Spring Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

CCM Certified Contract Manager Questions and Answers

Questions 4

(For specific probable future events or circumstances which may adversely affect the Works, FIDIC Red and Yellow Books (edition 1999) provide a duty to notify specific parties. Which two statements are correct?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The Notice shall be given when the Time for Completion will be affected.

B.

Each Party shall advise the other and the Engineer of such events or circumstances, and the Engineer shall advise the Parties.

C.

The Engineer has no obligation under General Conditions to notify the Contractor of such events.

D.

The obligation to issue such Notice requires the Contractor to give such Notice to the Engineer.

Buy Now
Questions 5

When does discharge become effective under the FIDIC Red Book (edition 1999)? (1 correct answer applies)

Options:

A.

When the Contractor receives full payment certified through the Final Payment Certificate.

B.

When the Contractor receives its Performance Security from the Employer.

C.

When the Contractor receives full payment certified through the Final Payment Certificate and return of the Performance Security.

D.

When the Employer counter signs a discharge notice as issued by the Contractor, following full payment and return of the Performance Security.

Buy Now
Questions 6

Regarding the FIDIC Red Book (edition 1999): which two statements are true in respect of Building Information Modelling (BIM)?

Choose all of the correct answers (multiple possibilities).

Options:

A.

General Conditions of Contract require the use of BIM.

B.

BIM is one of the digital data technologies used in all aspects of project planning, investigation, design, construction and operation.

C.

BIM is not related to the improvement of quality, accuracy, delivery times and cost savings.

D.

For construction or building projects involving BIM, many Sub-Clauses of FIDIC Red Book (edition 2017) should be thoroughly reviewed when drafting the Particular Conditions.

Buy Now
Questions 7

Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 8

Which of the following situations form legally binding contracts? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities)

Options:

A.

The Employer received the Contractor ' s Letter of Tender and issued a Letter of Intent.

B.

The Employer and the Contractor signed the Contract Agreement.

C.

The Employer received the Contractor ' s Letter of Tender and issued a conditional Letter of Acceptance.

D.

The Employer received the Contractor ' s Letter of Tender and issued Letter of Acceptance.

Buy Now
Questions 9

In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs. This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 10

What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Notice is a defined term, while other communications are not defined as a term in the General Conditions.

B.

Contractually there is no difference between a notice and other communications.

C.

Both ' Notice ' and ' Other Communications ' are defined terms under the Conditions of Contract.

D.

The Parties and Engineer shall be given original or copy of any Notice, Notice of Dissatisfaction (NOD) and Certificates, which is not always the case for other communications.

Buy Now
Questions 11

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?

Options:

A.

True

B.

False

Buy Now
Questions 12

Which of the following documents form part of a FIDIC Construction Contract [ " Red Book " (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Schedule of Guarantees

B.

Bill of Quantities

C.

Employer ' s Requirements

D.

Schedule of Baselines

E.

Specifications

Buy Now
Questions 13

Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?

Options:

A.

A description of the varied work.

B.

A description of the proposed design.

C.

Details of the resources and methods to be adopted by the Contractor.

D.

A Programme for execution of the varied work.

Buy Now
Questions 14

Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?

Options:

A.

A declaration of joint and several liability

B.

A bank guarantee

C.

A surety bond

D.

A parent company guarantee

Buy Now
Questions 15

Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor ' s Proposal. Which two of the following statements are true in this respect, after it has been submitted?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor is entitled to change the design by optimising the design, without approval of the Employer/Engineer.

B.

The Contractor is not allowed to make any changes regarding the design to optimise the design, unless approved by the Engineer/Employer.

C.

The Contractor may submit a proposal for Value Engineering.

D.

The Contractor is not allowed to submit a proposal for Value Engineering, as any value engineering should already have taken place before submitting its design proposal.

Buy Now
Questions 16

In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an " ad-hoc " basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)

Options:

A.

Ad-hoc DAAB

B.

DAB

C.

Ad-hoc DB

D.

Ad-hoc arbitration

Buy Now
Questions 17

The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.

Options:

A.

True

B.

False

Buy Now
Questions 18

You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?

Options:

A.

Delay Damages is intended to provide full compensation to the Employer for all damages that it is expected to suffer as a result of the delay.

B.

Delay Damages is intended to be treated as an incentive for the Contractor to perform on time.

C.

Delay Damages is not intended to remove burden for the Employer to demonstrate and prove that it has suffered any loss or damage.

D.

None of the above.

Buy Now
Questions 19

Which of the following obligations are relevant to the Engineer ' s roles with regards to insurance? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Engineer shall receive a copy of the evidence(s) demonstrating Contractor ' s payment of the necessary insurance premiums.

B.

The Engineer is entitled to take out an insurance on behalf of the Contractor, in case the Contractor fails to extend the validity of a specific insurance.

C.

The Engineer should continuously monitor that the Contractor ' s insurance policies are kept valid, and extensions are duly arranged, when necessary.

D.

The Engineer shall immediately suspend all construction activities at the Site, in case the Contractor failed to take out any necessary insurance.

Buy Now
Questions 20

Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?

Options:

A.

The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.

B.

The General Conditions allocate the risks between the parties on a fair and equitable basis.

C.

A disproportionate amount of risks is allocated to the Contractor under the General Conditions.

D.

The Contractor provides plant and designs (except as otherwise specified) and executes the other works, all in accordance with the Contract, which includes its Proposal and the Employer ' s Requirements.

Buy Now
Questions 21

Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

FIDIC Conditions of Contract for Construction ( " Red Book " ).

B.

FIDIC Conditions of Contract for Plant and Design Build ( " Yellow Book " ).

C.

FIDIC Conditions of Contract for EPC/Turnkey Projects ( " Silver Book " ).

Buy Now
Questions 22

Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?

(Choose all correct answers — multiple possibilities)

Options:

A.

The Employer is bound by the Certificate issued by the Engineer, and must make payment in full, except for any compensation arising from any claim which the Employer may have against the Contractor.

B.

The Employer is not bound by the Certificate issued by the Engineer.

C.

The Employer is bound by the Certificate issued by the Engineer and must make payment in full, irrespective of any entitlement to compensation arising from any claim which the Employer may have against the Contractor.

D.

If the Employer considers itself entitled to claim against the Contractor, notice and particulars must first be submitted under Sub-Clause 2.5. The Employer ' s entitlement is then to be agreed or determined by the Engineer, and then, incorporated as a deduction in a Payment Certificate.

Buy Now
Questions 23

A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4. However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.

Options:

A.

The Employer should check on the Appendix to Tender, Employer ' s Requirements and / or Particular Conditions. There could very well be specific requirements regarding the language in those. If that is not the case, the language of the Contract determined in Sub-Clause 1.4 and the language of the Operation and Maintained Manuals should in this case be English.

B.

If French is indeed an official second language of the region where the Plant is built, the Contractor is entitled to deliver the documents in French. The usability in terms of language is not described in Sub-Clause 5.7, so the Employer should accept the Operation and Mantained Manuals in French.

C.

Golden Principle no. 1 states: The duties, rights, obligations, roles and responsibilities of all the Contract Participants must be generally as implied in the General Conditions, and appropriate to the requirements of the project. In this case this means it is appropriate that the Operation and Maintenance Manuals are in French, as the maintenance is based in France.

D.

As the Contract is written in the English language, Sub-Clause 1.4 dictates that the Operation and Maintenance Manuals should be written in English as well.

Buy Now
Questions 24

Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ' s Requirements. Which statement is correct?

Options:

A.

Scrutinising in FIDIC Yellow Book 1999 and Silver Book 1999 means that the Contractor must ask the Employer to check the Employer ' s Requirements very well to see if the Works can be built on that location according to the Employer ' s Requirements.

B.

Scrutinising in FIDIC Silver Book 1999 means that the Contractor should read the Employer ' s Requirements very thoroughly after the contract closes and see if the Employer ' s Requirements is complete or if something is missing.

C.

Scrutinising in FIDIC Yellow Book 1999 means the same as in FIDIC Silver Book 1999. In both models it means that after the contract closes and before starting the actual making of the design, the Contractor has to read the Employer ' s Requirements very thoroughly and check on any errors, omissions or conflicts.

D.

Scrutinising in FIDIC Yellow Book 1999 means that the Contractor has the opportunity after contract close to report on any errors, mistakes or conflicts in the Employer ' s Requirements. In the FIDIC Silver Book 1999 scrutinising provides that obligation during the tender period; Contractor has the opportunity to report on any errors, mistakes or conflicts in the Employer ' s Requirements and for Employer to change it; for after contract cl

Buy Now
Questions 25

(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)

Options:

A.

You compliment the supervisor and ask him to excavate further and personally deliver the treasure to a university. No extension of time is granted.

B.

You thank the supervisor, secure the Site, instruct guarding measures, inform the Employer and authorities, and issue a Variation to cover the costs of protection measures.

C.

You inform the supervisor that a formal written notice under Sub-Clause 4.24 is required and no further instruction can be given until then.

D.

You instruct the supervisor to cover the finding and resume the Works immediately, and make a determination later.

Buy Now
Questions 26

When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition 1999)?

Options:

A.

Without undue delay after the issuance of the Taking-Over Certificate.

B.

Without undue delay after the issuance of the Performance Certificate.

C.

Within 21 days after the issuance of the Taking-Over Certificate.

D.

Within 21 days after the issuance of the Performance Certificate.

Buy Now
Questions 27

(Golden Principle 2 states that " The Particular Conditions must be drafted clearly and unambiguously. " Which statement best underlines this Golden Principle in relation to the FIDIC Red, Yellow, and Silver Books (both editions)?)

Options:

A.

Clarifications to the meaning of tender documents together with answers to tenderers’ inquiries made during the tender period by the Employer can be inconsistent. If Sub-Clause 1.5 does not provide for the right order, this Sub-Clause can be amended explicitly or implicitly, and this can be done through any of the documents mentioned in Sub-Clause 1.5.

B.

When clarifications are given during the tender period, which might impact several general conditions, it is not necessary to amend all these conditions through the Particular Conditions or to consider which exact general conditions require amendment, as such clarifications are deemed to be self-explanatory.

C.

Modifications made to the Conditions of Contract during tender negotiations that were only documented in emails between the Parties can be part of the Contract as long as those emails are subsequently included in the List of Contract documents. In such a case, it is not necessary to incorporate those modifications in, for instance, the Particular Conditions.

D.

In the Particular Conditions, all changes to the General Conditions must be clearly identified by reference to specific Sub-Clause numbers. Additionally, the Particular Conditions Sub-Clauses must clearly indicate the relationship between the newly introduced text and the corresponding General Conditions Sub-Clauses’ original text, e.g., addition, omission, replacement, or amendment.

Buy Now
Questions 28

(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)

Options:

A.

Red Book

B.

Yellow Book

C.

Silver Book

D.

All the above

Buy Now
Questions 29

If the Engineer is required to obtain the Employer ' s prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Remain silent and not do anything in the subject.

B.

The Engineer should refer the matter in subject to the DAB.

C.

Issuing the determination to the Contractor in the form and with the content agreeable to the Employer, with a remark, that it is the Employer ' s determination and not the Engineer ' s determination.

D.

Informing the Contractor of their inability of issuing the determination, in lack of the Employer ' s necessary approval.

Buy Now
Questions 30

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities)

Options:

A.

In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.

B.

If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub-Clause 21.4 to obtain a DAAB decision on it.

C.

The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.

D.

Both ' Disagreement ' and ' Dispute ' are defined terms under the Conditions of Contract.

Buy Now
Questions 31

(Under FIDIC Red and Yellow Books (both editions) the Engineer must have received technical education. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Questions 32

(In FIDIC contracts, a number of time limits are included for the Parties and the Engineer to perform various obligations. How are failures to comply with these time limits most typically being dealt with in these forms of contracts? [2017 Edition] (1 correct answer))

Options:

A.

In all these cases, the stakeholder not performing a required action within the allocated time limit loses all of his/her related rights that he/she otherwise would have in relation to this matter.

B.

If a Party fails to perform an obligation within the allocated time limit, then the failing party shall pay damages to the other Party.

C.

In these cases, there is a " deemed " outcome if the stakeholder does not take action within the pre-set period of time – all enabling to secure continuity of contractual processes.

D.

A Party ' s failure to perform an obligation within the allocated time limit would mean that the Engineer ' s or Employer’s decision becomes automatically binding.

Buy Now
Questions 33

The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP ' s)?

Options:

A.

GP 3

B.

GP 1

C.

GP 2

D.

GPA

Buy Now
Questions 34

You are the Contract Manager of the Employer for a Data Centre Project using the FIDIC Yellow Book (edition 2017). As a Contract Manager during the procurement stage, you are to explain the difference between Dispute Avoidance and Adjudication Board (DAAB) and other alternative dispute resolutions for this type of project. Which one of the following statements of its explanation is NOT correct?

Options:

A.

DAAB is to provide for a fair, timely and efficient resolution of Disputes.

B.

The function of the DAAB is to remain in place as part of the Parties ' project team to assist both Parties, equally and impartially.

C.

Avoidance of Disputes on the project and resolution of Disputes at or soon after the time they arise is a two-part role of the DAAB.

D.

DAAB provided supports for Parties during arbitration, as a witness to give factual evidence on the background for the DAAB ' s Decision.

Buy Now
Questions 35

Giving " Notice " .... [2017 edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

... is not a compulsory obligation, but " highly recommended " .

B.

... is always compulsory together with a clear indication of the relevant Sub-Clause under which the Notice is being served.

C.

... is a special obligation for the Engineer only, in order to enable him/her to manage the implementation of the contract.

D.

... is intended for written communications, in full compliance with the formal requirements outlined in the dedicated Sub-Clause.

Buy Now
Questions 36

(Which one of the following statements is correct regarding the Employer ' s Representative under the FIDIC Silver Book (edition 1999)?)

Options:

A.

The Representatives of both the Employer and the Engineer have no authority to amend the Contract at all.

B.

The Employer may appoint an Employer ' s Representative to act on his behalf under the Contract.

C.

The Employer must always appoint an Employer ' s Representative to act on his behalf under the Contract.

D.

The Employer may appoint an Employer ' s Representative to act on his behalf under the Contract but has to consult the Contractor to agree to this Representative.

Buy Now
Questions 37

(What is the maximum period for the Engineer to issue the Notice of Commencement Date?)

Options:

A.

84 days

B.

42 days

C.

21 days

D.

14 days

Buy Now
Questions 38

(Which two of the following items are new features introduced in FIDIC Red and Yellow Books (edition 2017) in respect to the procedures relating to the Programme?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The requirement to submit a revised programme by the Contractor whenever the previous programme is inconsistent with actual progress.

B.

Specifying the programming software that shall be used by the Contractor in preparation of the Programme.

C.

The requirement that any revised programmes to be submitted by the Contractor is to reflect accurately the actual progress of the works.

D.

Submission by the Contractor of a detailed time Programme to the Engineer within 28 days after receiving the notice under Sub-Clause 8.1.

Buy Now
Questions 39

You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer ' s claim on Delay Damages. You have asked Y to consider whether the Contractor ' s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor ' s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?

Options:

A.

Both you and Y are both correct.

B.

You are correct, Y is wrong.

C.

You are wrong, Y is correct.

D.

Both you and Y are wrong.

Buy Now
Questions 40

(Which of the following types of insurances belong to the basic (typical) scope of insurances? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).)

Options:

A.

Injury to persons and damage to property.

B.

Force Majeure Insurance.

C.

Insurance of Goods and other things brought to Site.

D.

Insurance for non-performance of the Works.

Buy Now
Questions 41

Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?

Options:

A.

The concentration on dispute avoidance, including an enhanced role for the Dispute Avoidance and Adjudication Board (DAAB) in this respect, and promoting cooperation between the parties during the project.

B.

New procedures requiring the Contractor to prepare and implement a Quality Management System to show compliance with the Contract requirements.

C.

A fair and balanced approach where risk is allocated to the Party that is best able to bear and control that risk.

D.

New procedures requiring the Contractor to prepare and implement a Compliance Verification System to show that the design, materials, workmanship and certain other matters all comply.

Buy Now
Questions 42

Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?

Options:

A.

Yellow Book

B.

Red Book

C.

Silver Book

D.

Yellow or Silver Book

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Apr 7, 2026
Questions: 140

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now CCM testing engine

PDF (Q&A)

$31.5  $104.99
buy now CCM pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 07 Apr 2026