Weekend Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

Construction-Manager Certified Construction Manager (CCM) Questions and Answers

Questions 4

One word or phrase to describe the process of transitioning from construction to permanent operations by the owner is

Options:

A.

O&M.

B.

turnover.

C.

move-in.

D.

beneficial occupancy.

Buy Now
Questions 5

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

Options:

A.

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.

Send the bid back to the contractor and apologize for the mishap.

C.

Include the unopened bid. since it clearly was an oversight.

D.

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Buy Now
Questions 6

Owner's representation staff are managing the construction of a new water treatment plant. The owner has specific operational and sustainability goals they want met and are contracting the team for full commissioning services. The commissioning plan should include which of the following requirements for each party in the commissioning process?

Options:

A.

Sequencing, scheduling, design review, verification procedures

B.

Sequencing, scheduling, startup procedures, verification process

C.

Budgeting, sequencing, scheduling, documentation

D.

Sequencing, scheduling, documentation, verification procedures

Buy Now
Questions 7

Construction schedule coordination and enforcement means and methods techniques, and sequence of work are typically assigned to the construction manager under which delivery method?

Options:

A.

CM at Risk(CMAR)

B.

Design-Build (DB)

C.

Multi-Prime

D.

Design-Bid-Build (DBB)

Buy Now
Questions 8

Contract administration includes, but is not limited to, planning for implementation of drawings, specifications, and

Options:

A.

standards.

B.

owner's scope of work.

C.

permits.

D.

licenses.

Buy Now
Questions 9

As the owner’s representative, you are providing on-site construction management services to a municipality for their new design-build city hall project.

The mechanical subcontractor discovers that his ductwork will not fit in the above-ceiling area of the Mayor’s office. Which entity is best-suited to resolve this risk?

Options:

A.

Owner (Municipality)

B.

Architect (DOR)

C.

Owner’s rep

D.

Design-Build Team

Buy Now
Questions 10

ACM agent has assisted the owner by creating contractual safety requirements. By reviewing the contractor's safety submittals, the CM

Options:

A.

certifies that the submittals cover all site conditions that may occur.

B.

approves the contractors fall protection program.

C.

determines if the contract specifications have been met.

D.

accepts responsibility and liability for site safety.

Buy Now
Questions 11

An agency CM is representing the public owner of a large, complex project with numerous site challenges. The owner has received numerous differing site condition claims on previous projects on this site. The agency CM has reviewed the bid documents and believes the site challenges are clearly and sufficiently detailed for bidders. This is a design-bid-build, lump sum procurement. The apparent low bid is more than 10% lower than the next lowest bid, and the owner is very concerned that the apparent low bidder has not included the cost of mitigating the site challenges in its bid. What should the agency CM do?

Options:

A.

Ask the designer to verify that the technical specifications describing the site challenges in sufficient detail.

B.

Conduct a post-bid conference to see if all bidders included the cost of mitigating the site challenges in their bids.

C.

Conduct a post-bid interview with the apparent low bidder to determine if the bidder has a clear understanding of the site challenges.

D.

Make the recommendation to the owner to reject all bids and re-advertise the project.

Buy Now
Questions 12

BIM best assists the CM with

Options:

A.

managing time, safety, quality, and facility operations.

B.

planning, coordination, and control of the project.

C.

developing drawings and facility management.

D.

gathering energy, cost, facility maintenance, safety, and spatial data.

Buy Now
Questions 13

A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate?

Options:

A.

0.0014

B.

150

C.

286

D.

700

Buy Now
Questions 14

Which of the following statements BEST describes the recommended approach CMs should take with respect to building information modeling (BIM)?

Options:

A.

The CM should assure the owner has considered using BIM.

B.

The CM should not recommend the use of BIM.

C.

The CM should require the owner to use BIM.

D.

The CM should not discuss BIM unless requested by the owner.

Buy Now
Questions 15

A CM's responsibility for safety on the jobsite includes

Options:

A.

no obligation for safety as it is the contractor's responsibility.

B.

a professional obligation shared with others.

C.

certifying subcontractor compliance.

D.

drafting the contractor's safety plan.

Buy Now
Questions 16

Which schedule process determines the earliest times that schedule activities can start and Finish, and the total project duration?

Options:

A.

Master Schedule Review

B.

Forward Pass

C.

Schedule Update

D.

Backward Pass

Buy Now
Questions 17

The joint between a cast-in-place wall and a cast-in-place roof slab contains a waterstop for a sub-grade structure. While installing roof beams, the waterstop became dislodged from the already-placed wall. A non-conformance report was issued. The engineer of record's repair detail showed to cut and remove the dislodged waterstop sections. The authority/agency re-approved the detail as the waterstop is part of a secondary waterproofing system and the primary system was deemed sufficient. The contractor did not comply with the detail and placed the concrete roof slab over the dislodged material. In this scenario, which of the following options represents the BEST course of action?

Options:

A.

Based on the engineer of record's recommendation, the contractor should develop a repair detail and submit for approval.

B.

The concrete should be chopped out, rebar dowels should be drilled into the new slab, and the repair detail should be implemented.

C.

The agency should accept as-is and rely on the primary system.

D.

All slab concrete should be removed.

Buy Now
Questions 18

Which of the following contract types limits the potential incentive to increase profit through increasing contract costs?

Options:

A.

Time and materials

B.

Unit price

C.

Cost plus fixed fee

D.

Cost plus a percentage of cost

Buy Now
Questions 19

Program management includes the early participation of the program manager in developing and making which of the following types of decisions that become the basis of a capital improvement program?

Options:

A.

Business

B.

Safety

C.

Staffing

D.

Jurisdictional

Buy Now
Exam Name: Certified Construction Manager (CCM)
Last Update: Oct 19, 2025
Questions: 65

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now Construction-Manager testing engine

PDF (Q&A)

$31.5  $104.99
buy now Construction-Manager pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 20 Oct 2025