CHFM Certified Health Care Facility Manager (CHFM) Questions and Answers

Questions 4

Which of the following Environment of Care (EOC) management plans requires inspecting buildings/facilities and grounds to identify hazardous conditions?

Options:

A.

Utilities Management

B.

Hazardous Materials Management

C.

Safety and Security Management

D.

Fire Safety Management

Buy Now
Questions 5

Life Safety Code® requires which of the following in an on-call sleep room?

Options:

A.

smoke alarm

B.

rated door

C.

emergency call button

D.

bathroom

Buy Now
Questions 6

Regulations governing medical gas and vacuum systems are covered under which of the following NFPA codes?

Options:

A.

70

B.

99

C.

101

D.

110

Buy Now
Questions 7

A high kW demand on a facility electrical consumption report is noted for a one-hour interval. Consumption is less than normal for the same interval. Which of the following could be the cause?

Options:

A.

high electric heat loads

B.

utilizing a generator to load shed

C.

equipment restart after a power interruption

D.

shutdown of a 1,000-ton chiller

Buy Now
Questions 8

Which of the following items are allowed to remain in the corridor in an inpatient care area?

Options:

A.

laundry hampers

B.

work stations on wheels (WOWs)

C.

recycle bins

D.

crash carts

Buy Now
Questions 9

An energy conservation project involving motion-activated light switches and electronic ballasts is expected to provide a savings of $400/month in utility costs, and reduce labor costs by $25/month. If the payback is estimated at 2.5 years, what is the estimated cost of the project?

Options:

A.

$10,200

B.

$11,250

C.

$12,000

D.

$12,750

Buy Now
Questions 10

When should the PCRA be completed for a project in an Operating Room suite?

Options:

A.

while the contractors are placing the containments

B.

before any construction has started

C.

at the conclusion of the job

D.

after the containments are installed

Buy Now
Questions 11

What document is commonly used for legal binding when a facility engages architects, engineers, contractors, or specialty consultants for work?

Options:

A.

American Institute of Architects

B.

American Bar Association

C.

Construction Owners Association of America

D.

American Arbitration Association

Buy Now
Questions 12

Which of the following is classified as regulated medical waste by the EPA?

Options:

A.

fluorescent light bulbs

B.

blood-saturated gauze

C.

urine-soaked pads

D.

home-use sharps

Buy Now
Questions 13

Construction and/or renovation project submittals and shop drawings are reviewed to ensure

Options:

A.

code compliance.

B.

compliance with plans and specifications.

C.

the project has minimal change orders.

D.

the contractor understands the intent of the specifications.

Buy Now
Questions 14

According to NFPA 70, what is the minimum working clearance required for enclosed electrical equipment with 600 volts or less?

Options:

A.

18 in.

B.

24 in.

C.

36 in.

D.

48 in.

Buy Now
Questions 15

As part of developing a HVA, which of the following elements should be considered?

events affecting demand for hospital services

cost of addressing the events

consequences of the events

likelihood of the events occurring

Options:

A.

1, 2, and 3 only

B.

1, 2, and 4 only

C.

1, 3, and 4 only

D.

2, 3, and 4 only

Buy Now
Questions 16

A code compliant, medical gas storage room contains a large number of different compressed gases. The gases are in 25 cu. ft. cylinders and in 250 cu. ft. cylinders. All cylinders are full. The Safety Officer completed a cylinder storage audit and discovered the room was over the maximum amount of compressed gas cylinders allowed by 140 cu. ft. Which of the following is the minimum number of 25 cu. ft. cylinders that must be removed to make the storage room code compliant?

Options:

A.

4

B.

5

C.

6

D.

7

Buy Now
Questions 17

Which of the following types of injuries is most likely to occur during an MRI scanning process?

Options:

A.

visual impairment

B.

radiation overexposure

C.

permanent hearing loss

D.

missile projection

Buy Now
Questions 18

"Guidelines for Preventing the Transmission of Mycobacterium Tuberculosis in Healthcare Facilities" is a document produced by the

Options:

A.

FDA.

B.

CDC.

C.

EPA.

D.

OSHA.

Buy Now
Questions 19

Which of the following types of duct-mounted humidifiers is recommended by the FGI Guidelines for Design and Construction of Hospitals and Outpatient Facilities?

Options:

A.

steam

B.

evaporative pan

C.

water spray

D.

reservoir

Buy Now
Questions 20

The cost to replace an aging chiller should be part of an organization's

Options:

A.

capital budget.

B.

project fund.

C.

depreciation fund.

D.

operating budget.

Buy Now
Questions 21

According to the AIA standard contract, final approval of shop drawings submitted by suppliers of construction materials is typically the responsibility of the

Options:

A.

architect.

B.

construction manager.

C.

owner.

D.

subcontractor.

Buy Now
Questions 22

According to the AIA Standard Form of Agreement Between Owner and Architect, who shall conduct inspections to determine the date of substantial completion?

Options:

A.

owner

B.

architect

C.

authority having jurisdiction

D.

construction manager

Buy Now
Questions 23

The occupants of a building wing complain of nausea, dizziness, or drowsiness. Which of the following is the most likely cause?

Options:

A.

mercury spill

B.

humidity levels

C.

insufficient outside air

D.

medical gas leak

Buy Now
Questions 24

A hospital is required to have what class of essential electrical system installed?

Options:

A.

Type A

B.

Type B

C.

Type 1

D.

Type 2

Buy Now
Questions 25

During an analysis of a recent fire alarm log, a higher-than-normal incidence of construction-related fire alarm activations is discovered. The following tasks must be performed:

The hospital evaluates actions to confirm that they resulted in improvements.

The hospital takes action when it does not achieve or sustain planned improvements.

The facility manager identifies and prioritizes improvement opportunities.

The hospital takes action on improvement priorities.

What is the most effective procedural sequence?

Options:

A.

4, 3, 1, 2

B.

3, 4, 2, 1

C.

3, 4, 1, 2

D.

4, 3, 2, 1

Buy Now
Questions 26

When a motor malfunctions on an air handler, what is the first step to be taken in the replacement of the motor?

Options:

A.

Megger the motor windings.

B.

Remove the motor/machine guard.

C.

Disconnect the power wiring.

D.

Initiate lockout/tagout procedures.

Buy Now
Questions 27

What is the required fire rating of a door in a 2-hour rated wall assembly?

Options:

A.

1/2 hour

B.

1 hour

C.

1 1/2 hours

D.

2 hours

Buy Now
Questions 28

When more than one employee works on equipment that must be locked-out in accordance with OSHA regulations, which of the following is an acceptable procedure to follow?

Options:

A.

Utilize a single lock and apply a tag to the energy-isolating device with the name of each employee listed.

B.

Utilize a single lock on the energy-isolating device and provide each employee with a copy of the key to the lock.

C.

Utilize a multiple lockout device on the cabinet and place one commonly keyed lock on the multiple lockout device for each employee.

D.

Utilize a multiple lockout device that allows each individual working on the equipment to apply a personal lock on the energy-isolating device.

Buy Now
Questions 29

Engineering controls required by the CDC for TB isolation rooms include

Options:

A.

use of personal protective equipment.

B.

negative air pressure of rooms.

C.

respirator fit testing of engineering employees.

D.

engineering departmental policies and procedures.

Buy Now
Questions 30

Which scenario is best for managing an inventory of repair parts?

Options:

A.

Purchase spare parts from suppliers as replacements are needed.

B.

Purchase critical spare parts from suppliers on an annual basis.

C.

Purchase one spare part in inventory for all patient equipment parts in use.

D.

Purchase one spare part in inventory for each part in use.

Buy Now
Questions 31

In an outpatient clinic classified as a business occupancy, The Joint Commission requires fire drills to be held how often?

Options:

A.

every 12 months

B.

every 6 months

C.

every 3 months

D.

once a month

Buy Now
Questions 32

According to NFPA 13, when replacing standard response sprinkler heads with quick response heads, all heads must be replaced in the entire

Options:

A.

compartment.

B.

zone.

C.

building.

D.

corridor.

Buy Now
Questions 33

A facility manager wants to communicate to leadership the need to replace an old boiler. What is the most critical piece of information that is needed to support the capital budget request?

Options:

A.

the size of the existing boiler

B.

the annual cost to maintain the new boiler

C.

time frame for replacing the boiler

D.

the ROI for replacing the boiler

Buy Now
Questions 34

A measured carbon dioxide level of 1,500 ppm in an area of a facility may indicate

Options:

A.

air exchange rates are within design.

B.

vehicular exhaust entering the area.

C.

lack of outside air.

D.

humidity/dewpoint problems.

Buy Now
Questions 35

Costs to overhaul an AHU to the extent that the life of the equipment is extended for five years are considered what type of cost?

Options:

A.

operating

B.

capital

C.

non-depreciable

D.

contingency

Buy Now
Exam Code: CHFM
Exam Name: Certified Health Care Facility Manager (CHFM)
Last Update: Nov 15, 2026
Questions: 118

PDF + Testing Engine

$42.5  $169.99

Testing Engine

$32.5  $129.99
buy now CHFM testing engine

PDF (Q&A)

$27.5  $109.99
buy now CHFM pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 15 Nov 2026