C_TS412_2021 SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Questions 4

You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?

Options:

A.

Vendor selection -> Purchase order handling -> Invoice receipt- Purchase order monitoring -> Goods receipt

B.

. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> invoice receipt

C.

Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval

D.

Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt

Buy Now
Questions 5

Project Structure

Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates.

What standard report do you recommend?

Options:

A.

Structure overviews for budget.

B.

Cost element report on budget updates.

C.

Line item report for budget

D.

Hierarchical report on budget updates.

Buy Now
Questions 6

You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

Options:

A.

Maintain subordinate internal activity elements assigned to other work centres

B.

Increase the capacities of the work center in the project planning board.

C.

Trigger automatic capacity leveling inside the project planning board

D.

Shift activities backward or forward on the time axis where more capacities are available

Buy Now
Questions 7

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

Options:

A.

Enter an offset of -18 days to the finish date of the activity

B.

Enter February 10 as fixed date

C.

Enter 10 days as duration

D.

Enter an offset of 10 days to the start date of the activity

Buy Now
Questions 8

How can you confirm the working hours of different work centers for a single activity?

Options:

A.

Create multiple confirmations for the activity and use the appropriate work center for each confirmation

B.

Enter direct activity allocation assigning multiple work centers

C.

Enter multiple work centers within a single confirmation

D.

Assign multiple work centers to the activity

Buy Now
Questions 9

Which statement regarding the creation of a new work breakdown structure (WBS element) are true?

Note : there are 3 correct answer for this question.

Options:

A.

You can create several WBS elements per level.

B.

A new work breakdown structure must contain up to 10 levels.

C.

A WBS element of the new project can be assigned to a different project definition.

D.

WBS element can be a planning element, an account assignment element, and a billing element at the same time.

E.

The WBS structure can contain several level 1 WBS element,

Buy Now
Questions 10

Project Structures

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the

project.

What are the prerequisites?

Note: There are 3 correct answers to this question

Options:

A.

A bill of material with sales views

B.

A material master with sales views

C.

Assignment between material and standard network

D.

Standard network with activities

E.

A production order

Buy Now
Questions 11

You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?

Note : there are 2 correct answers for this question.

Options:

A.

Use an offset of two days for the relationship of both activities.

B.

Use an offset of two days for milestone date.

C.

Use an offset of two days for the requirement date of the material component

D.

Calculate the start date of the activity and set the constraint "Must start on" accordingly.

Buy Now
Questions 12

A service company uses project management and they complain that the system does not prevent

their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

Options:

A.

Activate availability control for the WBS elements. Define the tolerance limits on each WBS element

B.

Activate availability control in the assigned budget profile. Define the tolerance limits in customizing

C.

Activate commitment management in the project definition Enter the budget in the master data of the top WBS element

D.

Activate availability control for projects in the controlling area. Enter the plan data for each WBS element

Buy Now
Questions 13

You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question

Options:

A.

Duration

B.

Activity type

C.

Work

D.

Profit center

Buy Now
Questions 14

Project Structures

Which the following statement regarding networks are correct?.

Note : there are 3 correct answers for this question.

Options:

A.

If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.

B.

You can assign more than one activity element to a network activity.

C.

Capacity requirements of a network activity are reduced when the activity is confirmed.

D.

During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.

E.

You can assign the same work center to more than one activity on the same network.

Buy Now
Questions 15

Cost & budget

A service Company use project management and they complain that the system does not prevent their project manager from

exceeding their budget.

What action do you have tsolve the problem?

Options:

A.

Activate availability control For projects in the control area. Enter the plan data for each WBS element.

B.

Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.

C.

Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.

D.

management in the project definition. Enter the budget in the master data of the top WBS element.

E.

Activate commitment

Buy Now
Questions 16

Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct answers to this question.

Options:

A.

Reservations

B.

Sales order items

C.

Purchase order items

D.

Internal orders

Buy Now
Exam Code: C_TS412_2021
Exam Name: SAP Certified Application Associate - SAP S/4HANA Project Systems
Last Update: Apr 18, 2024
Questions: 110

PDF + Testing Engine

$56  $159.99

Testing Engine

$42  $119.99
buy now C_TS412_2021 testing engine

PDF (Q&A)

$35  $99.99
buy now C_TS412_2021 pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 24 Apr 2024