioritised Requirements List was baselined. Now the Solution Development

Team is setting detailed acceptance criteria against each requirement.

Is this an appropriate approach to setting detailed acceptance criteria?

Options:

A.

Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.

B.

Yes, because the Solution Development Team members will be setting acceptance criteria for the first time during Solution Development Timebox A.

C.

No, because the Solution Development Team should NOT be involved in setting acceptance criteria.

D.

No, because acceptance criteria should be set in detail against each requirement during Foundations.

Buy Now
Questions 49

Each of the following questions includes a list of true statements about individuals from Architecture Angels and Timber Tigers who have been appointed to the

project team. Only 2 statements explain why, in the context of an Agile team, the individual is a suitable candidate for that role.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements explain why the Architecture Angels ' Finance Director would be an appropriate Business Sponsor?

Options:

A.

Is able to delegate most of the required involvement to the Chief Accountant.

B.

Has been friends with the Architecture Angels ' Chief Executive since school.

C.

Is the project budget holder.

D.

Is concerned about preventing the costs of refurbishment from escalating and affecting the operations of the company.

E.

Will not distract the Solution Development Team, as is usually too busy to be involved.

Buy Now
Questions 50

Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do not

happen again.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Deliver on time.

C.

Build incrementally from firm foundations.

D.

Demonstrate control.

Buy Now
Questions 51

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

Options:

A.

Marketing Director, in the role of Business Visionary.

B.

Team Leader.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels ' Senior Management Team.

Buy Now
Questions 52

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

During Solution Development Timebox A, a new Health and Safety requirement arises: the front door is required to have wheelchair access. This is a legal requirement and is a Must Have before any staff or general public access can be allowed. The Solution Development Team will work with the Local Planning Authority Officer, the specialist who identified the requirement, to identify further acceptance criteria for Solution Development Timebox A.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because the new requirement needs to be understood, built and delivered in this Timebox.

B.

Yes, because the Local Planning Authority Officer owns the justification for the new requirement.

C.

No, because this new requirement would NOT be included in the original Prioritised Requirements List and therefore does NOT need acceptance criteria to be defined.

D.

No, because the Business Visionary is responsible for defining acceptance criteria.

Buy Now
Questions 53

Answer the following questions about the tracking and control activities carried out within the project.

Decide whether each activity has been applied appropriately and select the response that supports your decision.

During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager

organized a Facilitated Workshop with the project team to discuss and agree the requirements.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because discussing requirements in the presence of project stakeholders will promote communication and buy-in.

B.

Yes, because this will allow each team member working in a Timebox to raise any issues which may hinder their progress.

C.

No, because early and frequent delivery of the product features will on its own be sufficient to maintain engagement with the stakeholders.

D.

No, because a Review Session should have been scheduled to enable the Solution Development Team to validate their understanding of the stakeholders '

expectations.

Buy Now
Questions 54

There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as

it evolves.

Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2

can be used once, more than once or not at all.

Column 1

1) In order to get an objective

view, the financial transaction

function is to be tested by

someone from Finance who

has had no involvement in its

development.

2) Before the developer works on

the printing function for the

policy documents, the Sales

Manager will review a prototype

of the online application form

for the new coffee shop

insurance product with the

solution tester.

3) Security test scripts have been

provided by the company ' s

bank. These scripts will be used

to test the link from the

company ' s website to the

banking system, which is to be

developed specifically to achieve these tests

4.

The addition of the new coffee

shop insurance product may

threaten the stability of the

existing website. As a primary

route to market this is

unacceptable. The website ' s

capacity to run additional pages

is to be verified before any

other tests are performed.

5.

The Must Have and Should

Have requirements are to be

tested before the Could Have

requirements.

Column 2

    Collaborative Testing

    Repeatable Testing

    Independent Testing

    Prioritised Testing

    Test-Driven Development

AgilePM-Practitioner Question 54

Options:

Buy Now
Questions 55

Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.

Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully

meet Hoy Hall requirements, after deployment.

2. Developing a fully functioning in-house system, developed and hosted by Architecture

Angels IT Operations team.

3. All-in-one web-based reservation and accommodation management system built to Hoy Hall ' s

specification.

4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,

until a suitable system can be implemented at the site.

5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.

Column 2

    Maintainability is a required attribute of the initial delivered solution

    Deliver first, re-engineer later

    Short-term, tactical solution

AgilePM-Practitioner Question 55

Options:

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: May 24, 2026
Questions: 184

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now AgilePM-Practitioner testing engine

PDF (Q&A)

$31.5  $104.99
buy now AgilePM-Practitioner pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 24 May 2026