Labour Day - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpm65

CBAP Certified Business Analysis Professional Questions and Answers

Questions 4

You are the business analyst for your organization and are in the process of creating the solution approach for a technology problem.

Which one of the following definitions best describes the solution approach?

Options:

A.

It is the documentation and control of changes to the product scope as approved by the project stakeholders.

B.

Defines the general approach that will be taken to create or acquire new capabilities required to meet the business need.

C.

It is an uncertain event or condition that may have a positive or negative impact on the abilities of the chartered project.

D.

Decomposes the project scope into smaller deliverables; each deliverable is subdivided repeatedly until the deliverable cannot or should not be broken down any further.

Buy Now
Questions 5

You are the business analyst for your organization and you are preparing the business case for a proposed solution. You need to include the management horizon in your business case.

What is the management horizon?

Options:

A.

It is the expected deliverables that will be beneficial for the organization.

B.

It is the point in time when the solution will be completed.

C.

It is the duration of each phase of the project until the solution earns a profit.

D.

It is the point in time for the solution to break even on cost and begin earning a profit.

Buy Now
Questions 6

Your organization uses the MoSCoW approach to requirements prioritization.

What does MoSCoW mean?

Options:

A.

Must, Should, Could, Would

B.

Must, Should, Could, Won't

C.

Mission, Schedule, Cost, Willingness

D.

Must not, Should not, Could not, Will not

Buy Now
Questions 7

A card printing solution is comprised of 4 stages: Loading, Printing, Packaging and Sorting. Loading and sorting of cards is done manually through operators, while printing and packaging are automated. The loading stage requires the operator to load 100 cards after an alarm is raised. Sorting requires an operator to distribute each package based on the printed address into the appropriate delivery box.

Which stage should be assessed as the most likely to increase process inefficiencies?

Options:

A.

Loading

B.

Packaging

C.

Sorting

D.

Printing

Buy Now
Questions 8

Which of the following processes is must at the end of each project phase to determine the completeness of the project work and to gain the customer's acceptance to move the project forward?

Options:

A.

Scope verification

B.

Inspection of key results

C.

Quality control

D.

Phase gate review

Buy Now
Questions 9

The business sponsor of a project to automate a high risk, high profile process has expressed concerns that some activities people perform will be missed. The business analyst (BA) has already created a process flow with associated user stories.

Which of the following actions will address the sponsor’s concerns?

Options:

A.

Record the concerns in the risk register

B.

Schedule a formal review with the stakeholders

C.

Demonstrate traceability to the business case

D.

Review the final approved elicitation results

Buy Now
Questions 10

The business analyst (BA) is facilitating a requirements workshop with a large group of diverse stakeholders, some of whom are not entirely familiar with the goals and objectives of the project.

The BA must understand the business domain, corporate culture, group dynamics, and expected outputs to adequately communicate the:

Options:

A.

change strategy.

B.

requirements prioritization.

C.

elicitation scope.

D.

enterprise architecture.

Buy Now
Questions 11

A business analyst (BA) is working on a stakeholder collaboration plan. The main goal is to select the approaches that work best to meet the needs of external and internal stakeholders.

Which aspects should be taken into account?

Options:

A.

Collaboration skills of BA

B.

Solution design

C.

Timing and frequency of collaboration

D.

Business governance plan

Buy Now
Questions 12

You need to identify assumptions as part of the assessment of capability gaps.

Which of the following is an example of an assumption?

Options:

A.

The project manager believes that her project team members can program in COBOL.

B.

All vendors must have security clearance.

C.

The software must be compatible with the current operating system.

D.

The risk in the project must be quantified.

Buy Now
Questions 13

You are creating the solution scope for a proposed solution in your organization. You need to understand the scope of work that needs to be completed. You elect to identify the solution scope and then break the solution scope into smaller work products or deliverables.

What technique are you using in this instance?

Options:

A.

Interface analysis

B.

Scope modeling

C.

Vision statement creation

D.

Functional decomposition

Buy Now
Questions 14

When is stakeholder analysis performed?

Options:

A.

As soon as the project charter is created.

B.

As soon as the project sponsor is named.

C.

As soon as a business need is identified.

D.

As soon as a business solution is identified.

Buy Now
Questions 15

Paul is the business analyst for his organization. He is examining a single solution to determine if the solution he and his team have identified carries enough business value to justify its implementation.

What business analysis process is Paul performing in this scenario?

Options:

A.

Define transition requirements

B.

Assess proposed solution

C.

Assess organizational readiness

D.

Allocate requirements

Buy Now
Questions 16

The business analysis approach generally defines all of the following attributes except for which one?

Options:

A.

Requirements for solutions acceptance

B.

Deliverables

C.

Team roles

D.

Analysis technique

Buy Now
Questions 17

You are the business analyst for your organization and are working on prioritizing the project requirements. Management has asked you to prioritize the requirements based on the cost-benefit analysis for the requirements' value to the organization.

What basis for prioritization are you using in this instance?

Options:

A.

Business value

B.

Stakeholder agreement

C.

Likelihood of success

D.

Urgency

Buy Now
Questions 18

Which one of the following diagrams visualize the result of the root cause analysis study?

Options:

A.

Activity diagrams

B.

State diagrams

C.

Tornado diagrams

D.

Cause-and effect diagrams

Buy Now
Questions 19

A business analyst (BA) in a large financial institution, responsible for the management of requirements, has completed all the activities related to tracing requirements and is now pursuing to maintain them. The BA has identified a large number of requirements which have long term reuse and is now looking for guidance to manage these requirements.

Which of the following will indicate how requirements will be managed for reuse?

Options:

A.

Legal Regulatory Information

B.

Architectural Repositories

C.

Information Management Approach

D.

Business Rules Analysis

Buy Now
Questions 20

You are coaching Marcy, a new business analyst for your organization, on business analysis processes. Marcy is concerned about the define solution scope process, especially the implementation approach element.

Which of the following statements best defines the implementation approach element for Marcy?

Options:

A.

The implementation approach is described in terms of the major features and functions that are to be included.

B.

The implementation approach defines major business and technical dependencies that impose constraints to the effort to deploy the solution.

C.

The implementation approach describes the new capabilities required to meet the business need.

D.

The implementation approach describes how the chosen solution approach will deliver the solution scope.

Buy Now
Questions 21

Paul has been asked to complete SWOT analysis for his solution scope. What does SWOT analysis mean?

Options:

A.

Strengths, Weaknesses, Opportunities, Time

B.

Stakeholder Weaknesses, Organizational Threats

C.

Stakeholders Weaknesses, Organization, Threats

D.

Strengths, Weaknesses, Opportunities, Threats

Buy Now
Questions 22

What is the term used to describe the cost of the solution after the solution has been implemented in production by a vendor?

Options:

A.

Total ownership costing

B.

Lifecycle maintenance fees

C.

Sustainability fees

D.

Total cost of ownership

Buy Now
Questions 23

Which stakeholder must approve the business analysis approach to ensure that the business analysis approach is compatible with the other project activities?

Options:

A.

Project sponsor

B.

Project manager

C.

Project customer

D.

Change control board

Buy Now
Questions 24

You and Tom are writing the solution scope for a new project in your organization. You need to create a method to define what solution will and will not provide for the organization.

What technique can you and Tom use to establish appropriate boundaries for the solution?

Options:

A.

Interviews with the key stakeholders

B.

User stories

C.

Functional decomposition

D.

Scope modeling

Buy Now
Questions 25

Which of the following requires that all parties in the conflict must give up something?

Options:

A.

Barrier

B.

Problem solving

C.

Withdrawal

D.

Compromising

Buy Now
Questions 26

Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?

Options:

A.

Influence diagram

B.

Project schedule network diagram

C.

Arrow diagramming method

D.

Time-scaled schedule network diagram

Buy Now
Questions 27

Whilst working on business requirements to improve a process, a business analyst (BA) has created flowcharts from the viewpoint of several different users. The stakeholders have expressed some confusion because the flows seem inconsistent.

What ensures that the process models relate to each other?

Options:

A.

Roles and Permissions Matrix

B.

Organizational Model

C.

Future State Description

D.

Information Architecture

Buy Now
Questions 28

Which of the following are directed conversations for gathering ideas, opinions about a product, service, problem, or opportunity?

Options:

A.

Interviews

B.

Group discussions

C.

Feedback loops

D.

Focus groups

Buy Now
Questions 29

Enterprise analysis creates just five outputs.

Which one of the following is an output of the enterprise analysis tasks?

Options:

A.

Assumptions and constraints

B.

Stakeholder concerns

C.

Solution performance assessment

D.

Solution approach

Buy Now
Questions 30

What two factors must the business analyst consider when conducting stakeholder analysis?

Options:

A.

Politics and influence

B.

Influence and attitude

C.

Attitude and position

D.

Position and politics

Buy Now
Questions 31

An insurance company has two actuarial teams: Life and Non-Life. The Life team has a specialized tool to make their calculations while the Non-life team performs calculations manually. Last year the company bought a single solution to support both groups. The non-life team continues to do certain calculations manually to conform to their processes.

Which type of analysis was missed prior to purchasing a solution?

Options:

A.

Operational assessment

B.

Organizational structure

C.

Stakeholder impact analysis

D.

Stakeholder location

Buy Now
Questions 32

A business analyst (BA) plans to hold a workshop next week to elicit requirements for a project. In an informal conversation, another employee mentioned that one of the attendees is likely to be unhappy about the project's impact on their work.

Which of the following techniques will the BA use to avoid disrupting the workshop?

Options:

A.

Elicitation Activity Plan

B.

Collaborative Games

C.

Stakeholder List

D.

Risk Analysis and Management

Buy Now
Questions 33

Which of the following models defines the name of the data, data aliases, and description of system data?

Options:

A.

Class model

B.

Entity relationship

C.

Data dictionary

D.

CRUD matrix

Buy Now
Questions 34

You are the business analyst for the NHQ Project. You have identified several stakeholders that need different types of information related to the requirements.

Which stakeholder would need detailed technical interface requirements?

Options:

A.

Project manager

B.

Regulators

C.

Testers

D.

Implementation subject matter experts

Buy Now
Questions 35

You are the business analyst for your organization. You want to use a requirements elicitation technique to produce a broad set of options for an identified problem. You want the stakeholders to help you identify options, factors that affect the solution, any possible delays in the solution implementation, and ideas for creating a solution.

Which of the following requirements elicitation activities would best satisfy these requirements?

Options:

A.

Benchmarking

B.

Brainstorming

C.

Data flow diagrams

D.

Business rules analysis

Buy Now
Questions 36

Which of the following is NOT a component of flowchart?

Options:

A.

Forks

B.

Attributes

C.

Activities

D.

Joins

Buy Now
Questions 37

What portion of the communications model could be defined as the translator?

Options:

A.

Receiver

B.

Medium

C.

Translator

D.

Sender

Buy Now
Questions 38

You are the business analyst for a large, complex solution and you are working with the stakeholders to determine the prioritization of the requirements. You would like to use the decision analysis to determine the best decision for the requirements outcome. You must know four things as part of decision analysis.

Which one of the following will not help you with this approach to the requirements prioritization process?

Options:

A.

The values, goals, and objectives that are relevant to the requirements

B.

The consequences of each possible decision

C.

The nature of the decision that must be made

D.

The future value of the requirements

Buy Now
Questions 39

is a process to determine the completeness of the project work and to gain the customer's acceptance to move the project forward.

Options:

A.

Phase gate review

B.

Inspection of key results

C.

Verify scope

D.

Quality control

Buy Now
Questions 40

Henry is the business analyst for his organization and is completing the conduct elicitation activity. Part of this activity is to record the results of the requirements elicitation process.

All of the following are acceptable elements for requirements documentation except for which one?

Options:

A.

Text message sent via a secured mobile phone

B.

Written documents describing the outcomes

C.

Visual or audio recordings

D.

Whiteboards

Buy Now
Questions 41

All of the following are techniques that can be used to specify or model requirements except for which one?

Options:

A.

Organization modeling

B.

Data modeling

C.

Work breakdown structure creation

D.

State diagrams

Buy Now
Questions 42

Which conduct stakeholder analysis technique is useful for identifying shared characteristics of a stakeholder group?

Options:

A.

Surveys

B.

Scope modeling

C.

Brainstorming

D.

Interviews

Buy Now
Questions 43

There are just three inputs to the assess proposed solution process.

Which of the following is NOT one of the inputs for the assess proposed solution process?

Options:

A.

Requirements

B.

Decision analysis

C.

Assumptions and constraints

D.

Solution options

Buy Now
Questions 44

You have completed the requirements documentation and the stakeholders have signed off on the requirements. Now the requirements are advancing into a project as your organization has chartered a project based on the identified requirements.

What stakeholder is now responsible for assessing the solution scope to determine the project scope?

Options:

A.

Project sponsor

B.

Project manager

C.

Business analyst

D.

Key stakeholders

Buy Now
Questions 45

You are preparing the business case for a proposed solution in your organization. You need to identify several components for the business case including an assessment of the risks the solution may contain.

Which one of the following is the best definition of a risk as it pertains to the business case?

Options:

A.

Risk is an uncertain event or condition that may have both positive and negative affects on the solution.

B.

Risk is an uncertain event that can cause the organization to lose more monies than it invests in the solution.

C.

Risk is a potential event that can cause the solution to fail.

D.

Risks are threats to the organization's success.

Buy Now
Questions 46

You are the business analyst for the NHQ Organization. Management has asked that you examine the workflow and internal processes for order fulfillment. Specifically, they'd like you to complete an in-depth analysis and documentation of the business problems and opportunities that may be exist for the organization.

What business analysis knowledge area does this activity map to?

Options:

A.

Requirements elicitation

B.

Solution assessment and validation

C.

Enterprise analysis

D.

Requirements management and communication

Buy Now
Questions 47

You are the business analyst for a large project that will create new software for the entire organization. This new software will affect all of the administrative assistants in the organization schedule meetings, reserve facilities, and share calendars. There are approximately 2,400 administrative assistants in your organization and not all of these people can attend requirements gathering workshops.

What approach can you use to manage and gather requirements from these 2,400 administrative assistants?

Options:

A.

You can meet with a small group of administrative assistants and assume their requirements are reflective of the remaining group of administrative assistants.

B.

You will need to meet with all of the administrative assistants as part requirements elicitation.

C.

You can meet with a small group of administrative assistants that will serve as representatives for the remaining administrative assistants.

D.

You can meet with the administrative assistants' managers.

Buy Now
Questions 48

Which of the following process models needs to complete each set of tasks in one phase before moving into the next phase in a project development life cycle?

Options:

A.

Procedural model

B.

Evolutionary model

C.

Spiral model

D.

Waterfall model

Buy Now
Questions 49

You are the business analyst for your organization and are preparing for the conduct elicitation activity. You'll need several stakeholders' roles as you prepare for this activity in your organization.

Which one of the following stakeholders may be responsible to dictate that a specific process or technique be

followed during your requirements elicitation activities?

Options:

A.

Project manager

B.

Regulator

C.

Functional management

D.

Project sponsor

Buy Now
Questions 50

You are the business analyst for your organization and are preparing to conduct stakeholder analysis. As part of this process you realize that you'll need several inputs.

Which one of the following is NOT an input you'll use for the conduct stakeholder analysis task?

Options:

A.

Enterprise architecture

B.

Enterprise environmental factors

C.

Organizational process assets

D.

Business need

Buy Now
Questions 51

You are the business analyst for THY Organization and you have gathered the requirements. You have presented the requirements to the stakeholders and they have approved your requirements.

You are now working with Francie on recording the dependencies and relationships for each of the requirements.

Why would you want to record the dependencies and relationships for the requirements?

Options:

A.

To help determine the sequence in which requirements are to be addressed.

B.

To help determine which requirements carry the most risk.

C.

To help determine the total cost for the solution to be implemented.

D.

To help determine the total time for the solution to be implemented.

Buy Now
Questions 52

Martha is observing Gary complete several activities as part of her requirements elicitation process. Martha is simply observing the steps Gary takes to complete his work and she is taking notes. In this instance Martha does not ask Gary any questions.

What type of observation technique is Martha completing?

Options:

A.

Shadowing

B.

Active

C.

Passive

D.

Usage consideration

Buy Now
Questions 53

You are the business analyst for your organization and are leading a presentation about an identified problem. This presentation will help the stakeholders to understand the problem and it will help you when you begin to elicit requirements from the stakeholders.

Which type of learner learns best through the presentation of models?

Options:

A.

Visual learners

B.

Auditory learners

C.

Kinesthetic learners

D.

Communication model learners

Buy Now
Questions 54

Jenni is the business analyst for the UHQ Organization. She is preparing to complete the conduct elicitation activity for her organization.

Jenni can use all of the following techniques as part of this activity except for which one?

Options:

A.

Requirements workshops

B.

Document analysis

C.

Interviews

D.

Problem tracking

Buy Now
Questions 55

Your organization is using a plan-driven approach to business analysis.

What must you do with all of the communication documents created as part of this high-priority project that you are serving as the business analyst for?

Options:

A.

All formal communication must be destroyed once the project is completed.

B.

All communications must be documented and passed onto the solution's project manager for analysis and to serve as supporting detail.

C.

The communications management plan will dictate what will happen to the business analysis communications.

D.

All communications must be archived and will become part of the organizational process as sets.

Buy Now
Questions 56

Which of the following is mandatory in most software development projects?

Options:

A.

Communication Management plan

B.

Disaster recovery plan

C.

Test plan

D.

Procurement plan

Buy Now
Questions 57

Which of the following is a narrative description of the work required for the project?

Options:

A.

Contract work breakdown structure (CWBS)

B.

Work breakdown structure (WBS)

C.

Contract statement of work (CSOW)

D.

Statement of work (SOW)

Buy Now
Questions 58

You are the business analyst for your organization and are training Tracy on business analysis duties. You are explaining to Tracy how it's important for a business analyst to generate new ideas to approaching problems, solving problems, and to generate alternative solutions. You stress that it's important for the business analyst to generate new ideas and innovative concepts.

What type of analytical thinking are you describing for Tracy?

Options:

A.

Lateral thinking

B.

Brainstorming

C.

Creative thinking

D.

Decision making

Buy Now
Questions 59

What requirements elicitation technique examines the available information, documentation, records, and history of a solution, organization, or cause to identify relevant information to the current business analysis duties?

Options:

A.

Benchmarking

B.

Dataflow diagrams

C.

Document analysis

D.

Requirements elicitation

Buy Now
Questions 60

Which of the following is NOT a component of an entity relationship diagram?

Options:

A.

Attributes

B.

Relationships

C.

Forks

D.

Entities

Buy Now
Questions 61

You are the business analyst for a large project in your organization. You are working with Ben to create requirements packages to present to the stakeholders, the business analyst team, and to the project manager. Ben wants to know why you're creating requirements packages.

What's the primary goal of developing a requirements package?

Options:

A.

To convey the cost, schedule, and risk information clearly

B.

To convey information clearly and in an understandable fashion

C.

To present the requirements in packages that are easy for the project team to accomplish in their project execution

D.

To help the project manager create the work breakdown structure

Buy Now
Questions 62

What requirements elicitation involves carefully selected stakeholders and subject matter experts for a short, intensive period (usually for one to a few days) to define and document the requirements for a solution?

Options:

A.

Many-to-many interviews

B.

Requirements workshop

C.

Focus group

D.

Prototyping

Buy Now
Questions 63

You are the business analyst for your organization. As part of the requirements prioritization you have given each key stakeholder $10,000 in play money to distribute among the identified requirements. Each stakeholder can assign their play money to any of the requirements, but the requirementswill be prioritized based on the value of the play money assigned to each requirement.

What type of requirements prioritization is happening in this scenario?

Options:

A.

Resource leveling

B.

Confirmation management

C.

Utility function

D.

Voting

Buy Now
Questions 64

A bank moves currency from the mam office to the tranches daily for operational use. To avoid paying overnight interest, the branch** return the currency at the end of the business day. The Bank requires a new inventory management system to account for the whereabouts of the cash at all times A software provider has proposed a heavily customized version of their standard inventory management software. As the project progresses, the business analyst (BA) identifies a number of subtleties that would suggest a fully made to order solution may be a better option for the bank. What inputs does the BA need to perform the analysis?

Options:

A.

Requirements and business policies

B.

Needs and business analysis approach

C.

Change strategy and performance objectives

D.

Potential value and design options

Buy Now
Questions 65

A company is about to embark upon a large organizational change initiative that involves restructuring its service offerings. A senior business analyst (BA) is assigned the work of establishing performance measures for the business analysis work to be performed by the 6A ream. Which of the following performance measures is appropriate to assess the value delivered by the work products against the cost time, and resource investments expended to create them?

Options:

A.

Strategy

B.

Effectiveness

C.

Significance

D.

Knowledge

Buy Now
Questions 66

What is the increased cost in Scenario 2 for Company C?

Options:

A.

$453.635

B.

$207.790

C.

$653.934

D.

$695.448

Buy Now
Questions 67

A customer has provided a business analyst (BA) with many business requirements and some have inter-dependencies with other requirements. To ensure the requirements are delivered according to customer expectations which requirements attribute should the BA consider including in the project requirements document?

Options:

A.

Unique identifier

B.

Priority

C.

Constraints

D.

Acceptance criteria

Buy Now
Questions 68

A business analyst (BA) was tasked with eliciting requirements for a new product scheduling system. The BA interviewed and discussed the requirements with the manager and Supervisor. The requirements were written and approved by both the supervise and manager. Which stakeholders were missed in the requirements?

Options:

A.

End users

B.

Project manager

C.

Upper management

D.

IT support

Buy Now
Questions 69

Several commercial-off-the-shelf (COTS) software packages exist that would enable the business analyst (BA) to meet the needs of the business. For the potential deign options, the Ba included one of the COTS packages as a solution approach What kind of solution approach is this?

Options:

A.

Outsource

B.

Exploit

C.

Create

D.

Purchase

Buy Now
Questions 70

After the implementation of a new financial solution the business analyst (BA) observes that the performance of a solution does not meet the anticipated benefits detailed in the original business case. What is a technique the BA can use to understand the reason for that?

Options:

A.

Data flow diagram

B.

Fishbone diagram

C.

Business capability analysis

D.

interface analysis

Buy Now
Questions 71

A business analyst (BA) had identified redundancy in the process for the first contact resolution for customer issues: currently two separate a visions handle this task. A new solution identifies a single point of contact that will eliminate the redundancy. What can the BA do to highlight the required changes to the structure?

Options:

A.

Current state description

B.

Policies and procedures

C.

Business capability analysis

D.

Organizational modeling

Buy Now
Questions 72

A large insurance company wants to buy a new claims processing system or upgrade one of its two existing system. Each year the claims department is given a $3.5 million budget to spend. Time is of the essence since there are tome regulatory charges that will be coming the following year that will require several features that currently neither one of the two claims System currently support.

There are eight stakeholders involved in this initiative. There are local to where the claim system is managed, while five are located across the country. The business analyst (BA) struggled to get all stakeholders to agree on the desired features but ultimately got agreement on ten identified key features for the new claims system. The BA was able to build a current state and future state process model which included all ten key features.

System a processes 75% of the company's claims. It is 5 years old and the claim processors love it because it is easy to use. However, it must go offline for two hours each day. The code is very module so it does have flexibility to be modified. To upgrade system A to have all ten features it would cost $5 million. System A would be at capacity if it were to process all of the company's claims.

System B process 25% of the company's claims. It is an older mainframe system, but rarely goes offline. It could easily handle double the number of claims that system A processes. However, it has a lot of legacy code and would cost $6 million to upgrade.

Both systems have some of the desired key features. But neither system has all ten. The cost to buy a new system would be $7 million.

Below is the estimated cost for each feature in priority order.

CBAP Question 72

During elicitation the BA must understand the non-functional requirements. What nonfunctional requirement does System B support over System A?

Options:

A.

Usability

B.

Compatibility

C.

Scalability

D.

Compliance

Buy Now
Questions 73

A business analyst (BA) wants to create a high-level Overview of a business process as a part of an exploratory analysis. The sponsor has asked for a model that demonstrates the movement and transformation of data between entities and processes. What technique should the BA use?

Options:

A.

Entity relationship diagram

B.

Scope modeling

C.

Process modeling

D.

Data flow diagram

Buy Now
Questions 74

A business analyst (BA) working on a recently implemented project is approached by the sponsor to provide artifacts that can be used organization wide for the long -term. Which of the following should the BA provide?

Options:

A.

Transition requirements document

B.

Project solution architecture

C.

High-level business requirements document

D.

Process models

Buy Now
Questions 75

CBAP Question 75

The table illustrate the statement of cash flower for a courier company for the last fiscal year:

Due to aggressive market competition the management of the company performed a strategy review and based on their0-findings and the current market conditions, they came up with strategic and tactical changes in order to keep a competitive market position.

In order to strength customer retention strategies through a new competitive advantage, the company is considering implementing a live parcel tracking system. The added value will be that the customers may determine the exact location on of the parcel whether it is in a warehouse, crossing the ocean through an overseas the exact location of th parcel whether it is in a warehouse, crossing the ocean through an overseas the ship, or travelling in a delivery truck at any time. The system tracks the location of the parcel by tracking the vehicle in which it is contained. However, for a group of old delivery trucks, it was noticed that the engine sound and vibration disturbed the tracking signal and caused of management would like to sell these vehicles and replace them with newer ones, the Chief Financial Officer (CFO) was strongly against that approach. The CFO argoad that instead of hanging tracking devices on the trucks body they can have the truck drivers manually send the truck send the truck location from a hand held mobile device every 20 minutes.

The CFO's resistance to replacing the older vehicles represents which type of cost?

Options:

A.

Maintenance

B.

Operating

C.

Opportunity

D.

Sunk

Buy Now
Questions 76

Company A has been engaged to provided solution software to Company B as part of a combined service offering to Company C.

The initiative requires a sub project for Companies A and B learn Company Cs statutory requirements, a sub project for Company A to write custom functionality for the solution, and a sub project for Company B to develop infrastructure and support for the solution as well as the main project of implementation and cutover from Company Cs current data processing solution to the service from Company B, How does the business analyst (BA) assign requirements to the various solution components to ensure all objectives are met?

Options:

A.

Described Design Options

B.

Allocate Requirements

C.

Identify Improvement Opportunities

D.

Define Solution Approaches

Buy Now
Questions 77

A health insurance provider undertakes enhancements to its mobile application platform and finalizes the following capabilities as part of the scope of the next release:

I. Ability to integrate online maps and global positioning system (GPS) technology with the mobile application In real time to display location of service providers in the subscriber's vicinity that participate in the subscriber's plan network.

II. Ability for the subscriber to lookup the service providers by specifying either a postal code or a search area radius in miles.

III. Ability for the subscriber to initiate the download of fee information for one or more service providers in a single request.

Through requirements workshops the business analyst elicits the following detailed business requirements:

1. The company's mobile application platform must support real time integrate with the following third party systems:

A GPS System

B. Postal Code Validation

What kind of relationship is used to describe the traceability between requirement 8 and the solutes artifacts that implement it?

Options:

A.

Satisfy

B.

Validate

C.

Depends

D.

Derive

Buy Now
Questions 78

A business analyst (BA) on a project is in the process of validating requirements and finds that there is a high degree of uncertainty related 10 one of the assumptions being true. The BA adds the assumption to the risk register and performs a fun risk analysis to handle this situation. What type of strategy is in place if the organization is risk-averse?

Options:

A.

Acceptance

B.

Transfer

C.

Avoidance

D.

Mitigation

Buy Now
Questions 79

A business analyst (BA) is preparing for observation. A passive approach has been selected for establishing performance metrics. What should be identic for the next step?

Options:

A.

Performance measures

B.

Dependencies

C.

Participants

D.

Communication channels

Buy Now
Questions 80

The business analyst (BA) presented a concept model during a requirements walk through to the project sponsor, implementation subject matter expert and operational support start. While the presentation was clear to the project sponsor the other stakeholders were unsure about the impacts to their respective daily tasks. What should the BA include in the next walk through, so that all stakeholders have a better understanding of the requirements?

Options:

A.

A. An information management model to identify requirement gaps

B.

A capability model to illustrate strategic objectives

C.

A governance architecture to contextual^ toe business analysis approach

D.

An appropriate level of abstraction to support differing viewports

Buy Now
Questions 81

A corporation is experiencing poor financial performance and needs to change many aspects of its business strategy in coder to become solvent again. A business analyst (BA) is conducting a feasibility analysis and analyzing resources required. The BA has identified the existing resources, the resources that need to be increased, and the required additional capabilities. What is the other dimension this analysis should indicate?

Options:

A.

The new resources to be developed

B.

The new financial performance metrics

C.

The enterprise readiness agreement

D.

The timeline for instituting the change

Buy Now
Questions 82

A business analyst (BA) was developing an outline of the timing of business analysis activities with the project manager. What factors may impact the Timing of the activities the BA is performing?

Options:

A.

Solution design

B.

Project manager's experience

C.

Project sponsor Interest

D.

Contract Terms

Buy Now
Questions 83

The stakeholder of a new product that is in early adaptive development has requested a change to an approved feature. How should the business analyst (BA) handle this change?

Options:

A.

Change the business analysis approach to predictive

B.

Obtain formal approval through change request process

C.

Include The requirement in the next Iteration

D.

Add the feature to the product backlog for future prioritization

Buy Now
Questions 84

While reviewing the data feeds on a project the business analyst (BA) realizes there is a feed that contains complex relationships. In order to help understand the data and accurately reflect a set of requirements the BA decides to prioritize the requirements. What modeling format could the BA use?

Options:

A.

User interface

B.

Matrix

C.

Data model

D.

Data dictionary

Buy Now
Questions 85

A business analyst (BA) is capturing the requirements for an application which displays information on a mobile device. The information will be extracted from a database owned by another department within the organization. Which of the following will identify the stakeholder who can approve access to the database?

Options:

A.

Solution Scope

B.

Requirements Architecture

C.

Change Strategy

D.

Governance Approach

Buy Now
Questions 86

A business analyst (BA) is preparing a requirement package for access management system. A state diagram foe entity 'User* has been prepared. The BA wants to check the completeness of requirements by comparing different models. Which diagram should be used with a state diagram to verity that all functions are defined to work with entity "User" for the different roles?

Options:

A.

Sequence diagram

B.

Functional diagram

C.

Use case diagram

D.

Data flow diagram

Buy Now
Questions 87

Before investing further in the project, a customer and the key stakeholders of the project want to be able to visualize the final product. Which elicitation technique should the business analyst (BA) select?

Options:

A.

interface Analysis

B.

Reverse Engineering

C.

Observation

D.

Prototyping

Buy Now
Questions 88

A business analyst (BA) is preparing a governance approach. The BA is trying to define the approval process. Which factors should the BA consider?

Options:

A.

The organizational culture and type of information being approved

B.

The associated risks of foregoing or delaying an approval

C.

The formality and rigor of the prioritization process

D.

The solution performance measures

Buy Now
Questions 89

A business analyst (BA) finds conflicting requirements gathered from several stakeholders. Aside from interviews what additional activities can the BA use to safeguard against this happening?

Options:

A.

Reviews and workshops

B.

User stories and scope modeling

C.

Brainstorming and estimation

D.

Item tracking and mind mapping

Buy Now
Questions 90

In a requirements management effort, the business analyst (BA) has reviewed all the requirements and has completed assessing the various impacts of changes to some of the requirements. The BA is planning to share the impact of the changes to the stakeholders and obtain a consensus in resolution of some of the changes. Which technique will help the Ba obtain a resolution on the impact of the requirement changes?

Options:

A.

Focus groups

B.

Workshops

C.

Interviews

D.

Surveys

Buy Now
Questions 91

A business analyst (BA) has defined a business analysis approach and presented the documents to the sponsors, the senior executives, the domain experts, the project manager and the head of technology, to obtain agreement from all. At this juncture, the prefect manager objected to some of the estimates determined m the budget and refused to agree with the estimates. Which guideline or tool, if followed by the BA. would have helped in avoiding such disagreements?

Options:

A.

Requirements Classification Schema

B.

Stakeholder Engagement Approach

C.

Risk Analysis and Management

D.

Business Analysis Performance Assessment

Buy Now
Questions 92

After determining mat the enterprise culture was the driving force behind recent solution change decisions a business analyst (BA) has decided to conduct an enterprise-wide cultural assessment. What information can the 8A expect to learn from the results?

Options:

A.

Whether there will be an organizational impact as a result of the change

B.

That changes to the enterprise culture will better drive its actions

C.

That internal dependencies limit the performance of the entire solution

D.

Whether the stakeholders view the solution as something beneficial

Buy Now
Questions 93

Manufacturer 0 has received a merger proposal from Manufacturer K There is concern among the senior management of Manufacturer O that regulations could shift in the future, prompting Manufacturer K to move headquarters elsewhere and close operations at the current Manufacturer O site. In assessing the proposal limitations and as part of identifying enterprise limitations, a culture assessment is completed. As part of this work, what else would the BA perform?

Options:

A.

Scope and requirements prioritization

B.

Financial and risk analysis

C.

Organization and functional modelling

D.

Stakeholder impact and operational analysis

Buy Now
Questions 94

You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis.

Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?

Options:

A.

Change-driven approach

B.

Value-driven approach

C.

Plan-driven approach

D.

Requirements-driven approach

Buy Now
Questions 95

All of the following stakeholders participate in the prioritization of requirements except for which one?

Options:

A.

Implementation subject matter expert

B.

Project team

C.

Domain subject matter expert

D.

Project manager

Buy Now
Questions 96

Rachel is writing the business case for her organization. As she's completing this process Rachel is concerned that she's including all the correct information for management.

Which one of the following should Rachel not include in her business case?

Options:

A.

Time to break even

B.

Opportunities to prioritize requirements

C.

Follow-on opportunities

D.

Qualitative and quantitative benefits

Buy Now
Questions 97

Your organization is using a plan-driven approach to business analysis.

What characteristic must be true of changes in the approach that your organization is using?

Options:

A.

All the changes only occur if they are less than an agreed factor, such as ten percent of the solution's overall cost or a percentage of the project's schedule.

B.

All the changes only occur if they are less than ten percent of the solution's overall cost.

C.

All the changes only occur if they are genuinely necessary.

D.

Changes are generally not permitted in the plan-driven approach to business analysis.

Buy Now
Questions 98

You are the business analyst for your organization and are to conduct stakeholder analysis. Which of the following statements best describes the conduct stakeholder analysis task?

Options:

A.

This task identifies organizations and lines of business that may be affected by a proposed initiative or who share a common business need.

B.

This task identifies stakeholders who may be affected by a proposed initiative or who share a common business need.

C.

This task identifies the organizations that are likely affected by a problem that a project must solve.

D.

This task identifies the people who may be affected by a proposed initiative or who share a common business need.

Buy Now
Questions 99

What business analysis element tries to identify as many potential options as possible to meet the business objectives and fill identified gaps in capabilities?

Options:

A.

Ranking of approaches

B.

Decision analysis

C.

Documentation of assumptions and constraints

D.

Alternative generation

Buy Now
Questions 100

You are the business analyst for your organization. Management wants you to prioritize the identified requirements by the requirements that have the highest likelihood of success.

Why would management want you to prioritize the requirements with this factor even though some of the requirements may be difficult to implement?

Options:

A.

They want a fast return on investment.

B.

They want to show early success in the implementation to the project stakeholders.

C.

They don't understand the requirements.

D.

They want to avoid penalties or fines due to a pending law.

Buy Now
Questions 101

When do change requests generally increase in a project?

Options:

A.

During the project's launch.

B.

Towards the beginning of the project.

C.

During the project scope management processes.

D.

Towards the end of the project.

Buy Now
Questions 102

Your organization is trying to determine which one of two opportunities they will pursue. The Project A is worth

$235,987 and Project B is worth $567,000 but carries significant risk. The organization elects to purse Project B and not Project A.

What is the opportunity cost in this scenario?

Options:

A.

$331013

B.

There is not enough information to know as the risk for Project B has not been quantified.

C.

$235,987

D.

$567,000

Buy Now
Questions 103

What document defines the business needs, identifies key stakeholders, and describes the positive impact the solution will provide on the key stakeholders?

Options:

A.

Project charter

B.

Project scope statement

C.

Solution scope

D.

Vision statement

Buy Now
Questions 104

Henry is the business analyst for his organization. Management has created a pre-determined budget of

$450,000 for his solution. Henry has identified the project requirements but now wants to prioritize them based on timeboxing and budgeting. Henry examines the cost of the requirements and begins removing the requirements from the allowed list in order to meet the $450,000 budget.

What timeboxing or budgeting approach is Henry using?

Options:

A.

Parametric

B.

All in

C.

Selective

D.

All out

Buy Now
Questions 105

Nancy has asked you to trace a particular requirement for her.

What does 'to trace a requirement' mean?

Options:

A.

Tracing a requirement means to look at a requirement and the others to which it is related. It links risk,

cost, quality, and scope elements to stakeholder and solution requirements to other artifacts created by the team and to solution components.

B.

Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to stakeholder and solution requirements to other artifacts created by the team and to solution components.

C.

Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to components in the project's work breakdown structure.

D.

Tracing a requirement means to track a requirements from its first identification all the way to its completion to see what issues, risks, costs, quality, and defects have surrounded the requirement

Buy Now
Questions 106

Which of the following terms is used to describe a major deliverable or key even in the project used to measure project progress?

Options:

A.

Project life cycle

B.

Phase

C.

Achievement

D.

Milestone

Buy Now
Questions 107

Which of the following techniques is used to test customer acceptance of the solution and to measure marketplace demand?

Options:

A.

Interviews

B.

Market Survey

C.

Technology Assessment

D.

Prototyping

Buy Now
Questions 108

Which of the following tasks cannot start until other tasks are completed?

Options:

A.

Analysis task

B.

Dependent task

C.

Predecessor task

D.

Independent task

Buy Now
Questions 109

Which of the following processes includes tasks and roles, risk categories, schedules for risk management activities, definitions of probability and impact, and the stakeholders' tolerances?

Options:

A.

Risk management plan

B.

Risk register

C.

Risk analysis

D.

Risk response plan

Buy Now
Questions 110

Which of the following stages of a project defines the number of risks and opportunities, including intense planning and anticipation of risk events?

Options:

A.

Planning

B.

Executing

C.

Initiation

D.

Closing

Buy Now
Questions 111

All of the following are examples of transference risk response except for which one?

Options:

A.

Warranties

B.

Performance bonds

C.

Life cycle costing

D.

Use of insurance

Buy Now
Questions 112

Which of the following is a conversation between one or more speakers centering on one specific topic?

Options:

A.

Feedback loop

B.

Presentation

C.

Survey

D.

Formal requirements review

Buy Now
Questions 113

A business analyst (BA) has been writing requirements for a project that has several stakeholders with varying levels of product expertise.

What must the BA take into consideration to meet stakeholder perspectives?

Options:

A.

The competency of individual stakeholders

B.

The format of the requirements

C.

The types of diagrams produced

D.

The level of decomposition needed

Buy Now
Questions 114

Which of the following techniques involves attempting to make and numerically determine the probability of various adverse events and measuring the likely extent of the losses?

Options:

A.

Risk analysis

B.

Qualitative risk analysis

C.

Risk assessment

D.

Quantitative risk analysis

Buy Now
Questions 115

A business analyst (BA) has engaged various groups from across the organization to define the business opportunity a potential project will address. The BA must consolidate the information collected from the groups.

The BA should ensure the business needs.

Options:

A.

are traceable to their source stakeholders.

B.

are articulated from the enterprise perspective.

C.

describe the potential solutions that they will satisfy.

D.

have minimal risk associated with them.

Buy Now
Questions 116

A big construction company has grown into a group of 17 companies spread across the country. The rationale behind forming the group was to become more competitive in bidding for federal and regional government contracts. Another reason was to increase consolidated profitability by lowering the cost of materials and using combined assets more efficiently. Disjointed technological capabilities of the individual companies impede gathering the data needed to make decisions on both handling materials and allocating the resources.

What improvement opportunity does this represent?

Options:

A.

Create a business model canvas to outline business needs

B.

Deploy a new system across the companies

C.

Enhance access to the relevant information

D.

Develop a repository of information from each company

Buy Now
Questions 117

Which of the following techniques is used to divide a project into controllable parts?

Options:

A.

Gantt Chart

B.

Pareto Chart

C.

WBS

D.

CPM

Buy Now
Questions 118

In performing the task of planning for business analysis governance for a software implementation project, the business analyst (BA) recommends that prioritization of requirements be done based on the amount of work that the project team is capable of delivering in a given period of time.

Which of the following techniques is the BA recommending?

Options:

A.

Negotiation

B.

Grouping

C.

Time Boxing

D.

Budgeting

Buy Now
Questions 119

Which of the following can be an effective tool during quality control to help determine the how the problem occurred?

Options:

A.

Rework

B.

Trend Analysis

C.

Flowcharting

D.

Pareto Diagram

Buy Now
Questions 120

As part of defining the business analysis approach for a project, the business analyst (BA) identifies the key stakeholders responsible for upcoming activities for the initial phase. The BA emails each of these stakeholders and asks when they can be finished. One stakeholder does not reply, one angrily comments that it is not their job and is too busy, and two respond saying that they do not understand what is being asked of them.

What competencies can the BA draw on that would best assist with getting agreement from all these stakeholders?

Options:

A.

Personal accountability, time management, demonstrated trustworthiness

B.

Negotiation, conflict resolution, effective communication

C.

Industry knowledge, solution knowledge, organization knowledge

D.

Learning, creative thinking, problem solving

Buy Now
Questions 121

An insurance company wants to increase sales by 15% and customer retention by 10% within 1 calendar year.

Various strategies to achieve this were considered and a restructure to the existing pricing model is selected to help achieve these goals.

A business analyst (BA) works with stakeholders such as actuaries, product specialists, sales staff, risk managers, and underwriters who agree to applying varying levels of discounts to customers based on:

•Total annual premium the customer has with the company (Financial worth)

•Time with the insurance company (Loyalty)

Various financial models are considered but the stakeholders agree that an initial applicable discount is determined based on the customer's overall premium:

CBAP Question 121

The percentage of the maximum possible discount available to the customer is adjusted based on time with the company:

CBAP Question 121

What did the BA create to ensure that everyone who needed to be included had been?

Options:

A.

Onion diagram

B.

Concept model

C.

Capability diagram

D.

Context model

Buy Now
Questions 122

A non-profit utility company has 900 employees, a majority of whom are hourly employees and must track their time using a paper based process. A few years ago, the Director of Human Resources purchased a software system to eliminate the current paper-based time reporting process. No requirements specific to the utility company were defined prior to the purchase. A team was formed to implement the software During implementation process, the team discovered the software lacked functionality and was not robust enough to support the general ledger requirements The company stopped the effort and incurred a $500,000 USD loss on the cost of the software.

This year, the Director of Finance requested that a team investigate the current paper-based time reporting process and recommend solutions. The Director of Finance feels that the Director of Human Resources must be involved as a critical stakeholder. The Director of Human Resources is still bitter about the last effort because the process stopped'.

Which of the following is included in performing a stakeholder analysis?

Options:

A.

Compare the expertise of the Director of Human Resources to other stakeholders

B.

Recommend excluding the Director of Human Resources as a stakeholder

C.

Develop a risk plan to anticipate negative behavior from the Director of Human Resources

D.

Implement all of the Director of Human Resources suggestions to relieve tension

Buy Now
Questions 123

The business analyst (BA) is not having great success scheduling stakeholder meetings. Stakeholders say they are too busy or there are higher priority meetings on their calendars. The BA is concerned, knowing that stakeholder availability, attitude, and willingness to engage will impact the timeliness of project delivery as well as the.

Options:

A.

test execution.

B.

approval process.

C.

requirements reuse.

D.

risk analysis process.

Buy Now
Questions 124

An insurance company wants to increase sales by 15% and customer retention by 10% within 1 calendar year.

Various strategies to achieve this were considered and a restructure to the existing pricing model is selected to help achieve these goals.

A business analyst (BA) works with stakeholders such as actuaries, product specialists, sales staff, risk managers, and underwriters who agree to applying varying levels of discounts to customers based on:

•Total annual premium the customer has with the company (Financial worth)

•Time with the insurance company (Loyalty)

Various financial models are considered but the stakeholders agree that an initial applicable discount is determined based on the customer's overall premium:

CBAP Question 124

The percentage of the maximum possible discount available to the customer is adjusted based on time with the company:

CBAP Question 124

As the new pricing structure was being implemented, the chief executive officer (CEO) of the company wanted to change the premiums and associated discounts offered to customers. The BA investigated the cost, anticipated benefits and the length of time the change would likely take to complete before presenting the results back to the CEO.

What type of analysis has the BA just conducted?

Options:

A.

Impact

B.

Capability

C.

Market

D.

Document

Buy Now
Questions 125

A business analyst (BA) elicits requirements for the sales order processing of multiple product lines. Elicitation reveals that the business processes for the sales orders of most products follow similar activity patterns that have been established over a number of years. Some of the new proposed seasonal products, however, will necessitate major variations in the process flow of some departments. The seasonal products are likely to be different every year. The business needs to carefully adapt its business practices so that the significant but seasonal variations in some of the business processes for the new products are handled adequately without disrupting the processes for the other established products.

Which of the following approaches must the BA take to manage the requirements for sales order processing in the long term?

Options:

A.

Reference specific departments in the requirements for the seasonal products

B.

Reference specific departments in the requirements for the established products

C.

Use a high level of abstraction for the seasonal products to make them less subject to revision during a change

D.

Use a high level of abstraction for the established products to make them less subject to revision during a change

Buy Now
Questions 126

The BA Is finalizing the definition of the requirements architecture by understanding how requirements relate to each other. A key component that must be apparent in all three diagrams is that none of the requirements be linked in different or conflicting ways. What relationship quality criterion does this represent?

Options:

A.

Unambiguous

B.

Correct

C.

Necessary

D.

Defined

Buy Now
Questions 127

A health insurance provider undertakes enhancements to its mobile application platform and finalizes the following capabilities as part of the scope of the next release:

I.Ability to integrate online maps and global positioning system (GPS) technology with the mobile application in real time to display location of service providers in the subscriber's vicinity that participate in the subscriber's plan network.

II.Ability for the subscriber to lookup the service providers by specifying either a postal code or a search area radius in miles.

III.Ability for the subscriber to initiate the download of fee information for one or more service providers in a single request.

Through requirements workshops the business analyst elicits the following detailed business requirements:

1.The company's mobile application platform must support real time integration with the following third party systems:

A ) GPS System

B ) Postal Code Validation

2.The service providers available for selection must participate in the subscriber's medical plan network as of the current system date.

3.The map display shall highlight the boundary of the search area with a dotted yellow line.

4.The extent and shape of the search area shall be determined based on one of the following user choices:

A ) Postal code – Subscriber location acquired from GPS shall be used to determine and populate the related postal code as the default postal code with options for the user to change the postal code.

B ) Radius for the search area around the subscriber's location, that will have default value of 5 miles. The radius can be changed by the subscriber with a maximum range of 50 miles.

5.Subscriber shall be able to select one of the options above and supply corresponding input.

6.System shall validate the user input and display appropriate error messages if invalid.

7.Based on the inputs and the plan of the subscriber, the system shall retrieve information for the participating service providers that are located within the designated search area.

8.System shall display a map including visual markers to indicate locations of the service providers in the top half of the device screen and a list of the same service providers in the bottom half of the device screen.

9.The list of service providers shall include the Name, Phone Number and Street Address.

10.If the subscriber specified the radius or retained the default postal code for the search area, the list shall additionally include the approximate driving distance in miles from the subscriber's last registered location and the list shall be sorted in the ascending order of the driving distance.

11.The subscriber shall be able to select a service provider either from the list or from the map and download a document that contains the name, contact telephone, email address, fax number and the fee schedule for the covered services applicable to the subscriber's plan.

Which of the following characteristics is violated by requirement 5?

Options:

A.

Feasible

B.

Concise

C.

Consistent

D.

Atomic

Buy Now
Questions 128

A business analyst (BA) has been given a defect during user acceptance testing. After analyzing the defect, the BA determines it is a change in the requirement.

What does the BA need to do to assess the change?

Options:

A.

Close the defect "working as designed"

B.

Evaluate the risk analysis and management information

C.

Perform a root cause analysis

D.

Conduct an impact analysis using traceability

Buy Now
Questions 129

A business analyst (BA) works for an organization that is moving from a waterfall methodology to an agile approach. This causes new challenges and opportunities for the BA.

Which business analysis planning and monitoring element is most impacted by the organization's change?

Options:

A.

Timing of business analysis work

B.

Conflict and issue management

C.

Technology and infrastructure

D.

Solution scope

Buy Now
Questions 130

The technology team at a financial institution has successfully constructed a software application to be deployed as part of a digital banking strategy. A business analyst (BA) has completed a review of the current state description and now needs to evaluate the solution and determine limiting factors for value realization.

What additional input is required to perform the assessment of enterprise limitations?

Options:

A.

Operational assessment

B.

Potential value

C.

Solution performance analysis

D.

Organizational structure

Buy Now
Questions 131

The seminar administrator reviewed these three diagrams and asked the BA to create a fourth diagram to model the various levels that a trainee goes through (e.g., white belt to yellow belt yellow belt to green belt etc). What modeling technique will the BA use to create this diagram?

Options:

A.

Decision modeling

B.

State modeling

C.

Concept modeling

D.

Organizational modeling

Buy Now
Questions 132

An organization is trying to streamline its current processes to improve performance and reduce costs. A business analyst (BA) conducted a process improvement workshop and identified the following issues as the top three items to be addressed:

1: There are multiple teams to define systems, functionality, and content in many instances, multiple teams are defining the same functionalities while other functionalities are not being defined at all leading to unclear understanding of business requirements.

2: Product specification forms are published each year. A comparison tool is used to evaluate specification differences between yearly releases; but does not adequately identify changes between versions and needs to be improved.

3: Training consists of a new team member shadowing a seasoned team member. There are no written training materials or formal training sources therefore training is inconsistent and not meeting the needs of the organization.

What analysis approach must the BA use to determine changes required to address the training needs?

Options:

A.

Market

B.

Decision

C.

Root cause

D.

Future state

Buy Now
Questions 133

Company A is a nation-wide leader in commercial demolition. Having just celebrated its 100th year of operations, the company decided to begin doing work internationally. The current system used for reporting company finances is unable to keep pace with the potential demands of doing work in geographically dispersed locations. Therefore, the company decided to replace its client-based Profit & Loss (P&L) reporting system with a more robust, web-based system. This will ensure transparency across the organization and enable better decision making.

The business analyst (BA) at Company A has recently completed several rounds of elicitation to determine the requirements for the new, web-based system. Over 1250 requirements were elicited. An initial Requirements Traceability Matrix (RTM) has been drafted, and a subset of the RTM can be seen below:

CBAP Question 133

The BA will create a Data Model to meet which requirement?

Options:

A.

Requirement ID F-R0002

B.

Requirement ID FE10001

C.

Requirement ID NFP0002

D.

Requirement ID F-R0003

Buy Now
Questions 134

The performance of a newly implemented document management system is falling significantly short of the measures defined as part of the project. However, the business is recognizing some level of value from the system. The business analyst (BA) considers the only option available to the company to increase performance and determines that the cost of implementing the option is ten times higher than the expected benefits. What should the BA recommend?

Options:

A.

Continue with the implemented solution

B.

Retire the implemented solution

C.

Conduct elicitation

D.

Plan stakeholder engagement

Buy Now
Questions 135

The business analyst (BA) is preparing to determine the impact of various risks associated with the business analysis effort currently underway.

Which of the following would the BA use as an input into the assessment of risk?

Options:

A.

Defined change strategy

B.

Analysis of potential value of the recommended solution

C.

List of prioritized requirements

D.

Unconfirmed results of elicitation activities

Buy Now
Questions 136

A national branch of a global company is struggling to improve business processes of its Public and Government Affairs (PGA) department. To work with external stakeholders effectively, PGA employees need to collect, manage, and exchange a vast amount of information. Complex cases involve collaboration of many employees from different departments. The ability to share information and to coordinate corresponding activities is crucial for the company's growth plans. Their current tools and practices do not serve the purpose well. The existing system, which was deployed a couple of years ago, has only a few active users. The majority of PGA employees avoid using it because the system is hard to use and lacks needed functionality. Consequently, available information is mostly unstructured and stored either locally or on a shared network drive. Some of the information exists only in a paper form.

The branch's PGA head, who sponsors the project, wants to implement a configurable solution that two other branches successfully deployed several months ago. Both deployments were done by three solution consultants, who will be available to assist in the project. They will be responsible for tailoring the solution to PGA needs, as well as for training the PGA staff. With their help, the sponsor plans to complete the project in approximately three months.

The solution consultants reside in another country 7 hours ahead of the rest of the project team. They will be available part-time, but are planning two one-week long trips to the PGA central office to conduct initial training and to participate in the final deployment of the system into production. The consultants, in turn, expect a business analyst (BA) to assist in collecting necessary data and defining customization requirements.

The solution consultants have composed a set of as-is solution documents. A spreadsheet contains a catalog of brief definitions of all requirements with priorities assigned to them. A separate document explains data models and user interfaces. For the new and changed requirements, the BA wants to capture additional attributes such as the source, reason, complexity, and priority of change. Some of these requirements can be reused in other work.

How should information for these requirements be managed?

Options:

A.

Rewrite requirements independent of the solution design

B.

Enter the information in the company's change management system

C.

Add the attributes to the original requirements catalog and change requirements

D.

Create a new workbook of requirements with necessary attributes

Buy Now
Questions 137

Most users of a pilot application have experienced more efficient processing compared to the old system. However, the business analyst (BA) has observed that a few people took much longer to complete the process. The system event log shows that those users encountered errors when they attempted to sign on.

Which of the following would the BA recommend to improve overall performance?

Options:

A.

Sent a reminder to all users of their user ID and password

B.

Automate the login process

C.

Gather more information from the individuals who had errors

D.

Extend the pilot to more people

Buy Now
Questions 138

A financial institution engaged in mortgage lending has embarked on a business process improvement initiative to eliminate the activities that hinder growth to ultimately improve the success rate of its mortgage business. As a benchmark for identification, the institution is keen on improving any business process that has less than a 75% success rate. The institution has appointed a business analyst (BA) to review the business transactions for the processes of origination, payments, and closures, as well as identify opportunities for improvements and recommend solutions.

The BA has collected the following information over the last three months pertaining to these business processes:

•All the business processes are at their maximum capacity in terms of the current number of transactions.

•Each business process has a certain number of rejects and the reasons for rejection include documentation, verification, collateral, and funding. Funding rejects occur when the bank's customers have failed to make payment of their mortgage processing fee or mortgage closure payment.

The BA has also recommended the use of documentation checklists as a solution to eliminate the documentation rejects.

CBAP Question 138

If an additional recommendation to reduce Verification Rejects by 50% were to be introduced into the mortgage origination process, what is the potential success rate of the mortgage origination process?

Options:

A.

86%

B.

83%

C.

70%

D.

74%

Buy Now
Questions 139

Company A is a nation-wide leader in commercial demolition. Having just celebrated its 100th year of operations, the company decided to begin doing work internationally. The current system used for reporting company finances is unable to keep pace with the potential demands of doing work in geographically dispersed locations. Therefore, the company decided to replace its client-based Profit & Loss (P&L) reporting system with a more robust, web-based system. This will ensure transparency across the organization and enable better decision making.

The business analyst (BA) at Company A has recently completed several rounds of elicitation to determine the requirements for the new, web-based system. Over 1250 requirements were elicited. An initial Requirements Traceability Matrix (RTM) has been drafted, and a subset of the RTM can be seen below:

CBAP Question 139

While verifying the requirements, the BA notices that Requirement ID NFO0003 does not meet the "unambiguous" or the "testable" characteristics of requirements quality. The BA plans to re-write the requirement.

Which of the following requirements is both unambiguous and testable?

Options:

A.

"The solution shall employ a blue background."

B.

"The solution shall employ a background color blue (HEX #0000FF)."

C.

"The solution shall employ a high-contrast between background and text."

D.

"The solution shall employ a background color that is viewable to a colored-blind user."

Buy Now
Questions 140

An organization is trying to streamline its current processes to improve performance and reduce costs. A business analyst (BA) conducted a process improvement workshop and identified the following issues as the top three items to be addressed:

1: There are multiple teams to define systems, functionality, and content, in many instances, multiple teams are defining the same functionalities while other functionalities are not being defined at all. leading to unclear understanding of business requirements.

2: Product specification forms are published each year. A comparison tool is used to evaluate specification differences between yearly releases; but does not adequately identify changes between versions and needs to be improved.

3: Training consists of a new team member shadowing a seasoned team member. There are no written training materials or formal training sources therefore training is inconsistent and not meeting the needs of the organization.

What approach would help the BA to understand the functionality definition issues?

Options:

A.

Business Analysis Communication Plan

B.

Business Analysis Performance Assessment

C.

Risk Register

D.

Requirements Traceability Repository

Buy Now
Questions 141

A business analyst (BA) is developing an approach for information management. The BA needs to identify and categorize which information is to be managed.

Which of the following techniques should the BA use to achieve this objective?

Options:

A.

Item Tracking

B.

Observation

C.

Prototyping

D.

Mind Mapping

Buy Now
Questions 142

A major manufacturer of popular beverages has appointed a local distributor to serve a specific territory. The demand for the beverages has a pronounced seasonal pattern. The distributor performs well overall, but is repeatedly unable to keep up with fulfilling many customer orders during peak demand periods. The distributor's current delivery capability is stretched to deliver 60 tons of merchandise per day whereas the season's peak demand periods need a daily delivery capability of up to 100 tons.

The distributor is under pressure to fully meet the year-round market demand in order to stay in business. The distributor's management wants to identify and consider more cost-effective options as resorting to adding more trucks and drivers would not be economically feasible.

A business analyst (BA) has spent several days observing and measuring the warehouse activities to understand the situation and to gain insights into possible solutions. The delivery workflow is a four-step process: (1) picking the orders and assembling them on trays, (2) bringing the trays to the loading bay, (3) loading the orders into trucks, and (4) delivering the orders to customers. As the following table illustrates, overall performance depends is dependent on five major resources: (1) the workers who pick the orders and load them into trucks, (2) the tallyers who check the orders, (3) the drivers, (4) the trucks, and (5) eight loading bays (LBs).

CBAP Question 142

Preparing a customer order for loading takes about one hour. Upon the BA's observation, only 30% of trips have their orders available for loading when a truck arrives. This causes a waste of both the truck's and the driver's time.

What should the BA recommend to eliminate such waste?

Options:

A.

Elicit requirements for a system to coordinate in advance order processing activities with all trips

B.

Begin assembling orders for the next trip immediately following the truck's departure

C.

Hire more warehouse staff (workers) so that order assembly is done faster and less waiting occurs

D.

Ask the drivers to call the operations team member if they are going to be late

Buy Now
Questions 143

A company with a big information technology (IT) department has hired a lead business analyst (BA) to enhance its business analysis practices. The lead BA discovers that sponsors are not satisfied with project outcomes. Developers complain about incomplete, ambiguous, and changing requirements. All stakeholders, including project managers, are blaming long cycles of analysis for the delays. The business analysts, in turn, feel overwhelmed with the number of projects and frustrated by the lack of collaboration from reviewers of their deliverables. All of the evidence is anecdotal and none of the groups could strongly substantiate their opinions.

The lead BA wants the BAs to report anticipated and actual completion dates for their deliverables, as well as the time spent on planned and unplanned activities. What is the lead BA trying to do by analyzing the results of such measurements?

Options:

A.

Identify typical missing or wasteful activities

B.

Ensure even workloads of the BA

C.

Establish an equitable compensation system

D.

Motivate the BA to work belter

Buy Now
Questions 144

A very large insurer of General Liability and Property Damage insurance has an upward trend of increased claims over the past 5 years.

The Risk Control Area for that company has just completed a 12 month Pilot of a new improved Risk Control Site.

The purpose of the site is to help their customers manage their exposures and ideally prevent them from having claims There were 100 customers that were part of the Pilot that represented 25 different industries. The business goals were to increase use of the site and provide tools to help customer awareness of their exposures, so that they may reduce existing exposures and ultimately reduce claims.

The sites Features were as follows:

* Improvements to the search engine to all customers to search for articles, tools and services on the site

* A checklist function that allow customer to create their own unique Checklists or utilize a sample provided by ABC company to use daily, weekly etc for an area of their facility.

* A promotion feature - where Risk preventing Articles, and tools on the site are marketed toward a customer.

* A profile section allowing for Customer Name, Address and contact Phone number.

Alter the 12 month pilot the business sponsor received an assessment of what was working and what was not. The Assessment of the pilot revealed overall site activity had significantly increased, however only 5% of the time the promotions were viewed. And the most shocking was that total claims increased by nearly 20% for these 100 customers during the pilot period. The business sponsor was perplexed as he had an expectation of reduced claims and at least for 30% viewing of promotions since the project team had spent a lot of careful time and effort on this feature. A BA was assigned to do further analysis regarding the low use of the promotions and why claims were not being reduced.

Regarding the use of promotions the BA looked into other similar companies to see what they did differently to get their customer to look at their promotions. The BA found that similar companies had promotions that targeted the industry the customer was in so it was more relevant to them and they were more interested to view the promotion. In addition the BA sent out a survey to all 100 pilot customers asking probing questions about what they thought of the site and if they felt it had decreased their exposure to risk sufficiently. The Survey responses came back with raving positive comments and providing examples of how the site had been helping in the reduction of claims from the customer's perspective. In addition the survey also revealed insight that the customers found the promotion often irrelevant to their industry.

The BA asked for a dump of all documentation of the 1000 claims that were filed over the 12 month pilot period. The BA found the nearly 90% of the claim filed were all in one region of the country and were all for property damage related to several severe winter storms in the region and the claims were nearly all unavoidable by the customers. The BA brought all this analysis back to the business sponsor and made the recommendation to the business sponsor to require the customer to select 1 of 25 industries in their profile. This would in turn allow for the ability to show industry specific promotions and promote search results relative to a customer's industry to be sorted at the top giving the customer a more personalized experience.

What type of recommendation has the BA made to the business sponsor?

Options:

A.

Perform organizational change

B.

Identify additional capabilities

C.

Reduce complexity of interfaces

D.

Retire the solution

Buy Now
Questions 145

The BA is working on the design options for the future state at the martial arts organization. There are several design elements that need to be considered for the future state. Which of the following design elements does the Activity Diagram address?

Options:

A.

People who operate and maintain the solution

B.

Operational business decisions to be made

C.

Business processes to be performed and managed

D.

Business policies and business rules

Buy Now
Questions 146

Several risks were identified for an upcoming change initiative. One risk is related to a slippage concern because of loose gravel at the local site of the change initiative. The business analyst (BA) has recommended that all on-site stakeholders must wear durable, slip-resistant boots while the change initiative is being executed.

This is an example of which type of risk treatment?

Options:

A.

Transfer

B.

Mitigate

C.

Accept

D.

Avoid

Buy Now
Questions 147

A business analyst (BA) is working on a payment system (PS) implementation. A set of systems which should interact with a new system has been identified. The business analyst defined that a user with role of "Supervisor" in the PS must pass a two-factor authentication before an execution of the functions: "Change system parameters" and "Set up new supervisor." A user must have the role of "Supervisor" to use the standard functions "Send mail notification" or "Send SMS notification".

The BA defined the following use cases:

•"Change system parameters"

•"Setup new supervisor"

•"Send mail notification"

•"Send SMS notification"

•"Send notification"

•"Pass a two-factor authentication"

The BA wants to create a Use Case diagram.

Which technique should be used to define a communications protocol between the PS and other systems?

Options:

A.

Vertical prototyping

B.

Interface analysis

C.

Concept modelling

D.

System analysis

Buy Now
Questions 148

A software development company is in the process of creating a new product for their customer base. It has been several years since such a project has been initiated and the organization has created a new team to own and develop the product. The project team will be evaluated by the successful adoption of the product, which will be developed over the next 12 months.

The team's business analyst (BA) has analyzed the current state in partnership with the product owner and has been meeting with senior management to identify the goals that need to be attained. A broad view of the business has been analyzed in order to have an understanding of how the company is currently providing value to its customer base.

What has the BA evaluated to help determine value of the project?

Options:

A.

Internal assets

B.

External influencers

C.

Change strategy

D.

Business architecture

Buy Now
Questions 149

A software development company is in the process of creating a new product for their customer base. It has been several years since such a project has been initiated and the organization has created a new team to own and develop the product. The project team will be evaluated by the successful adoption of the product, which will be developed over the next 12 months.

The team's business analyst (BA) has analyzed the current state in partnership with the product owner and has been meeting with senior management to identify the goals that need to be attained. A broad view of the business has been analyzed in order to have an understanding of how the company is currently providing value to its customer base.

After the BA completed the initial analysis, the information is reviewed with leadership. At this point in the project, what will the BA be presenting?

Options:

A.

Project timeline

B.

Project deliverables

C.

Resource staffing

D.

Expected benefits

Buy Now
Exam Code: CBAP
Exam Name: Certified Business Analysis Professional
Last Update: Apr 22, 2024
Questions: 497

PDF + Testing Engine

$56  $159.99

Testing Engine

$42  $119.99
buy now CBAP testing engine

PDF (Q&A)

$35  $99.99
buy now CBAP pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 27 Apr 2024