Spring Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

ISO-IEC-27001-Lead-Auditor PECB Certified ISO/IEC 27001 2022 Lead Auditor exam Questions and Answers

Questions 4

Scenario 5

CyberShielding Systems Inc. provides security services spanning the entire information technology infrastructure. It provides cybersecurity software, including endpoint security, firewalls, and antivirus software. CyberShielding Systems Inc. has helped various companies secure their networks for two decades through advanced products and services. Having achieved a reputation in the information and network security sector, CyberShielding Systems Inc. decided to implement a security information management system (ISMS) based on ISO/IEC 27001 and obtain a certification to better secure its internal and customer assets and gain a competitive advantage.

The certification body initiated the process by selecting the audit team for CyberShielding Systems Inc.'s ISO/IEC 27001 certification. They provided the company with the name and background information of each audit member. However, upon review, CyberShielding Systems Inc. discovered that one of the auditors did not hold the security clearance required by them. Consequently, the company objected to the appointment of this auditor. Upon review, the certification body replaced the auditor in response to CyberShielding Systems Inc.'s objection.

As part of the audit process, CyberShielding Systems Inc.'s approach to risk and opportunity determination was assessed as a standalone activity. This involved examining the organization’s methods for identifying and managing risks and opportunities. The audit team’s core objectives encompassed providing assurance on the effectiveness of CyberShielding Systems Inc.'s risk and opportunity identification mechanisms and reviewing the organization's strategies for addressing these determined risks and opportunities. During this, the audit team also identified a risk due to a lack of oversight in the firewall configuration review process, where changes were implemented without proper approval, potentially exposing the company to vulnerabilities. This finding highlighted the need for stronger internal controls to prevent such issues.

The audit team accessed process descriptions and organizational charts to understand the main business processes and controls. They performed a limited analysis of the IT risks and controls because their access to the IT infrastructure and applications was limited by third-party service provider restrictions. However, the audit team stated that the risk of a significant defect occurring in CyberShielding’s ISMS was low since most of the company's processes were automated. They therefore evaluated that the ISMS, as a whole, conforms to the standard requirements by questioning CyberShielding representatives on IT responsibilities, control effectiveness, and anti-malware measures. CyberShielding’s representatives provided sufficient and appropriate evidence to address all these questions.

Despite the agreement signed before the audit, which outlined the audit scope, criteria, and objectives, the audit was primarily focused on assessing conformity with established criteria and ensuring compliance with statutory and regulatory requirements.

Question

Based on Scenario 5, what else should CyberShielding Systems Inc. have included when defining the audit objectives?

Options:

A.

Identifying areas where the company's security practices could be improved

B.

Ensuring the audit scope focused primarily on areas with recent incidents or management concerns

C.

Limiting the audit to the verification of control documentation to maintain efficiency

Buy Now
Questions 5

An audit team leader is planning a follow-up audit after the completion of a third-party surveillance audit earlier in the year. They have decided they will verify the nonconformities that require corrections before they move on to consider corrective actions.

Based on the descriptions below, which four of the following are corrections for nonconformities identified at the surveillance?

Options:

A.

A signature missing from a client's contract for the supply of data services was added

B.

A software installation guide which had not been sent to the client along with their new system was posted out

C.

An incorrectly dated purchase order for a new network switch was rectified

D.

Data centre staff not carrying out backups in accordance with specified procedures were retrained

E.

Hard drive HD302 which had been colour-coded green (available for use) instead of red (to be destroyed) was removed from the system

F.

Scheduled management reviews, having been missed, were prioritised by the General Manager for holding on a specific date twice each following year

G.

The documented process for product shipment, which did not reflect how this activity was conducted by the despatch team, was re-written and the team trained accordingly

Buy Now
Questions 6

Which two of the following statements are true?

    The benefits of implementing an ISMS primarily result from a reduction in information security risks

Options:

A.

The benefit of certifying an ISMS is to obtain contracts from governmental institutions

B.

The purpose of an ISMS is to apply a risk management process for preserving information security

C.

The purpose of an ISMS is to demonstrate compliance with regulatory requirements

Buy Now
Questions 7

Below is Purpose of "Integrity", which is one of the Basic Components of Information Security

Options:

A.

the property that information is not made available or disclosed to unauthorized individuals

B.

the property of safeguarding the accuracy and completeness of assets.

C.

the property that information is not made available or disclosed to unauthorized individuals

D.

the property of being accessible and usable upon demand by an authorized entity.

Buy Now
Questions 8

Question

The auditor discovered that two out of 15 employees of the IT Department did not receive adequate information security training. What does this represent?

Options:

A.

Audit finding

B.

Audit evidence

C.

Information source

Buy Now
Questions 9

You are an experienced audit team leader guiding an auditor in training.

Your team is currently conducting a third-party surveillance audit of an organisation that stores data on behalf of external clients. The auditor in training has been tasked with reviewing the PHYSICAL controls listed in the Statement of Applicability (SoA) and implemented at the site.

Select four controls from the following that would you expect the auditor in training to review.

Options:

A.

Access to and from the loading bay

B.

How power and data cables enter the building

C.

Information security awareness, education, and training

D.

The conducting of verification checks on personnel

E.

The development and maintenance of an information asset inventory

F.

The operation of the site CCTV and door control systems

G.

The organisation's arrangements for maintaining equipment

Buy Now
Questions 10

Scenario 5: Cobt. an insurance company in London, offers various commercial, industrial, and life insurance solutions. In recent years, the number of Cobt's clients has increased enormously. Having a huge amount of data to process, the company decided that certifying against ISO/IEC 27001 would bring many benefits to securing information and show its commitment to continual improvement. While the company was well-versed in conducting regular risk assessments, implementing an ISMS brought major changes to its daily operations. During the risk assessment process, a risk was identified where significant defects occurred without being detected or prevented by the organizations internal control mechanisms.

The company followed a methodology to implement the ISMS and had an operational ISMS in place after only a few months After successfully implementing the ISMS, Cobt applied for ISO/IEC 27001 certification Sarah, an experienced auditor, was assigned to the audit Upon thoroughly analyzing the audit offer, Sarah accepted her responsibilities as an audit team leader and immediately started to obtain general information about Cobt She established the audit criteria and objective, planned the audit, and assigned the audit team members' responsibilities.

Sarah acknowledged that although Cobt has expanded significantly by offering diverse commercial and insurance solutions, it still relies on some manual processes Therefore, her initial focus was to gather information on how the company manages its information security risks Sarah contacted Cobt's representatives to request access to information related to risk management for the off-site review, as initially agreed upon for part of the audit However, Cobt later refused, claiming that such information is too sensitive to be accessed outside of the company This refusal raised concerns about the audit's feasibility, particularly regarding the availability and cooperation of the auditee and access to evidence Moreover, Cobt raised concerns about the audit schedule, stating that it does not properly reflect the recent changes the company made It pointed out that the actions to be performed during the audit apply only to the initial scope and do not encompass the latest changes made in the audit scope

Sarah also evaluated the materiality of the situation, considering the significance of the information denied for the audit objectives. In this case, the refusal by Cobt raised questions about the completeness of the audit and its ability to provide reasonable assurance. Following these situations, Sarah decided to withdraw from the audit before a certification agreement was signed and communicated her decision to Cobt and the certification body. This decision was made to ensure adherence to audit principles and maintain transparency, highlighting her commitment to consistently upholding these principles.

Based on the scenario above, answer the following question:

Question:

Based on Scenario 5, Sarah decided to withdraw from the audit before a certification agreement was signed. Is this acceptable?

Options:

A.

Yes, Sarah can withdraw from the audit but only if the certification body approves her withdrawal

B.

Yes, there is no relation between Sarah’s withdrawal from the audit and the certification agreement

C.

No, the certification agreement is directly tied to the auditor’s presence

Buy Now
Questions 11

Scenario 2: Knight is an electronics company from Northern California, US that develops video game consoles. Knight has more than 300 employees worldwide. On the

fifth anniversary of their establishment, they have decided to deliver the G-Console, a new generation video game console aimed for worldwide markets. G-Console is

considered to be the ultimate media machine of 2021 which will give the best gaming experience to players. The console pack will include a pair of VR headset, two

games, and other gifts.

Over the years, the company has developed a good reputation by showing integrity, honesty, and respect toward their customers. This good reputation is one of the

reasons why most passionate gamers aim to have Knight's G-console as soon as it is released in the market. Besides being a very customer-oriented company, Knight

also gained wide recognition within the gaming industry because of the developing quality. Their prices are a bit higher than the reasonable standards allow.

Nonetheless, that is not considered an issue for most loyal customers of Knight, as their quality is top-notch.

Being one of the top video game console developers in the world, Knight is also often the center of attention for malicious activities. The company has had an

operational ISMS for over a year. The ISMS scope includes all departments of Knight, except Finance and HR departments.

Recently, a number of Knight's files containing proprietary information were leaked by hackers. Knight's incident response team (IRT) immediately started to analyze

every part of the system and the details of the incident.

The IRT's first suspicion was that Knight's employees used weak passwords and consequently were easily cracked by hackers who gained unauthorized access to their

accounts. However, after carefully investigating the incident, the IRT determined that hackers accessed accounts by capturing the file transfer protocol (FTP) traffic.

FTP is a network protocol for transferring files between accounts. It uses clear text passwords for authentication.

Following the impact of this information security incident and with IRT's suggestion, Knight decided to replace the FTP with Secure Shell (SSH) protocol, so anyone

capturing the traffic can only see encrypted data.

Following these changes, Knight conducted a risk assessment to verify that the implementation of controls had minimized the risk of similar incidents. The results of

the process were approved by the ISMS project manager who claimed that the level of risk after the implementation of new controls was in accordance with the

company's risk acceptance levels.

Based on this scenario, answer the following question:

Based on scenario 2, the ISMS project manager approved the results of risk assessment. Is this acceptable?

Options:

A.

No, the risk remaining after the treatment of risk should be approved by the top management at any stage

B.

No, the risk remaining after the implementation of new controls for the ISMS should be approved by the ISMS team

C.

Yes, the risk remaining after the treatment of risk should be approved by the ISMS project manager

Buy Now
Questions 12

Please match the following situations to the type of audit required.

ISO-IEC-27001-Lead-Auditor Question 12

Options:

Buy Now
Questions 13

Question:

An organization is evaluating the materiality of different processes within its ISMS. It is assessing the direct expenses involved with personnel, third-party services, and general fees. Which factor of materiality is the company primarily considering?

Options:

A.

Cost of operations

B.

Cost of the process

C.

Potential cost of errors or nonconformities

Buy Now
Questions 14

Question:

A cybersecurity company implemented an access control software that allows only authorized personnel to access sensitive files. Which type of control has the company implemented in this case?

Options:

A.

Preventive control

B.

Detective control

C.

Corrective control

Buy Now
Questions 15

Scenario 8

[Scenario text identical to Question 69]

Question

Following the initial audit, when is a surveillance audit typically conducted?

Options:

A.

Only when the auditee requests additional evaluations

B.

During the first and second years of certification

C.

Five years after the initial certification

Buy Now
Questions 16

Question

To verify conformity to control 8.15 Logging of ISO/IEC 27001 Annex A, the audit team studied a sample of server logs to determine if they could be edited or deleted. Which audit procedure did the audit team use?

Options:

A.

Analysis

B.

Technical verification

C.

Observation

Buy Now
Questions 17

The data center at which you work is currently seeking ISO/IEC27001:2022 certification. In preparation for your initial certification visit a number of internal audits have been carried out by a colleague working at another data centre within your Group. They secured their ISO/IEC 27001:2022 certificate earlier in the year.

You have just qualified as an Internal ISMS auditor and your manager has asked you to review the audit process and audit findings as a final check before the external Certrfication Body arrives.

Which six of the following would cause you concern in respect of conformity to ISO/IEC 27001:2022 requirements?

Options:

A.

The audit programme shows management reviews taking place at irregular intervals during the year

B.

Audit reports are not held in hardcopy (i.e. on paper). They are only stored as ".POF documents on the organisation's intranet

C.

The audit programme does not take into account the relative importance of information security processes

D.

The audit programme mandates auditors must be independent of the areas they audit in order to satisfy the requirements of ISO/IEC 27001:2022

E.

Although the scope for each internal audit has been defined, there are no audit criteria defined for the audits carried out to date

F.

Audit reports to date have used key performance indicator information to focus solely on the efficiency of ISMS processes

G.

The audit programme does not reference audit methods or audit responsibilities

Buy Now
Questions 18

You are an experienced ISMS audit team leader. An auditor in training has approached you to ask you to clarify the different types of audits she may be required to undertake.

Match the following audit types to the descriptions.

To complete the table click on the blank section you want to complete so that It is highlighted In fed, and then click on the applicable text from the options below. Alternatively, you may drag and drop each option to the appropriate blank section.

ISO-IEC-27001-Lead-Auditor Question 18

Options:

Buy Now
Questions 19

You are performing an ISMS audit at a European-based residential nursing home called ABC that provides healthcare services. The next step in your audit plan is to verify the effectiveness of the continual improvement process.

During the audit, you learned most of the residents' family members (90%) receive WeCare medical devices promotion advertisements through email and SMS once a week via ABC's healthcare mobile app. All of them do not agree on the use of the collected personal data for marketing or any other purposes than nursing and medical care on the signed service agreement with ABC. They have very strong reason to believe that ABC is leaking residents' and family members' personal information to a non-relevant third party and they have filed complaints.

The Service Manager says that, after investigation, all these complaints have been treated as nonconformities. The corrective actions have been planned and implemented according to the nonconformity and corrective management procedure (Document reference ID: ISMS_L2_10.1, version 1).

You write a nonconformity which you will follow up on later. Select the words that best complete the sentence:

ISO-IEC-27001-Lead-Auditor Question 19

Options:

Buy Now
Questions 20

You are an experienced ISMS audit team leader providing guidance to an auditor in training.

The auditor in training appears to be confused about the interpretation of competence in ISO 27001:2022 and is seeking clarification from you that his understanding is correct. He sets out a series of mini scenarios and asks you which of these you would attribute to a lack of competence. Select four correct options.

Options:

A.

An employee recently transferred from the IT networks team to Software development was unaware of the need to complete product release forms prior to shipping

B.

A senior programmer did not check their coding for errors as they were running late for a doctor's appointment

C.

A new starter was unable to switch on CCTV monitoring because they had not been shown how to do this

D.

An IT technician failed to configure a new model of server correctly as a result of not reading the supplied instructions

E.

An experienced receptionist allowed a contractor she recognised to enter the data centre without his access card

F.

A system administrator deleted two live accounts as well as five redundant accounts as a result of receiving an incorrect instruction

G.

A data centre operator inadvertently placed a backup tape into an incorrect drive because they were in a hurry to move on to another task

Buy Now
Questions 21

Select the words that best complete the sentence:

To complete the sentence with the best word(s), click on the blank section you want to complete so that it is highlighted in red, and then click on the applicable text from the options below. Alternatively, you may drag and drop the option to the appropriate blank section.

ISO-IEC-27001-Lead-Auditor Question 21

Options:

Buy Now
Questions 22

You are an experienced ISMS audit team leader providing instruction to an auditor in training. They are unclear in their understanding of risk processes and ask you to provide them with an example of each of the processes detailed below.

Match each of the descriptions provided to one of the following risk management processes.

To complete the table click on the blank section you want to complete so that it is highlighted in red, and then click on the applicable text from the options below. Alternatively, you may drag and drop each option to the appropriate blank section.

ISO-IEC-27001-Lead-Auditor Question 22

Options:

Buy Now
Questions 23

An organization does not check the source code of the updated version of an application when it is updated automatically. Thus, the application may be open to

unauthorized modifications. This represents a _________________ that may impact information ___________________

Options:

A.

Threat, (2) confidentiality

B.

Risk, (2) availability

C.

Vulnerability, (2) integrity

Buy Now
Questions 24

Question:

Finnco, a subsidiary of a certification body, provided ISMS consultancy services to an organization. Considering this scenario, when can the certification body certify the organization?

Options:

A.

There is no time constraint in such a situation

B.

The certification body can certify the organization immediately after consulting services end

C.

If a minimum period of two years has passed since the last consulting activities

Buy Now
Questions 25

You are an experienced ISMS audit team leader, talking to an Auditor in training who has been assigned to your audit team. You want to ensure that they understand the importance of the Check stage of the Plan-Do-Check-Act cycle in respect of the operation of the information security management system.

You do this by asking him to select the words that best complete the sentence:

To complete the sentence with the best word(s), click on the blank section you want to complete so that it is highlighted in red, and then click on the applicable text from the options below. Alternatively, you may drag and drop the option to the appropriate blank section.

ISO-IEC-27001-Lead-Auditor Question 25

Options:

Buy Now
Questions 26

Question:

What is the purpose of using a combination of audit test plans?

Options:

A.

To verify compliance with standards and criteria through multiple methods

B.

To ensure that all areas of the organization are audited equally

C.

To reduce the need for frequent audits

Buy Now
Questions 27

Information or data that are classified as ______ do not require labeling.

Options:

A.

Public

B.

Internal

C.

Confidential

D.

Highly Confidential

Buy Now
Questions 28

You are an experienced ISMS audit team leader providing guidance to an ISMS auditor in training. They have been asked to carry out an assessment of external providers and have prepared a checklist containing the following activities. They have asked you to review their checklist to confirm that the actions they are proposing are appropriate.

The audit they have been invited to participate in is a third-party surveillance audit of a data centre . The data centre agent is part of a wider telecommunication group. Each data centre within the group operates its own ISMS and holds its own certificate.

Select three options that relate to ISO/IEC 27001:2022's requirements regarding external providers.

Options:

A.

I will check the other data centres are treated as external providers, even though they are part of the same telecommunication group

B.

I will ensure external providers have a documented process in place to notify the organisation of any risks arising from the use of its products or services

C.

I will ensure that the organisation has a reserve external provider for each process it has identified as critical to preservation of the confidentiality, integrity and accessibility of its information

D.

I will limit my audit activity to externally provided processes as there is no need to audit externally provided products of services

E.

I will ensure the organization is regularly monitoring, reviewing and evaluating external provider performance

F.

I will ensure the organization is has determined the need to communicate with external providers regarding the ISMS

G.

I will ensure that top management have assigned roles and responsibilities for those providing external ISMS processes as well as internal ISMS processes

Buy Now
Questions 29

The audit team leader decided to involve a technical expert as part of the audit team, so they could fill the potential gaps of the audit team members' knowledge. What should the audit team leader consider in this case?

Options:

A.

The technical expert is allowed to take decisions related to the audit process when it is needed

B.

The technical expert should discuss their concerns directly with the certification body, and not with the auditor

C.

The technical expert can communicate their audit findings to the auditee only through one of the audit team members

Buy Now
Questions 30

You have a hard copy of a customer design document that you want to dispose off. What would you do

Options:

A.

Throw it in any dustbin

B.

Shred it using a shredder

C.

Give it to the office boy to reuse it for other purposes

D.

Be environment friendly and reuse it for writing

Buy Now
Questions 31

The data centre at which you work is currently seeking ISO/IEC27001:2022 certification. In preparation for your initial certification visit, several internal audits have been carried out by a colleague working at another data centre within your Group. They secured their own ISO/IEC 27001:2022 certificate earlier in the year.

You have just qualified as an Internal ISMS auditor and your manager has asked you to review the audit process and audit findings as a final check before the external Certification Body arrives.

Which four of the following would cause you concern in respect of conformity to ISO/IEC 27001:2022 requirements?

Options:

A.

Although the scope for each internal audit has been defined, there are no audit criteria defined for the audits carried out to date.

B.

Audit reports are not held in hardcopy (i.e. on paper). They are only stored as *. PDF documents on the organisation's intranet.

C.

The audit process states the results of audits will be made available to 'relevant' managers, not top management.

D.

The audit programme does not reference audit methods or audit responsibilities.

E.

The audit programme does not take into account the relative importance of information security processes.

F.

The audit programme does not take into account the results of previous audits.

G.

The audit programme has not been signed as 'approved by Top Management.

Buy Now
Questions 32

Question

An organization scheduled an internal audit to evaluate the ISMS effectiveness. However, it did not define the audit scope and clear audit objectives. As a result, the internal auditor overlooked critical departments handling sensitive information.

What risk associated with the audit program was present in this scenario?

Options:

A.

Planning risk

B.

Communication risk

C.

Resource risk

Buy Now
Questions 33

You are the person responsible for managing the audit programme and deciding the size and composition of the audit team for a specific audit. Select the two factors that should be considered.

    The audit scope and criteria

Options:

A.

Customer relationships

B.

The overall competence of the audit team needed to achieve audit objectives

C.

Seniority of the audit team leader

D.

The cost of the audit

E.

The duration preferred by the auditee

Buy Now
Questions 34

Select the words that best complete the sentence to describe an audit finding.

ISO-IEC-27001-Lead-Auditor Question 34

Options:

Buy Now
Questions 35

As the Information Security Management System audit team leader, you are conducting a second-party audit of an international logistics company on behalf of an online retailer. During the audit, one of your team members reports a nonconformity relating to control 5.18 (Access rights) of Appendix A of ISO/IEC 27001:2022. She found evidence that removing the server access protocols of 20 people who left in the last 3 months took up to 1 week whereas the policy required removing access within 24 hours of their departure.

When the auditee was asked why there was a delay in removing access they replied, 'no one was available in the IT department during that period as a result of COVID-19. As soon as an IT officer became available the rights were removed.

You note that she intends to raise a minor non-conformity against Access rights control (5.18). How should you respond to this?

Options:

A.

Agree with the raising of a minor non-conformity but against control 5.15, not 5.18.

B.

Agree with the raising of the minor non-conformity against 5.18.

C.

Disagree with the raising of a minor conformity as appropriate action was taken at the earliest opportunity Take no further action.

D.

Disagree with the raising of the minor nonconformity as appropriate action was taken at the earliest opportunity. Instead raise an opportunity for improvement.

E.

Disagree with the raising of the minor nonconformity, there is sufficient evidence to justify an escalation to a major non-conformity.

F.

Require additional audit evidence to be obtained before determining whether a non-conformity is appropriate.

Buy Now
Questions 36

Scenario 5: Data Grid Inc. is a well-known company that delivers security services across the entire information technology infrastructure. It provides cybersecurity software, including endpoint security, firewalls, and antivirus software. For two decades, Data Grid Inc. has helped various companies secure their networks through advanced products and services. Having achieved reputation in the information and network security field, Data Grid Inc. decided to obtain the ISO/IEC 27001 certification to better secure its internal and customer assets and gain competitive advantage.

Data Grid Inc. appointed the audit team, who agreed on the terms of the audit mandate. In addition, Data Grid Inc. defined the audit scope, specified the audit criteria, and proposed to close the audit within five days. The audit team rejected Data Grid Inc.'s proposal to conduct the audit within five days, since the company has a large number of employees and complex processes. Data Grid Inc. insisted that they have planned to complete the audit within five days, so both parties agreed upon conducting the audit within the defined duration. The audit team followed a risk-based auditing approach.

To gain an overview of the main business processes and controls, the audit team accessed process descriptions and organizational charts. They were unable to perform a deeper analysis of the IT risks and controls because their access to the IT infrastructure and applications was restricted. However, the audit team stated that the risk that a significant defect could occur to Data Grid Inc.'s ISMS was low since most of the company's processes were automated. They therefore evaluated that the ISMS, as a whole, conforms to the standard requirements by asking the representatives of Data Grid Inc. the following questions:

•How are responsibilities for IT and IT controls defined and assigned?

•How does Data Grid Inc. assess whether the controls have achieved the desired results?

•What controls does Data Grid Inc. have in place to protect the operating environment and data from malicious software?

•Are firewall-related controls implemented?

Data Grid Inc.'s representatives provided sufficient and appropriate evidence to address all these questions.

The audit team leader drafted the audit conclusions and reported them to Data Grid Inc.'s top management. Though Data Grid Inc. was recommended for certification by the auditors, misunderstandings were raised between Data Grid Inc. and the certification body in regards to audit objectives. Data Grid Inc. stated that even though the audit objectives included the identification of areas for potential improvement, the audit team did not provide such information.

Based on this scenario, answer the following question:

Based on scenario 5, the audit team assessed the ISMS as a whole, rather than assessing the effectiveness and conformity of each process. Is this acceptable?

Options:

A.

Yes, due to time constraints for the audit completion, the audit team must obtain absolute assurance by assessing the ISMS as a whole

B.

No, the audit team should obtain assurance that the ISMS conforms to the standard requirements by assessing each process

C.

Yes, if the audit team has obtained a reasonable assurance that helps them evaluate the ISMS conformity

Buy Now
Questions 37

A data processing tool crashed when a user added more data in the buffer than its storage capacity allows. The incident was caused by the tool's inability to bound check arrays. What kind of vulnerability is this?

Options:

A.

Intrinsic vulnerability, because inability to bound check arrays is a characteristic of the data processing tool

B.

Extrinsic vulnerability, because inability to bound check arrays is related to external factors

C.

None, the tool's inability to bound check arrays is not a vulnerability, but a threat

Buy Now
Questions 38

You are an experienced ISMS audit team leader guiding an auditor in training. She asks you about the grading of nonconformities in audit reports. You decide to test her knowledge by asking her which four of the following statements are true.

Options:

A.

Major nonconformities may be subject to on-site follow up

B.

Nonconformities must be graded only using the terms 'major' or 'minor'

C.

The action taken to address major nonconformities is typically more substantial than the action taken to address minor nonconformities

D.

Very minor nonconformities should be re-graded as opportunities for improvement

E.

Several minor nonconformities can be grouped into a major nonconformity

F.

The grading of nonconformities must be explained to the auditee at the opening meeting

G.

The auditee is always responsible for determining the criteria for grading nonconformities

Buy Now
Questions 39

Scenario 5: Data Grid Inc. is a well-known company that delivers security services across the entire information technology infrastructure. It provides cybersecurity software, including endpoint security, firewalls, and antivirus software. For two decades, Data Grid Inc. has helped various companies secure their networks through advanced products and services. Having achieved reputation in the information and network security field, Data Grid Inc. decided to obtain the ISO/IEC 27001 certification to better secure its internal and customer assets and gain competitive advantage.

Data Grid Inc. appointed the audit team, who agreed on the terms of the audit mandate. In addition, Data Grid Inc. defined the audit scope, specified the audit criteria, and proposed to close the audit within five days. The audit team rejected Data Grid Inc.'s proposal to conduct the audit within five days, since the company has a large number of employees and complex processes. Data Grid Inc. insisted that they have planned to complete the audit within five days, so both parties agreed upon conducting the audit within the defined duration. The audit team followed a risk-based auditing approach.

To gain an overview of the main business processes and controls, the audit team accessed process descriptions and organizational charts. They were unable to perform a deeper analysis of the IT risks and controls because their access to the IT infrastructure and applications was restricted. However, the audit team stated that the risk that a significant defect could occur to Data Grid Inc.'s ISMS was low since most of the company's processes were automated. They therefore evaluated that the ISMS, as a whole, conforms to the standard requirements by asking the representatives of Data Grid Inc. the following questions:

•How are responsibilities for IT and IT controls defined and assigned?

•How does Data Grid Inc. assess whether the controls have achieved the desired results?

•What controls does Data Grid Inc. have in place to protect the operating environment and data from malicious software?

•Are firewall-related controls implemented?

Data Grid Inc.'s representatives provided sufficient and appropriate evidence to address all these questions.

The audit team leader drafted the audit conclusions and reported them to Data Grid Inc.'s top management. Though Data Grid Inc. was recommended for certification by the auditors, misunderstandings were raised between Data Grid Inc. and the certification body in regards to audit objectives. Data Grid Inc. stated that even though the audit objectives included the identification of areas for potential improvement, the audit team did not provide such information.

Based on this scenario, answer the following question:

Data Grid Inc. is responsible for all the actions below, EXCEPT:

Options:

A.

Specifying the audit criteria

B.

Appointing the audit team

C.

Defining the audit scope

Buy Now
Questions 40

You are conducting an ISMS audit. The next step in your audit plan is to verify that the organisation's

information security risk treatment plan has been established and implemented properly. You decide to

interview the IT security manager.

You: Can you please explain how the organisation performs its information security risk assessment and

treatment process?

IT Security Manager: We follow the information security risk management procedure which generates a

risk treatment plan.

Narrator: You review risk treatment plan No. 123 relating to the planned installation of an electronic

(invisible) fence to improve the physical security of the nursing home. You found the risk treatment plan was

approved by IT Security Manager.

You: Who is responsible for physical security risks?

IT Security Manager: The Facility Manager is responsible for the physical security risk. The IT department helps them to monitor the alarm. The Facility Manager is authorized to approve the budget for risk treatment plan No. 123.

You: What residual information security risks exist after risk treatment plan No. 123 was implemented?

IT Security Manager: There is no information for the acceptance of residual information security risks as far as I know.

You prepare your audit findings. Select three options for findings that are justified in the scenario.

Options:

A.

Nonconformity (NC) - The information for the acceptance of residual information security risks should be updated after the risk treatment is implemented. Clause 6.1.3.f

B.

There is an opportunity for improvement (OI) to conduct security checks on the perimetre fence

C.

There is an opportunity for improvement (OI) once the Electronic (invisible) fence is installed. Residents' physical security is improved

D.

Nonconformity (NC) - Top management must ensure that the resources needed for the ISMS are available. Clause 5.1.c

E.

Nonconformity (NC) - The IT security manager should be aware of and understand his authority and area of responsibility. Clause 7.3

F.

Nonconformity (NC) - The organization should provide the resources needed for the continual improvement of the ISMS. Clause 7.1

G.

Nonconformity (NC) - The risk treatment plan No. 123 should be approved by the risk owner, the Facility Manager in this case. Clause 6.1.3.f

Buy Now
Questions 41

Scenario:

Northstorm is an online retail shop offering unique vintage and modern accessories. It initially entered a small market but gradually grew thanks to the development of the overall e-commerce landscape. Northstorm works exclusively online and ensures efficient payment processing, inventory management, marketing tools, and shipment orders. It uses prioritized ordering to receive, restock, and ship its most popular products.

Northstorm has traditionally managed its IT operations by hosting its website and maintaining full control over its infrastructure, including hardware, software, and data administration. However, this approach hindered its growth due to the lack of responsive infrastructure. Seeking to enhance its e-commerce and payment systems, Northstorm opted to expand its in-house data centers, completing the expansion in two phases over three months. Initially, the company upgraded its core servers, point-of-sale, ordering, billing, database, and backup systems. The second phase involved improving mail, payment, and network functionalities. Additionally, during this phase, Northstorm adopted an international standard for personally identifiable information (PII) controllers and PII processors regarding PII processing to ensure its data handling practices were secure and compliant with global regulations.

Despite the expansion, Northstorm's upgraded data centers failed to meet its evolving business demands. This inadequacy led to several new challenges, including issues with order prioritization. Customers reported not receiving priority orders, and the company struggled with responsiveness. This was largely due to the main server's inability to process orders from YouDecide, an application designed to prioritize orders and simulate customer interactions. The application, reliant on advanced algorithms, was incompatible with the new operating system (OS) installed during the upgrade.

Faced with urgent compatibility issues, Northstorm quickly patched the application without proper validation, leading to the installation of a compromised version. This security lapse resulted in the main server being affected and the company's website going offline for a week. Recognizing the need for a more reliable solution, the company decided to outsource its website hosting to an e-commerce provider. The company signed a confidentiality agreement concerning product ownership and conducted a thorough review of user access rights to enhance security before transitioning.

Question:

Which of the following situations represents a vulnerability in Northstorm’s systems?

Options:

A.

The new version of the application directly affected the main server

B.

The need for a replacement version of the application

C.

The new version of the application was not legitimate

Buy Now
Questions 42

Scenario 3

NightCore, a multinational technology enterprise headquartered in the United States, specializes in e-commerce, cloud computing, digital streaming, and artificial intelligence (AI). After having an information security management system (ISMS) implemented for over a year, NightCore contracted a certification body to perform an audit for ISO/IEC 27001 certification.

The certification body formed a team of five auditors, with Jack as a team leader. Jack is renowned for his extensive auditing experience in risk management, information security controls, and incident management. His skill set aligns well with the requirements of auditing principles and processes, enabling him to effectively comprehend the audit scope and apply relevant criteria effectively. Jack also demonstrates a solid understanding of NightCore’s organizational structure, purpose, and management practices and the statutory and regulatory requirements applicable to its activities.

The audit carried out by the audit team followed a rational method to reach reliable and reproducible conclusions systematically. The audit team recognized that only information capable of being verified to some extent should be considered valid evidence. In some rare instances during the audit where the verification of certain information posed challenges and where its degree of verifiability was low, the auditors exercised their professional judgment to assess the reliability and determine the level of reliance that could be placed on such evidence.

During the audit, the auditors documented their observations and inspection notes regarding the operational planning and control of NightCore’s ISMS operations. They also recorded observations of NightCore’s inventory of information and associated assets. Additionally, the auditors reviewed the configuration of firewalls implemented to secure connections to network services.

As the audit approached its final stages, NightCore’s commitment to upholding the highest levels of information security became evident. With ISO/IEC 27001 certification within reach, NightCore is well-positioned to achieve ISO/IEC 27001 certification, enhancing its reputation in the technology sector.

Question

During the audit at NightCore, the auditors focused on key areas of ISMS operations, including operational planning, asset inventory, and firewall configurations. What type of evidence did the auditors collect during the audit conducted at NightCore?

Options:

A.

Analytical and documentary evidence

B.

Physical and technical evidence

C.

Mathematical evidence

Buy Now
Questions 43

Which statement below best describes the relationship between information security aspects?

Options:

A.

Threats exploit vulnerabilities to damage or destroy assets

B.

Controls protect assets by reducing threats

C.

Risk is a function of vulnerabilities that harm assets

Buy Now
Questions 44

Which one option best describes the purpose of retaining documented information related to the Information Security Management System (ISMS) of an organisation?

Options:

A.

To ensure that all workers will follow the established procedure.

B.

To show compliance with legal requirements.

C.

To show objective evidence to third-party auditors.

D.

To the extent necessary, to have confidence that the processes have been carried out as planned.

Buy Now
Questions 45

You are performing an ISMS audit at a residential nursing home that provides healthcare services. The next step in your audit plan is to verify the information security incident management process. The IT Security Manager presents the information

security incident management procedure (Document reference ID: ISMS_L2_16, version 4) and explains that the process is

based on ISO/IEC 27035-1:2016.

You review the document and notice a statement "any information security weakness, event, and incident should be reported

to the Point of Contact (PoC) within 1 hour after identification". When interviewing staff, you found that there were differences

in the understanding of the meaning of "weakness, event, and incident".

The IT Security Manager explained that an online "information security handling" training seminar was conducted 6 months

ago. All of the interviewed persons participated in and passed the reporting exercise and course assessment.

You are preparing the audit findings. Select two options that are correct.

Options:

A.

There is a nonconformity (NC). The information security incident training has failed. This is not conforming with clause 7.2 and control A.6.3.

B.

There is a nonconformity (NC). The terminology of the the incident management reporting process is unclear as evidenced by staff misunderstanding of the meaning of "weakness, event and incident". This is not conforming with clause 9.1 and control A.5.24.

C.

There is an opportunity for improvement (OFI). The information security incident training effectiveness can be improved. This is relevant to clause 7.2 and control A.6.3.

D.

There is an opportunity for improvement (OFI). The information security weaknesses, events, and incidents are reported. This is relevant to clause 9.1 and control A.5.24.

E.

There is no nonconformance. The information security handling training has been effective. This conforms with clause 7.2 and control A.6.3.

F.

There is no nonconformance. The information security weaknesses, events, and incidents are reported. This conforms with clause 9.1 and control A.5.24.

Buy Now
Questions 46

Question

A retail company experienced a malware infection that bypassed its existing security measures. To minimize damage, remove the malware, and restore affected systems to normal operation, what type of controls should the company implement?

Options:

A.

Corrective

B.

Detective

C.

Preventive

Buy Now
Questions 47

You are an ISMS audit team leader preparing to chair a closing meeting following a third-party surveillance audit. You are drafting a closing meeting agenda setting out the topics you wish to discuss with your auditee.

Which one of the following would be appropriate for inclusion?

Options:

A.

A detailed explanation of the certification body's complaints process

B.

An explanation of the audit plan and its purpose

C.

A disclaimer that the result of the audit is based on the sampling of evidence

D.

Names of auditees associated with nonconformities

Buy Now
Questions 48

You are carrying out a third-party surveillance audit of a client's ISMS. You are currently in the secure storage area of the data centre where the organisation's customers are able to temporarily locate equipment coming into or going out of the site. The equipment is contained within locked cabinets and each cabinet is allocated to a single, specific client.

Out of the corner of your eye you spot movement near the external door of the storage area. This is followed by a loud noise. You ask the guide what is going on. They tell you that recent high rainfall has raised local river levels and caused an infestation of rats. The noise was a specialist pest control stunning device being triggered. You check the device in the corner and find there is a large immobile rat contained within it.

What three actions would be appropriate to take next?

Options:

A.

Take no further action. This is an ISMS audit, not an environmental management system audit

B.

Investigate whether pest infestation is an identified risk and if so, what risk treatment is to be applied

C.

Determine whether the high levels of rainfall have had other impacts on data centre operations e.g. damage to infrastructure, access issues for clients, invocation of business continuity arrangements

D.

Raise a nonconformity against control 7.4 Physical Security monitoring

E.

Raise a nonconformity against control 7.2 Physical Entry

F.

Check with the guide that they intend to initiate the organisation's information security incident process

G.

Inspect the client cabinets for signs of rodent ingress and record your findings as audit evidence

Buy Now
Questions 49

Question

Factors such as costs related to nonconformities or penalties in case of failure to comply with legal and contractual obligations are evaluated during the definition of which of the following?

Options:

A.

Materiality

B.

Audit risks

C.

Reasonable assurance

Buy Now
Questions 50

Scenario 8: Tessa. Malik, and Michael are an audit team of independent and qualified experts in the field of security, compliance, and business planning and strategies. They are assigned to conduct a certification audit in Clastus, a large web design company. They have previously shown excellent work ethics, including impartiality and objectiveness, while conducting audits. This time, Clastus is positive that they will be one step ahead if they get certified against ISO/IEC 27001.

Tessa, the audit team leader, has expertise in auditing and a very successful background in IT-related issues, compliance, and governance. Malik has an organizational planning and risk management background. His expertise relies on the level of synthesis and analysis of an organization's security controls and its risk tolerance in accurately characterizing the risk level within an organization On the other hand, Michael is an expert in the practical security of controls assessment by following rigorous standardized programs.

After performing the required auditing activities, Tessa initiated an audit team meeting They analyzed one of Michael s findings to decide on the issue objectively and accurately. The issue Michael had encountered was a minor nonconformity in the organization's daily operations, which he believed was caused by one of the organization's IT technicians As such, Tessa met with the top management and told them who was responsible for the nonconformity after they inquired about the names of the persons responsible

To facilitate clarity and understanding, Tessa conducted the closing meeting on the last day of the audit. During this meeting, she presented the identified nonconformities to the Clastus management. However, Tessa received advice to avoid providing unnecessary evidence in the audit report for the Clastus certification audit, ensuring that the report remains concise and focused on the critical findings.

Based on the evidence examined, the audit team drafted the audit conclusions and decided that two areas of the organization must be audited before the certification can be granted. These decisions were later presented to the auditee, who did not accept the findings and proposed to provide additional information. Despite the auditee's comments, the auditors, having already decided on the certification recommendation, did not accept the additional information. The auditee's top management insisted that the audit conclusions did not represent reality, but the audit team remained firm in their decision.

Based on the scenario above, answer the following question:

Question:

Was the closing meeting conducted accordingly?

Options:

A.

Yes, the closing meeting is conducted on the last day of the audit

B.

No, it should be conducted after the audit conclusions have been drafted

C.

No, it should be conducted several weeks after the on-site audit

Buy Now
Questions 51

Scenario 3: NightCore is a multinational technology company based in the United States that focuses on e-commerce, cloud computing, digital streaming, and artificial intelligence. After having an information security management system (ISMS) implemented for over 8 months, they contracted a certification body to conduct a third party audit in order to get certified against ISO/IEC 27001.

The certification body set up a team of seven auditors. Jack, the most experienced auditor, was assigned as the audit team leader. Over the years, he received many well known certifications, such as the ISO/IEC 27001 Lead Auditor, CISA, CISSP, and CISM.

Jack conducted thorough analyses on each phase of the ISMS audit, by studying and evaluating every information security requirement and control that was implemented by NightCore. During stage 2 audit. Jack detected several nonconformities. After comparing the number of purchased invoices for software licenses with the software inventory, Jack found out that the company has been using the illegal versions of a software for many computers. He decided to ask for an explanation from the top management about this nonconformity and see whether they were aware about this. His next step was to audit NightCore's IT Department. The top management assigned Tom, NightCore's system administrator, to act as a guide and accompany Jack and the audit team toward the inner workings of their system and their digital assets infrastructure.

While interviewing a member of the Department of Finance, the auditors discovered that the company had recently made some unusual large transactions to one of their consultants. After gathering all the necessary details regarding the transactions. Jack decided to directly interview the top management.

When discussing about the first nonconformity, the top management told Jack that they willingly decided to use a copied software over the original one since it was cheaper. Jack explained to the top management of NightCore that using illegal versions of software is against the requirements of ISO/IEC 27001 and the national laws and regulations. However, they seemed to be fine with it.

Several months after the audit, Jack sold some of NightCore's information that he collected during the audit for a huge amount of money to competitors of NightCore.

Based on this scenario, answer the following question:

According to scenario 3, which audit principle has Jack compromised when he sold NightCore’s information after the audit?

Options:

A.

Independence

B.

Integrity

C.

Confidentiality

Buy Now
Questions 52

Which two of the following phrases would apply to "audit objectives"?

Options:

A.

Audit duration

B.

Determining conformity

C.

Checking legal compliance

D.

Auditor competence

E.

Revising management policy

F.

Identifying opportunities for improvement, if required

Buy Now
Questions 53

ISMS (1)---------------helps determine (2)--------------,

Options:

A.

(1) Continual improvement, (2) the effectiveness of corrective actions

B.

Q (1) Management review, (2) opportunities for continual improvement

C.

(1) Internal audit, (2) the ISMS scope

Buy Now
Questions 54

Finnco, a subsidiary of a certification body, provided ISMS consultancy services to an organization. Considering this scenario, when can the certification body certify the organization?

Options:

A.

There is no time constraint in such a situation

B.

At no time, since it presents a conflict of interest

C.

If a minimum period of two years has passed since the last consulting activities

Buy Now
Questions 55

Scenario:

Northstorm is an online retail shop offering unique vintage and modern accessories. It initially entered a small market but gradually grew thanks to the development of the overall e-commerce landscape. Northstorm works exclusively online and ensures efficient payment processing, inventory management, marketing tools, and shipment orders. It uses prioritized ordering to receive, restock, and ship its most popular products.

Northstorm has traditionally managed its IT operations by hosting its website and maintaining full control over its infrastructure, including hardware, software, and data administration. However, this approach hindered its growth due to the lack of responsive infrastructure. Seeking to enhance its e-commerce and payment systems, Northstorm opted to expand its in-house data centers, completing the expansion in two phases over three months. Initially, the company upgraded its core servers, point-of-sale, ordering, billing, database, and backup systems. The second phase involved improving mail, payment, and network functionalities. Additionally, during this phase, Northstorm adopted an international standard for personally identifiable information (PII) controllers and PII processors regarding PII processing to ensure its data handling practices were secure and compliant with global regulations.

Despite the expansion, Northstorm's upgraded data centers failed to meet its evolving business demands. This inadequacy led to several new challenges, including issues with order prioritization. Customers reported not receiving priority orders, and the company struggled with responsiveness. This was largely due to the main server's inability to process orders from YouDecide, an application designed to prioritize orders and simulate customer interactions. The application, reliant on advanced algorithms, was incompatible with the new operating system (OS) installed during the upgrade.

Faced with urgent compatibility issues, Northstorm quickly patched the application without proper validation, leading to the installation of a compromised version. This security lapse resulted in the main server being affected and the company's website going offline for a week. Recognizing the need for a more reliable solution, the company decided to outsource its website hosting to an e-commerce provider. The company signed a confidentiality agreement concerning product ownership and conducted a thorough review of user access rights to enhance security before transitioning.

Question:

According to Scenario 1, Northstorm reviewed users' access rights. What is the type and function of this security control?

Options:

A.

Detective and administrative

B.

Corrective and managerial

C.

Legal and technical

Buy Now
Questions 56

Question:

Which controls are related to the Annex A controls of ISO/IEC 27001 and are often selected from other guides and standards or defined by the organization to meet its specific needs?

Options:

A.

General controls

B.

Strategic controls

C.

Specific controls

Buy Now
Questions 57

Scenario 8

Trustingo has been providing banking and financial services in Estonia since 2010. The company has a network of 30 branches with over 100 ATMs nationwide. To meet strict data security and privacy regulations, Trustingo implemented an information security management system (ISMS) based on ISO/IEC 27001, ensuring better security, improved risk management, and compliance with legal requirements.

Nine months after the successful implementation of the ISMS, Trustingo decided to pursue certification for their ISMS based on ISO/IEC 27001 by an independent certification body. The certification audit included Trustingo's systems, processes, and technologies.

The audit team conducted the Stage 1 and Stage 2 audits jointly, and several nonconformities were detected. The first nonconformity was related to Trustingo's labeling of information. The company had an information classification scheme but no information labeling procedure. As a result, documents requiring the same level of protection would be labeled differently.

The nonconformity also impacted media handling. The audit team used sampling and concluded that 50 of 200 removable media stored sensitive information mistakenly classified as confidential. According to the information classification scheme, confidential information can be stored in removable media, whereas storing sensitive information is strictly prohibited.

The audit team drafted the nonconformity report and discussed the audit conclusions with Trustingo's representatives, who agreed to submit an action plan for the detected nonconformities within two months. Since the certification recommendation is conditional upon filing corrective actions, Trustingo must submit corrective action plans to show how they will address and resolve these nonconformities. Trustingo accepted the audit team leader's proposed solution and addressed the nonconformities by drafting an information labeling procedure and updating the removable media procedure.

Two weeks after the audit completion, Trustingo submitted a general action plan. Although the plan addressed the detected nonconformities and corrective actions taken, it lacked detailed action steps for each nonconformity and did not include specific details on the impacted systems, controls, or operations. The audit team evaluated the action plan. Nevertheless, Trustingo received an unfavorable recommendation for certification.

Question

Which option justifies the unfavorable recommendation for certification? Refer to Scenario 8.

Options:

A.

The major nonconformity related to storing sensitive information in removable media

B.

The minor nonconformity related to the lack of information labeling procedure

C.

The company's decision to submit the action plan in two weeks despite having a different timeline available

Buy Now
Questions 58

AppFolk, a software development company, is seeking certification against ISO/IEC 27001. In the initial phases of the external audit, the certification body in discussion with the company excluded the marketing division from the audit scope, although they stated in their ISMS scope that the whole company is included. Is this acceptable?

Options:

A.

Yes, audit and ISMS scope do not necessarily need to be the same

B.

No, divisions that are not critical for the industrial sector in which the auditee operates can be excluded from the audit scope

C.

No, audit scope should reflect all of the organization’s divisions covered by the ISMS

Buy Now
Questions 59

Scenario 3: Rebuildy is a construction company located in Bangkok.. Thailand, that specializes in designing, building, and maintaining residential buildings. To ensure the security of sensitive project data and client information, Rebuildy decided to implement an ISMS based on ISO/IEC 27001. This included a comprehensive understanding of information security risks, a defined continual improvement approach, and robust business solutions.

The ISMS implementation outcomes are presented below

•Information security is achieved by applying a set of security controls and establishing policies, processes, and procedures.

•Security controls are implemented based on risk assessment and aim to eliminate or reduce risks to an acceptable level.

•All processes ensure the continual improvement of the ISMS based on the plan-do-check-act (PDCA) model.

•The information security policy is part of a security manual drafted based on best security practices Therefore, it is not a stand-alone document.

•Information security roles and responsibilities have been clearly stated in every employees job description

•Management reviews of the ISMS are conducted at planned intervals.

Rebuildy applied for certification after two midterm management reviews and one annual internal audit Before the certification audit one of Rebuildy’s former employees approached one of the audit team members to tell them that Rebuildy has several security problems that the company is trying to conceal. The former employee presented the documented evidence to the audit team member Electra, a key client of Rebuildy, also submitted evidence on the same issues, and the auditor determined to retain this evidence instead of the former employee's. The audit team member remained in contact with Electra until the audit was completed, discussing the nonconformities found during the audit. Electra provided additional evidence to support these findings.

At the beginning of the audit, the audit team interviewed the company’s top management They discussed, among other things, the top management's commitment to the ISMS implementation. The evidence obtained from these discussions was documented in written confirmation, which was used to determine Rebuildy’s conformity to several clauses of ISO/IEC 27001

The documented evidence obtained from Electra was attached to the audit report, along with the nonconformities report. Among others, the following nonconformities were detected:

•An instance of improper user access control settings was detected within the company's financial reporting system.

•A stand-alone information security policy has not been established. Instead, the company uses a security manual drafted based on best security practices.

After receiving these documents from the audit team, the team leader met Rebuildy’s top management to present the audit findings. The audit team reported the findings related to the financial reporting system and the lack of a stand-alone information security policy. The top management expressed dissatisfaction with the findings and suggested that the audit team leader's conduct was unprofessional, implying they might request a replacement. Under pressure, the audit team leader decided to cooperate with top management to downplay the significance of the detected nonconformities. Consequently, the audit team leader adjusted the report to present a more favorable view, thus misrepresenting the true extent of Rebuildy's compliance issues.

Based on the scenario above, answer the following question:

Question:

Based on Scenario 3, the audit team used information obtained from interviews with top management to determine Rebuildy’s conformity to several ISO/IEC 27001 clauses. Is this acceptable?

Options:

A.

No, the audit team should have used only documentary evidence, such as policies and procedures, to determine conformity

B.

Yes, the audit team obtained verbal evidence by written confirmations from the top management, which can be used to determine conformity to the standard

C.

Yes, interviews with top management are the most reliable form of audit evidence and can be used to determine conformity to the standard without further verification

Buy Now
Questions 60

Scenario 6: Sinvestment is an insurance company that offers home, commercial, and life insurance. The company was founded in North Carolina, but have recently expanded in other locations, including Europe and Africa.

Sinvestment is committed to complying with laws and regulations applicable to their industry and preventing any information security incident. They have implemented an ISMS based on ISO/IEC 27001 and have applied for ISO/IEC 27001 certification.

Two auditors were assigned by the certification body to conduct the audit. After signing a confidentiality agreement with Sinvestment. they started the audit activities. First, they reviewed the documentation required by the standard, including the declaration of the ISMS scope, information security policies, and internal audits reports. The review process was not easy because, although Sinvestment stated that they had a documentation procedure in place, not all documents had the same format.

Then, the audit team conducted several interviews with Sinvestment's top management to understand their role in the ISMS implementation. All activities of the stage 1 audit were performed remotely, except the review of documented information, which took place on-site, as requested by Sinvestment.

During this stage, the auditors found out that there was no documentation related to information security training and awareness program. When asked, Sinvestment's representatives stated that the company has provided information security training sessions to all employees. Stage 1 audit gave the audit team a general understanding of Sinvestment's operations and ISMS.

The stage 2 audit was conducted three weeks after stage 1 audit. The audit team observed that the marketing department (which was not included in the audit scope) had no procedures in place to control employees’ access rights. Since controlling employees' access rights is one of the ISO/IEC 27001 requirements and was included in the information security policy of the company, the issue was included in the audit report. In addition, during stage 2 audit, the audit team observed that Sinvestment did not record logs of user activities. The procedures of the company stated that "Logs recording user activities should be retained and regularly reviewed," yet the company did not present any evidence of the implementation of such procedure.

During all audit activities, the auditors used observation, interviews, documented information review, analysis, and technical verification to collect information and evidence. All the audit findings during stages 1 and 2 were analyzed and the audit team decided to issue a positive recommendation for certification.

Based on scenario 6, during stage 1 audit, the auditor found out that some documents regarding the ISMS had different format. What should the auditor do in this case?

Options:

A.

Verify if the documented information has the appropriate format and is in accordance with the company's documentation procedure since this is a requirement of the standard

B.

Verify only if the information required by the standard is documented without taking into account the format since this is not a requirement of the standard

C.

Document this observation as an issue that should be verified during stage 2 audit

Buy Now
Questions 61

Scenario 5: Cobt. an insurance company in London, offers various commercial, industrial, and life insurance solutions. In recent years, the number of Cobt's clients has increased enormously. Having a huge amount of data to process, the company decided that certifying against ISO/IEC 27001 would bring many benefits to securing information and show its commitment to continual improvement. While the company was well-versed in conducting regular risk assessments, implementing an ISMS brought major changes to its daily operations. During the risk assessment process, a risk was identified where significant defects occurred without being detected or prevented by the organizations internal control mechanisms.

The company followed a methodology to implement the ISMS and had an operational ISMS in place after only a few months After successfully implementing the ISMS, Cobt applied for ISO/IEC 27001 certification Sarah, an experienced auditor, was assigned to the audit Upon thoroughly analyzing the audit offer, Sarah accepted her responsibilities as an audit team leader and immediately started to obtain general information about Cobt She established the audit criteria and objective, planned the audit, and assigned the audit team members' responsibilities.

Sarah acknowledged that although Cobt has expanded significantly by offering diverse commercial and insurance solutions, it still relies on some manual processes Therefore, her initial focus was to gather information on how the company manages its information security risks Sarah contacted Cobt's representatives to request access to information related to risk management for the off-site review, as initially agreed upon for part of the audit However, Cobt later refused, claiming that such information is too sensitive to be accessed outside of the company This refusal raised concerns about the audit's feasibility, particularly regarding the availability and cooperation of the auditee and access to evidence Moreover, Cobt raised concerns about the audit schedule, stating that it does not properly reflect the recent changes the company made It pointed out that the actions to be performed during the audit apply only to the initial scope and do not encompass the latest changes made in the audit scope

Sarah also evaluated the materiality of the situation, considering the significance of the information denied for the audit objectives. In this case, the refusal by Cobt raised questions about the completeness of the audit and its ability to provide reasonable assurance. Following these situations, Sarah decided to withdraw from the audit before a certification agreement was signed and communicated her decision to Cobt and the certification body. This decision was made to ensure adherence to audit principles and maintain transparency, highlighting her commitment to consistently upholding these principles.

Based on the scenario above, answer the following question:

Question:

What type of risk did Cobt identify during the last risk assessment?

Options:

A.

Inherent risk

B.

Control risk

C.

Detection risk

Buy Now
Questions 62

Scenario 2:

Clinic, founded in the 1990s, is a medical device company that specializes in treatments for heart-related conditions and complex surgical interventions. Based in Europe, it serves both patients and healthcare professionals. Clinic collects patient data to tailor treatments, monitor outcomes, and improve device functionality. To enhance data security and build trust, Clinic is implementing an information security management system (ISMS) based on ISO/IEC 27001. This initiative demonstrates Clinic's commitment to securely managing sensitive patient information and proprietary technologies.

Clinic established the scope of its ISMS by solely considering internal issues, interfaces, dependencies between internal and outsourced activities, and the expectations of interested parties. This scope was carefully documented and made accessible. In defining its ISMS, Clinic chose to focus specifically on key processes within critical departments such as Research and Development, Patient Data Management, and Customer Support.

Despite initial challenges, Clinic remained committed to its ISMS implementation, tailoring security controls to its unique needs. The project team excluded certain Annex A controls from ISO/IEC 27001 while incorporating additional sector-specific controls to enhance security. The team evaluated the applicability of these controls against internal and external factors, culminating in the development of a comprehensive Statement of Applicability (SoA) detailing the rationale behind control selection and implementation.

As preparations for certification progressed, Brian, appointed as the team leader, adopted a self-directed risk assessment methodology to identify and evaluate the company’s strategic issues and security practices. This proactive approach ensured that Clinic’s risk assessment aligned with its objectives and mission.

Question:

Does the Clinic's SoA document meet the ISO/IEC 27001 requirements for the SoA?

Options:

A.

Yes, because it comprises an exhaustive list of controls considered applicable from Annex A of ISO/IEC 27001 and the other sources

B.

No, because security controls selected from sources other than Annex A of ISO/IEC 27001 are included

C.

No, because it does not contain the justification for the exclusion of controls from Annex A of ISO/IEC 27001

Buy Now
Questions 63

You are an experienced audit team leader guiding an auditor in training.

Your team is currently conducting a third-party surveillance audit of an organisation that stores data on behalf of external clients. The auditor in training has been tasked with reviewing the ORGANISATIONAL controls listed in the Statement of Applicability (SoA) and implemented at the site.

Select four controls from the following that would you expect the auditor in training to review.

Options:

A.

Access to and from the loading bay

B.

Confidentiality and nondisclosure agreements

C.

How information security has been addressed within supplier agreements

D.

How power and data cables enter the building

E.

Rules for transferring information within the organisation and to other organisations

F.

The development and maintenance of an information asset inventory

G.

The operation of the site CCTV and door control systems

Buy Now
Questions 64

During a third-party certification audit, you are presented with a list of issues by an auditee. Which four of the following constitute 'internal' issues in the context of a management system to ISO 27001:2022?

    Higher labour costs as a result of an aging population

Options:

A.

A rise in interest rates in response to high inflation

B.

Poor levels of staff competence as a result of cuts in training expenditure

C.

Poor morale as a result of staff holidays being reduced

D.

Increased absenteeism as a result of poor management

E.

A reduction in grants as a result of a change in government policy

F.

A fall in productivity linked to outdated production equipment

G.

Inability to source raw materials due to government sanctions

Buy Now
Questions 65

Scenario 7

Lawsy is a leading law firm with offices in Bangkok, Thailand. It has over 50 attorneys offering sophisticated legal services to clients in business and commercial law, intellectual property, banking, and financial services. They believe they have a comfortable position in the market thanks to their commitment to implementing information security best practices and remaining up to date with technological developments.

Lawsy has rigorously implemented, evaluated, and conducted internal audits for the information security management system (ISMS) for two years. Now, they have applied for ISO/IEC 27001 certification at ISMA, a well-known and trusted certification body.

During the stage 1 audit, the audit team reviewed all the ISMS documents created during the implementation phase. They also reviewed and evaluated the records from management reviews and internal audits. Lawsy submitted records of evidence that corrective actions on nonconformities were performed when necessary, so the audit team interviewed the internal auditor. The interview validated the adequacy and frequency of the internal audits by providing insight into the internal audit plan and procedures.

The audit team continued verifying strategic documents, including the information security policy and risk evaluation criteria. During the information security policy review, the team noticed inconsistencies between the documented information describing the governance framework and the procedures. Following the completion of stage 1, the audit team leader prepared the audit plan, which addressed the audit objectives, scope, criteria, and procedures.

During the stage 2 audit, the audit team interviewed the information security manager, who drafted the information security policy. He justified the issue identified in stage 1 by stating that Lawsy conducts mandatory information security training and awareness sessions every three months.

Later, the audit team found that Lawsy did not have procedures for using laptops outside the workplace, even though employees were allowed to take laptops outside the workplace. The company only provided general information about the use of laptops and relied on employees’ common knowledge to protect the confidentiality and integrity of information stored on the laptops.

Following the interview, the audit team examined 15 employee training records (out of 50) and concluded that Lawsy meets the requirements of ISO/IEC 27001 related to training and awareness. To support this conclusion, the auditor photocopied and archived the examined employee training records after completing the audit.

Question

Lawsy lacks a procedure for using laptops outside the workplace and relies on employees' common knowledge to protect the confidentiality of information stored on the laptops. What does this present?

Options:

A.

An anomaly

B.

A nonconformity

C.

A conformity

Buy Now
Questions 66

Scenario 1

Fintive is a distinguished security provider specializing in online payments and protection solutions. Founded in 1999 by Thomas Fin in San Jose, California, Fintive offers services to companies operating online that seek to improve their information security, prevent fraud, and protect user information such as personally identifiable information (PII).

Fintive bases its decision-making and operational processes on previous cases, gathering customer data, classifying them according to the case, and analyzing them.

Initially, Fintive required a large number of employees to be able to conduct such complex analyses. However, as technology advanced, the company recognized an opportunity to implement a modern tool — a chatbot — to achieve pattern analyses aimed at preventing fraud in real time. This tool would also assist in improving customer service.

The initial idea was communicated to the software development team, who supported the initiative and were assigned to work on the project. They began integrating the chatbot into the existing system and set an objective regarding the chatbot, which was to answer 85% of all chat queries.

After successfully integrating the chatbot, the company released it for customer use. However, the chatbot exhibited several issues. Due to insufficient testing and a lack of sample data provided during the training phase — when it was supposed to learn the query pattern — the chatbot failed to effectively address user queries. Additionally, it sent random files to users when it encountered invalid inputs, such as unusual patterns of dots and special characters.

Consequently, the chatbot could not effectively answer customer queries, overwhelming traditional customer support and preventing them from assisting customers with their requests.

Recognizing the potential risks, Fintive decided to implement a set of new controls. The measures included enabling comprehensive audit logging, configuring automated alert systems to flag unusual activities, performing periodic access reviews, and monitoring system behavior for anomalies. The objective was to identify unauthorized access, errors, or suspicious activities in a timely manner, ensuring that any potential issues could be quickly recognized and investigated before causing significant harm.

Question

According to Scenario 1, which of the following could be a potential impact of the chatbot issues?

Options:

A.

Temporary slowdown in internal system updates with no effect on users

B.

A breach of customer privacy due to the potential exposure of sensitive files

C.

Minor delays in customer service response times due to the chatbot malfunction

Buy Now
Questions 67

Scenario 4: SendPay is a financial company that provides its services through a network of agents and financial institutions. One of their main services is transferring money worldwide. SendPay, as a new company, seeks to offer top quality services to its clients. Since the company offers international transactions, it requires from their clients to provide personal information, such as their identity, the reason for the transactions, and other details that might be needed to complete the transaction. Therefore, SendPay has implemented security measures to protect their clients' information, including detecting, investigating, and responding to any information security threats that may emerge. Their commitment to offering secure services was also reflected during the ISMS implementation where the company invested a lot of time and resources.

Last year, SendPay unveiled their digital platform that allows money transactions through electronic devices, such as smartphones or laptops, without requiring an additional fee. Through this platform, SendPay's clients can send and receive money from anywhere and at any time. The digital platform helped SendPay to simplify the company's operations and further expand its business. At the time, SendPay was outsourcing its software operations, hence the project was completed by the software development team of the outsourced company. The same team was also responsible for maintaining the technology infrastructure of SendPay.

Recently, the company applied for ISO/IEC 27001 certification after having an ISMS in place for almost a year. They contracted a certification body that fit their criteria. Soon after, the certification body appointed a team of four auditors to audit SendPay's ISMS.

During the audit, among others, the following situations were observed:

1.The outsourced software company had terminated the contract with SendPay without prior notice. As a result, SendPay was unable to immediately bring the services back in-house and its operations were disrupted for five days. The auditors requested from SendPay's representatives to provide evidence that they have a plan to follow in cases of contract terminations. The representatives did not provide any documentary evidence but during an interview, they told the auditors that the top management of SendPay had identified two other software development companies that could provide services immediately if similar situations happen again.

2.There was no evidence available regarding the monitoring of the activities that were outsourced to the software development company. Once again, the representatives of SendPay told the auditors that they regularly communicate with the software development company and that they are appropriately informed for any possible change that might occur.

3.There was no nonconformity found during the firewall testing. The auditors tested the firewall configuration in order to determine the level of security provided by

these services. They used a packet analyzer to test the firewall policies which enabled them to check the packets sent or received in real-time.

Based on this scenario, answer the following question:

SendPay's representatives stated that the company did not have a plan to follow in case of a contract termination with the company that they outsource activities to. Instead, the top management had identified two other software development companies that could provide the same services. How do you describe this situation?

Options:

A.

Unacceptable, SendPay evidence and criteria for identifying alternative software development companies is insufficient

B.

Acceptable, SendPay can decide whether to develop a plan for similar contract terminations or not, hence there is no need for additional evidence

C.

Unacceptable, SendPay must always have a recovery plan in place that states what steps should the company follow

Buy Now
Questions 68

Question:

What is the purpose of audit test plans in the audit process?

Options:

A.

To develop detailed audit reports

B.

To conduct audit procedures such as observation and interviews

C.

To select all elements of the management system for validation

Buy Now
Questions 69

Scenario 2: Knight is an electronics company from Northern California, US that develops video game consoles. Knight has more than 300 employees worldwide. On the

fifth anniversary of their establishment, they have decided to deliver the G-Console, a new generation video game console aimed for worldwide markets. G-Console is

considered to be the ultimate media machine of 2021 which will give the best gaming experience to players. The console pack will include a pair of VR headset, two

games, and other gifts.

Over the years, the company has developed a good reputation by showing integrity, honesty, and respect toward their customers. This good reputation is one of the

reasons why most passionate gamers aim to have Knight's G-console as soon as it is released in the market. Besides being a very customer-oriented company, Knight

also gained wide recognition within the gaming industry because of the developing quality. Their prices are a bit higher than the reasonable standards allow.

Nonetheless, that is not considered an issue for most loyal customers of Knight, as their quality is top-notch.

Being one of the top video game console developers in the world, Knight is also often the center of attention for malicious activities. The company has had an

operational ISMS for over a year. The ISMS scope includes all departments of Knight, except Finance and HR departments.

Recently, a number of Knight's files containing proprietary information were leaked by hackers. Knight's incident response team (IRT) immediately started to analyze

every part of the system and the details of the incident.

The IRT's first suspicion was that Knight's employees used weak passwords and consequently were easily cracked by hackers who gained unauthorized access to their

accounts. However, after carefully investigating the incident, the IRT determined that hackers accessed accounts by capturing the file transfer protocol (FTP) traffic.

FTP is a network protocol for transferring files between accounts. It uses clear text passwords for authentication.

Following the impact of this information security incident and with IRT's suggestion, Knight decided to replace the FTP with Secure Shell (SSH) protocol, so anyone

capturing the traffic can only see encrypted data.

Following these changes, Knight conducted a risk assessment to verify that the implementation of controls had minimized the risk of similar incidents. The results of

the process were approved by the ISMS project manager who claimed that the level of risk after the implementation of new controls was in accordance with the

company's risk acceptance levels.

Based on this scenario, answer the following question:

FTP uses clear text passwords for authentication. This is an FTP:

Options:

A.

Vulnerability

B.

Risk

C.

Threat

Buy Now
Questions 70

Scenario 7: Webvue. headquartered in Japan, is a technology company specializing in the development, support, and maintenance of computer software. Webvue provides solutions across various technology fields and business sectors. Its flagship service is CloudWebvue, a comprehensive cloud computing platform offering storage, networking, and virtual computing services. Designed for both businesses and individual users. CloudWebvue is known for its flexibility, scalability, and reliability.

Webvue has decided to only include CloudWebvue in its ISO/IEC 27001 certification scope. Thus, the stage 1 and 2 audits were performed simultaneously Webvue takes pride in its strictness regarding asset confidentiality They protect the information stored in CloudWebvue by using appropriate cryptographic controls. Every piece of information of any classification level, whether for internal use. restricted, or confidential, is first encrypted with a unique corresponding hash and then stored in the cloud

The audit team comprised five persons Keith. Sean. Layla, Sam. and Tina. Keith, the most experienced auditor on the IT and information security auditing team, was the audit team leader. His responsibilities included planning the audit and managing the audit team. Sean and Layla were experienced in project planning, business analysis, and IT systems (hardware and application) Their tasks included audit planning according to Webvue’s internal systems and processes Sam and Tina, on the other hand, who had recently completed their education, were responsible for completing the day-to-day tasks while developing their audit skills

While verifying conformity to control 8.24 Use of cryptography of ISO/IEC 27001 Annex A through interviews with the relevant staff, the audit team found out that the cryptographic keys have been initially generated based on random bit generator (RBG) and other best practices for the generation of the cryptographic keys. After checking Webvue's cryptography policy, they concluded that the information obtained by the interviews was true. However, the cryptographic keys are still in use because the policy does not address the use and lifetime of cryptographic keys.

As later agreed upon between Webvue and the certification body, the audit team opted to conduct a virtual audit specifically focused on verifying conformity to control 8.11 Data Masking of ISO/IEC 27001 within Webvue, aligning with the certification scope and audit objectives. They examined the processes involved in protecting data within CloudWebvue. focusing on how the company adhered to its policies and regulatory standards. As part of this process. Keith, the audit team leader, took screenshot copies of relevant documents and cryptographic key management procedures to document and analyze the effectiveness of Webvue's practices.

Webvue uses generated test data for testing purposes. However, as determined by both the interview with the manager of the QA Department and the procedures used by this department, sometimes live system data are used. In such scenarios, large amounts of data are generated while producing more accurate results. The test data is protected and controlled, as verified by the simulation of the encryption process performed by Webvue's personnel during the audit

While interviewing the manager of the QA Department, Keith observed that employees in the Security Training Department were not following proper procedures, even though this department fell outside the audit scope. Despite the exclusion in the audit scope, the non conformity in the Security Training Department has potential implications for the processes within the audit scope, specifically impacting data security and cryptographic practices in CloudWebvue. Therefore, Keith incorporated this finding into the audit report and accordingly informed the auditee.

Based on the scenario above, answer the following question:

Question:

To verify conformity to the protection of test data control, Webvue’s personnel simulated the encryption process. Is this acceptable?

Options:

A.

No, the encryption process must not be simulated since it affects the auditee’s operations

B.

Yes, if the auditor is not competent to perform the operations linked to a test, a representative of the auditee may have the role of a technical expert

C.

Yes, simulation of a process to verify conformity to a control can be done with the assistance of the auditee’s personnel

Buy Now
Questions 71

The scope of an organization certified against ISO/IEC 27001 states that they provide editing and web hosting services. However, due to some changes in the organization, the technical support related to the web hosting services has been outsourced. Should a change in the scope be initiated in this case?

Options:

A.

Yes, because any change in the external environment initiates a change in the scope

B.

No, because the change does not require implementation of new security controls

C.

No, because the organization is already certified for its editing and web hosting services

Buy Now
Questions 72

A telecommunications company uses the AES method for ensuring that confidential information is protected. This means that they use a single key to encrypt and

decrypt the information. What kind of control does the company use?

Options:

A.

Detective

B.

Corrective

C.

Preventive

Buy Now
Questions 73

Scenario 6: Cyber ACrypt is a cybersecurity company that provides endpoint protection by offering anti-malware and device security, asset life cycle management, and device encryption. To validate its ISMS against ISO/IEC 27001 and demonstrate its commitment to cybersecurity excellence, the company underwent a meticulous audit process led by John, the appointed audit team leader.

Upon accepting the audit mandate, John promptly organized a meeting to outline the audit plan and team roles This phase was crucial for aligning the team with the audit's objectives and scope However, the initial presentation to Cyber ACrypt’s staff revealed a significant gap in understanding the audit's scope and objectives, indicating potential readiness challenges within the company

As the stage 1 audit commenced, the team prepared for on-site activities. They reviewed Cyber ACrypt's documented information, including the information security policy and operational procedures ensuring each piece conformed to and was standardized in format with author identification, production date, version number, and approval date Additionally, the audit team ensured that each document contained the information required by the respective clause of the standard This phase revealed that a detailed audit of the documentation describing task execution was unnecessary, streamlining the process and focusing the team's efforts on critical areas During the phase of conducting on-site activities, the team evaluated management responsibility for the Cyber Acrypt's policies This thorough examination aimed to ascertain continual improvement and adherence to ISMS requirements Subsequently, in the document, the stage 1 audit outputs phase, the audit team meticulously documented their findings, underscoring their conclusions regarding the fulfillment of the stage 1 objectives. This documentation was vital for the audit team and Cyber ACrypt to understand the preliminary audit outcomes and areas requiring attention.

The audit team also decided to conduct interviews with key interested parties. This decision was motivated by the objective of collecting robust audit evidence to validate the management system’s compliance with ISO/IEC 27001 requirements. Engaging with interested parties across various levels of Cyber ACrypt provided the audit team with invaluable perspectives and an understanding of the ISMS's implementation and effectiveness.

The stage 1 audit report unveiled critical areas of concern. The Statement of Applicability (SoA) and the ISMS policy were found to be lacking in several respects, including insufficient risk assessment, inadequate access controls, and lack of regular policy reviews. This prompted Cyber ACrypt to take immediate action to address these shortcomings. Their prompt response and modifications to the strategic documents reflected a strong commitment to achieving compliance.

The technical expertise introduced to bridge the audit team's cybersecurity knowledge gap played a pivotal role in identifying shortcomings in the risk assessment methodology and reviewing network architecture. This included evaluating firewalls, intrusion detection and prevention systems, and other network security measures, as well as assessing how Cyber ACrypt detects, responds to, and recovers from external and internal threats. Under John's supervision, the technical expert communicated the audit findings to the representatives of Cyber ACrypt. However, the audit team observed that the expert s objectivity might have been compromised due to receiving consultancy fees from the auditee. Considering the behavior of the technical expert during the audit, the audit team leader decided to discuss this concern with the certification body.

Based on the scenario above, answer the following question:

Question:

According to Scenario 6, Cyber ACrypt modified the SoA and the ISMS policy after the Stage 1 audit report. How do you define this situation?

Options:

A.

Unacceptable, once the external audit passes Stage 1, the SoA and the ISMS policy cannot be modified

B.

Acceptable, situations that lead to major nonconformities during the Stage 2 audit should be corrected

C.

Acceptable, minor modifications to the SoA and ISMS policy can be made until the submission of the final audit report

Buy Now
Questions 74

Scenario 9: Techmanic is a Belgian company founded in 1995 and currently operating in Brussels. It provides IT consultancy, software design, and hardware/software services, including deployment and maintenance. The company serves sectors like public services, finance, telecom, energy, healthcare, and education. As a customer-centered company, it prioritizes strong client relationships and leading security practices.

Techmanic has been ISO/IEC 27001 certified for a year and regards this certification with pride. During the certification audit, the auditor found some inconsistencies in its ISMS implementation. Since the observed situations did not affect the capability of its ISMS to achieve the intended results, Techmanic was certified after auditors followed up on the root cause analysis and corrective actions remotely During that year, the company added hosting to its list of services and requested to expand its certification scope to include that area The auditor in charge approved the request and notified Techmanic that the extension audit would be conducted during the surveillance audit

Techmanic underwent a surveillance audit to verify its iSMS's continued effectiveness and compliance with ISO/IEC 27001. The surveillance audit aimed to ensure that Techmanic’s security practices, including the recent addition of hosting services, aligned seamlessly with the rigorous requirements of the certification

The auditor strategically utilized the findings from previous surveillance audit reports in the recertification activity with the purpose of replacing the need for additional recertification audits, specifically in the IT consultancy sector. Recognizing the value of continual improvement and learning from past assessments. Techmanic implemented a practice of reviewing previous surveillance audit reports. This proactive approach not only facilitated identifying and resolving potential nonconformities but also aimed to streamline the recertification process in the IT consultancy sector.

During the surveillance audit, several nonconformities were found. The ISMS continued to fulfill the ISO/IEC 27001*s requirements, but Techmanic failed to resolve the nonconformities related to the hosting services, as reported by its internal auditor. In addition, the internal audit report had several inconsistencies, which questioned the independence of the internal auditor during the audit of hosting services. Based on this, the extension certification was not granted. As a result. Techmanic requested a transfer to another certification body. In the meantime, the company released a statement to its clients stating that the ISO/IEC 27001 certification covers the IT services, as well as the hosting services.

Based on the scenario above, answer the following question:

Question:

Is the purpose of reviewing previous surveillance audit reports in the recertification activity for Techmanic appropriately defined?

Options:

A.

Yes, the purpose of the recertification activity is to replace the need for recertification audits in the IT consultancy sector

B.

No, the purpose of the recertification activity is to compare Techmanic’s software development with industry benchmarks

C.

No, the purpose of the recertification activity is to consider the performance of Techmanic’s management system over the certification cycle

Buy Now
Questions 75

The auditor discovered that two out of 15 employees of the IT Department have not received adequate information security training. What does this represent?

Options:

A.

Audit finding

B.

Audit evidence

C.

Information source

Buy Now
Questions 76

Select the words that best complete the sentence:

To complete the sentence with the word(s) click on the blank section you want to complete so that it is highlighted in red, and then click on the application text from the options below. Alternatively, you may drag and drop the option to the appropriate blank section.

ISO-IEC-27001-Lead-Auditor Question 76

Options:

Buy Now
Questions 77

You are performing an ISMS audit at a residential nursing home that provides healthcare services. The next step in your audit plan is to verify the information security incident management process. The IT Security Manager presents the information security incident management procedure (Document reference ID: ISMS_L2_16, version 4).

You review the document and notice a statement "Any information security weakness, event, and incident should be reported to the Point of Contact (PoC) within 1 hour after identification". When interviewing staff, you found that there were differences in the understanding of the meaning of the phrase "weakness, event, and incident".

The IT Security Manager explained that an online "information security handling" training seminar was conducted 6 months ago. All the people interviewed participated in and passed the reporting exercise and course assessment.

You would like to investigate other areas further to collect more audit evidence. Select three

options that would not be valid audit trails.

Options:

A.

Collect more evidence on how areas subject to information security incidents are quarantined to maintain information security during disruption (relevant to control A.5.29)

B.

Collect more evidence on how information security incidents are reported via appropriate channels (relevant to control A.6.8)

C.

Collect more evidence on how the organisation conducts information security incident training and evaluates its effectiveness. (Relevant to clause 7.2)

D.

Collect more evidence on how the organisation learns from information security incidents and makes improvements. (Relevant to control A.5.27)

E.

Collect more evidence on how the organisation manages the Point of Contact (PoC) which monitors vulnerabilities. (Relevant to clause 8.1)

F.

Collect more evidence on how the organisation tests the business continuity plan. (Relevant to control A.5.30)

G.

Collect more evidence on whether terms and definitions are contained in the information security policy. (Relevant to control 5.32)

Buy Now
Questions 78

What is we do in ACT - From PDCA cycle

Options:

A.

Take actions to continually monitor process performance

B.

Take actions to continually improve process performance

C.

Take actions to continually monitor process performance

D.

Take actions to continually improve people performance

Buy Now
Questions 79

Which one of the following options best describes the main purpose of a Stage 1 third-party audit?

Options:

A.

To introduce the audit team to the client

B.

To learn about the organisation's procurement

C.

To determine redness for a stage 2 audit

D.

To check for legal compliance by the organisation

E.

To prepare an independent audit report

F.

To get to know the organisation's customers

Buy Now
Questions 80

An auditor of organisation A performs an audit of supplier B. Which two of the following actions is likely to represent a breach of confidentiality by the auditor after having identified findings in B's information security management system?

Options:

A.

Shares the findings with other relevant managers in A

B.

Shares the findings with B's Information Security Manager

C.

Shares the findings with A's supplier evaluation team

D.

Shares the findings with B's other customers

E.

Shares the findings with B's certification body

F.

Shares the findings with other relevant managers in B

Buy Now
Questions 81

Question

What should the auditors consider for judgement-based sampling?

Options:

A.

The results of monitoring activities from the period prior to the ISMS implementation

B.

Previous audit experience within the audit scope

C.

The auditee's experience with implementing management systems

Buy Now
Questions 82

As an auditor, you have noticed that ABC Inc. has established a procedure to manage the removable storage media. The procedure is based on the classification scheme adopted by ABC Inc. Thus, if the information stored is classified as "confidential," the procedure applies. On the other hand, the information that is classified as "public," does not have confidentiality requirements: thus, only a procedure for ensuring its integrity and availability applies. What type of audit finding is this?

Options:

A.

Nonconformity

B.

Anomaly

C.

Conformity

Buy Now
Questions 83

You are carrying out your first third-party ISMS surveillance audit as an Audit Team Leader. You are presently in the auditee's data centre with another member of your audit team.

Your colleague seems unsure as to the difference between an information security event and an information security incident. You attempt to explain the difference by providing examples.

Which three of the following scenarios can be defined as information security incidents?

Options:

A.

The organisation's malware protection software prevents a virus

B.

A hard drive is used after its recommended replacement date

C.

The organisation receives a phishing email

D.

An employee fails to clear their desk at the end of their shift

E.

A contractor who has not been paid deletes top management ICT accounts

F.

An unhappy employee changes payroll records without permission

G.

The organisation fails a third-party penetration test

Buy Now
Questions 84

You ask the IT Manager why the organisation still uses the mobile app while personal data

encryption and pseudonymisation tests failed. Also, whether the Service Manager is authorised to approve the test.

The IT Manager explains the test results should be approved by him according to the software security management procedure. The reason why the encryption and pseudonymisation functions failed is that these functions heavily slowed down the system and service performance. An extra 150% of resources are needed to cover this. The Service Manager agreed that access control is good enough and acceptable. That's why the Service Manager signed the approval.

You are preparing the audit findings. Select the correct option.

    There is a nonconformity (NC). The organisation and developer do not perform acceptance tests. (Relevant to clause 8.1, control A.8.29)

Options:

A.

There is a nonconformity (NC). The Service Manager does not comply with the software security management procedure. (Relevant to clause 8.1, control A.8.30)

B.

There is a nonconformity (NC). The organisation and developer perform security tests that fail. (Relevant to clause 8.1, control A.8.29)

C.

There is NO nonconformity (NC). The Service Manager makes a good decision to continue the service. (Relevant to clause 8.1, control A.8.30)

Buy Now
Questions 85

You are an ISMS audit team leader tasked with conducting a follow-up audit at a client's data centre. Following two days on-site you conclude that of the original 12 minor and 1 major nonconformities that prompted the follow-up audit, only 1 minor nonconformity still remains outstanding.

Select four options for the actions you could take.

Options:

A.

Agree with the auditee/audit client how the remaining nonconformity will be cleared, by when, and how its clearance will be verified

B.

Recommend that the outstanding minor nonconformity is dealt with at the next surveillance audit

C.

Close the follow-up audit as the organisation has demonstrated it is committed to clearing the nonconformities raised

D.

Recommend suspension of the organisation's certification as they have failed to implement the agreed corrections and corrective actions within the agreed timescale

E.

Advise the auditee that you will arrange for the next audit to be an online audit to deal with the outstanding nonconformity

F.

Note the progress made but hold the audit open until all corrective action has been cleared

G.

Advise the individual managing the audit programme of any decision taken regarding the outstanding nonconformity

Buy Now
Questions 86

The auditor used sampling to ensure that event logs recording information security events are maintained and regularly reviewed. Sampling was based on the audit objectives, whereas the sample selection process was based on the probability theory. What type of sampling was used?

Options:

A.

Statistical sampling

B.

Judgment-based sampling

C.

Systematic sampling

Buy Now
Questions 87

Which two of the following options do not participate in a first-party audit?

Options:

A.

A certification body auditor

B.

An audit team from an accreditation body

C.

An auditor certified by CQI and IRCA

D.

An auditor from a consultancy organisation

E.

An auditor trained in the CQI and IRCA scheme

F.

An auditor trained in the organization

Buy Now
Questions 88

After completing Stage 1 and in preparation for a Stage 2 initial certification audit, the auditee informs the audit team leader that they wish to extend the audit scope to include two additional sites that have recently been acquired by the organisation.

Considering this information, what action would you expect the audit team leader to take?

Options:

A.

Increase the length of the Stage 2 audit to include the extra sites

B.

Obtain information about the additional sites to inform the certification body

C.

Arrange to complete a remote Stage 1 audit of the two sites using a video conferencing platform

D.

Inform the auditee that the request can be accepted but a full Stage 1 audit must be repeated

Buy Now
Questions 89

You are performing an ISMS audit at a European-based residential

nursing home called ABC that provides healthcare services. You find all

nursing home residents wear an electronic wristband for monitoring

their location, heartbeat, and blood pressure always. You learned that

the electronic wristband automatically uploads all data to the artificial

intelligence (AI) cloud server for healthcare monitoring and analysis by

healthcare staff.

The next step in your audit plan is to verify that the information security

policy and objectives have been established by top management.

During the audit, you found the following audit evidence.

Match the audit evidence to the corresponding requirement in ISO/IEC 27001:2022.

ISO-IEC-27001-Lead-Auditor Question 89

Options:

Buy Now
Questions 90

A marketing agency has developed its own risk assessment approach as part of the ISMS implementation. Is this acceptable?

Options:

A.

Yes, any risk assessment methodology that complies with the ISO/IEC 27001 requirements can be used

B.

Yes, only if the risk assessment methodology is aligned with recognized risk assessment methodologies

C.

No, when implementing an ISMS, the risk assessment methodology provided by ISO/IEC 27001 should be used

Buy Now
Questions 91

The auditor should consider (1)-------when determining the (2)--------

Options:

A.

(1) Standard requirements. (2) audit criteria

B.

(1) Audit risks, (2) audit objectives

C.

(1) Penalties related to legal noncompliance, (2) materiality

Buy Now
Questions 92

Question:

A marketing agency has developed its risk assessment approach as part of the ISMS implementation. Is this acceptable?

Options:

A.

Yes, any risk assessment methodology that complies with the ISO/IEC 27001 requirements can be used

B.

Yes, only if the risk assessment methodology is aligned with recognized risk assessment methodologies

C.

No, the risk assessment methodology provided by ISO/IEC 27001 should be used when implementing an ISMS

Buy Now
Questions 93

Scenario 7: Lawsy is a leading law firm with offices in New Jersey and New York City. It has over 50 attorneys offering sophisticated legal services to clients in business and commercial law, intellectual property, banking, and financial services. They believe they have a comfortable position in the market thanks to their commitment to implement information security best practices and remain up to date with technological developments.

Lawsy has implemented, evaluated, and conducted internal audits for an ISMS rigorously for two years now. Now, they have applied for ISO/IEC 27001 certification to ISMA, a well-known and trusted certification body.

During stage 1 audit, the audit team reviewed all the ISMS documents created during the implementation. They also reviewed and evaluated the records from management reviews and internal audits.

Lawsy submitted records of evidence that corrective actions on nonconformities were performed when necessary, so the audit team interviewed the internal auditor. The interview validated the adequacy and frequency of the internal audits by providing detailed insight into the internal audit plan and procedures.

The audit team continued with the verification of strategic documents, including the information security policy and risk evaluation criteria. During the information security policy review, the team noticed inconsistencies between the documented information describing governance framework (i.e., the information security policy) and the procedures.

Although the employees were allowed to take the laptops outside the workplace, Lawsy did not have procedures in place regarding the use of laptops in such cases. The policy only provided general information about the use of laptops. The company relied on employees' common knowledge to protect the confidentiality and integrity of information stored in the laptops. This issue was documented in the stage 1 audit report.

Upon completing stage 1 audit, the audit team leader prepared the audit plan, which addressed the audit objectives, scope, criteria, and procedures.

During stage 2 audit, the audit team interviewed the information security manager, who drafted the information security policy. He justified the Issue identified in stage 1 by stating that Lawsy conducts mandatory information security training and awareness sessions every three months.

Following the interview, the audit team examined 15 employee training records (out of 50) and concluded that Lawsy meets requirements of ISO/IEC 27001 related to training and awareness. To support this conclusion, they photocopied the examined employee training records.

Based on the scenario above, answer the following question:

The audit team concluded that Lawsy meets the ISO/IEC 27001's requirements related to training and awareness by examining 15 out of 50 employee training records, as provided in scenario 7. This is a risk or error related to:

Options:

A.

The auditor

B.

Sampling

C.

The sample size

Buy Now
Questions 94

Scenario 6

Sinvestment is an insurance provider that offers a wide range of coverage options, including home, commercial, and life insurance. Originally established in North California, the company has expanded its operations to other locations, including Europe and Africa. In addition to its growth, Sinvestment is committed to complying with laws and regulations applicable to its industry and preventing any information security incident. They have implemented an information security management system (ISMS) based on ISO/IEC 27001 and have applied for certification.

A team of auditors was assigned by the certification body to conduct the audit. After signing a confidentiality agreement with Sinvestment, they started the audit activities. For the activities of the stage 1 audit, it was decided that they would be performed on site, except the review of documented information, which took place remotely, as requested by Sinvestment.

The audit team started the stage 1 audit by reviewing the documentation required, including the declaration of the ISMS scope, information security policies, and internal audit reports. The evaluation of the documented information was based on the content and procedure for managing the documented information.

In addition, the auditors found out that the documentation related to information security training and awareness programs was incomplete and lacked essential details. When asked, Sinvestment’s top management stated that the company has provided information security training sessions to all employees.

The stage 2 audit was conducted three weeks after the stage 1 audit. The audit team observed that the marketing department (not included in the audit scope) had no procedures to control employees’ access rights. Since controlling employees' access rights is one of the ISO/IEC 27001 requirements and was included in the company's information security policy, the issue was included in the audit report.

Question

What steps should Sinvestment take in regard to the missing information security training and awareness procedures during the stage 1 audit? Refer to Scenario 6.

Options:

A.

Make the necessary modifications to the documentation and submit the corrected documentation to the audit team before proceeding with the stage 2 audit

B.

Document the identified issue and correct it after the certification audit is completed

C.

Perform a new risk assessment process to understand whether the issue needs modification or not

Buy Now
Questions 95

A property of Information that has the ability to prove occurrence of a claimed event.

Options:

A.

Electronic chain letters 

B.

Integrity

C.

Availability

D.

Accessibility

Buy Now
Questions 96

You are an experienced audit team leader conducting a third-party surveillance audit of an organisation that designs websites for its clients. You are currently reviewing the organisation's Statement of Applicability.

Based on the requirements of ISO/IEC 27001, which two of the following observations about the Statement of Applicability are false?

Options:

A.

A Statement of Applicability must be produced by organisations seeking ISO/IEC 27001 conformity

B.

Justification is only required for any controls that the organisations choses to exclude

C.

Justification for both the inclusion and exclusion of Annex A controls in the Statement of Applicability is required

D.

The Statement of Applicability is owned and amended by the organisation's top management

E.

Additional controls not included in Appendix A may be added to the Statement of Applicability if the organisation choses to do so

F.

The Statement of Applicability must include Organisational, Physical, People and Technological controls that are necessary

Buy Now
Questions 97

Scenario 2: Knight is an electronics company from Northern California, US that develops video game consoles. Knight has more than 300 employees worldwide. On the

fifth anniversary of their establishment, they have decided to deliver the G-Console, a new generation video game console aimed for worldwide markets. G-Console is

considered to be the ultimate media machine of 2021 which will give the best gaming experience to players. The console pack will include a pair of VR headset, two

games, and other gifts.

Over the years, the company has developed a good reputation by showing integrity, honesty, and respect toward their customers. This good reputation is one of the

reasons why most passionate gamers aim to have Knight's G-console as soon as it is released in the market. Besides being a very customer-oriented company, Knight

also gained wide recognition within the gaming industry because of the developing quality. Their prices are a bit higher than the reasonable standards allow.

Nonetheless, that is not considered an issue for most loyal customers of Knight, as their quality is top-notch.

Being one of the top video game console developers in the world, Knight is also often the center of attention for malicious activities. The company has had an

operational ISMS for over a year. The ISMS scope includes all departments of Knight, except Finance and HR departments.

Recently, a number of Knight's files containing proprietary information were leaked by hackers. Knight's incident response team (IRT) immediately started to analyze

every part of the system and the details of the incident.

The IRT's first suspicion was that Knight's employees used weak passwords and consequently were easily cracked by hackers who gained unauthorized access to their

accounts. However, after carefully investigating the incident, the IRT determined that hackers accessed accounts by capturing the file transfer protocol (FTP) traffic.

FTP is a network protocol for transferring files between accounts. It uses clear text passwords for authentication.

Following the impact of this information security incident and with IRT's suggestion, Knight decided to replace the FTP with Secure Shell (SSH) protocol, so anyone

capturing the traffic can only see encrypted data.

Following these changes, Knight conducted a risk assessment to verify that the implementation of controls had minimized the risk of similar incidents. The results of

the process were approved by the ISMS project manager who claimed that the level of risk after the implementation of new controls was in accordance with the

company's risk acceptance levels.

Based on this scenario, answer the following question:

Which risk treatment option has Knight used in replacing FTP with SSH? Refer to scenario 2.

Options:

A.

Risk retention

B.

Risk avoidance

C.

Risk modification

Buy Now
Questions 98

Scenario:

Northstorm is an online retail shop offering unique vintage and modern accessories. It initially entered a small market but gradually grew thanks to the development of the overall e-commerce landscape. Northstorm works exclusively online and ensures efficient payment processing, inventory management, marketing tools, and shipment orders. It uses prioritized ordering to receive, restock, and ship its most popular products.

Northstorm has traditionally managed its IT operations by hosting its website and maintaining full control over its infrastructure, including hardware, software, and data administration. However, this approach hindered its growth due to the lack of responsive infrastructure. Seeking to enhance its e-commerce and payment systems, Northstorm opted to expand its in-house data centers, completing the expansion in two phases over three months. Initially, the company upgraded its core servers, point-of-sale, ordering, billing, database, and backup systems. The second phase involved improving mail, payment, and network functionalities. Additionally, during this phase, Northstorm adopted an international standard for personally identifiable information (PII) controllers and PII processors regarding PII processing to ensure its data handling practices were secure and compliant with global regulations.

Despite the expansion, Northstorm's upgraded data centers failed to meet its evolving business demands. This inadequacy led to several new challenges, including issues with order prioritization. Customers reported not receiving priority orders, and the company struggled with responsiveness. This was largely due to the main server's inability to process orders from YouDecide, an application designed to prioritize orders and simulate customer interactions. The application, reliant on advanced algorithms, was incompatible with the new operating system (OS) installed during the upgrade.

Faced with urgent compatibility issues, Northstorm quickly patched the application without proper validation, leading to the installation of a compromised version. This security lapse resulted in the main server being affected and the company's website going offline for a week. Recognizing the need for a more reliable solution, the company decided to outsource its website hosting to an e-commerce provider. The company signed a confidentiality agreement concerning product ownership and conducted a thorough review of user access rights to enhance security before transitioning.

Question:

Based on Scenario 1, which international standard did Northstorm adopt during the second phase of expansion?

Options:

A.

ISO/IEC 27701

B.

ISO/IEC 27009

C.

ISO/IEC 27003

Buy Now
Questions 99

Which two activities align with the “Check’’ stage of the Plan-Do-Check-Act cycle when applied to the process of managing an internal audit program as described in ISO 19011?

Options:

A.

Retains records of internal audits

B.

Define audit criteria and scope for each internal audit

C.

Update the internal audit programme

D.

Establish a risk-based internal audit programme

E.

Conduct internal audits

F.

Verify effectiveness of the internal audit programme

G.

Review trends in internal audit result

Buy Now
Questions 100

Question:

Which type of audit requires that the auditee and audit team agree on remote access protocols before conducting the audit?

Options:

A.

Virtual

B.

Internal

C.

External

Buy Now
Questions 101

Scenario 4: Branding is a marketing company that works with some of the most famous companies in the US. To reduce internal costs. Branding has outsourced the software development and IT helpdesk operations to Techvology for over two years. Techvology. equipped with the necessary expertise, manages Branding's software, network, and hardware needs. Branding has implemented an information security management system (ISMS) and is certified against ISO/IEC 27001, demonstrating its commitment to maintaining high standards of information security. It actively conducts audits on Techvology to ensure that the security of its outsourced operations complies with ISO/IEC 27001 certification requirements.

During the last audit. Branding's audit team defined the processes to be audited and the audit schedule. They adopted an evidence based approach, particularly in light of two information security incidents reported by Techvology in the past year The focus was on evaluating how these incidents were addressed and ensuring compliance with the terms of the outsourcing agreement

The audit began with a comprehensive review of Techvology's methods for monitoring the quality of outsourced operations, assessing whether the services provided met Branding's expectations and agreed-upon standards The auditors also verified whether Techvology complied with the contractual requirements established between the two entities This involved thoroughly examining the terms and conditions in the outsourcing agreement to guarantee that all aspects, including information security measures, are being adhered to.

Furthermore, the audit included a critical evaluation of the governance processes Techvology uses to manage its outsourced operations and other organizations. This step is crucial for Branding to verify that proper controls and oversight mechanisms are in place to mitigate potential risks associated with the outsourcing arrangement.

The auditors conducted interviews with various levels of Techvology's personnel and analyzed the incident resolution records. In addition, Techvology provided the records that served as evidence that they conducted awareness sessions for the staff regarding incident management. Based on the information gathered, they predicted that both information security incidents were caused by incompetent personnel. Therefore, auditors requested to see the personnel files of the employees involved in the incidents to review evidence of their competence, such as relevant experience, certificates, and records of attended trainings.

Branding's auditors performed a critical evaluation of the validity of the evidence obtained and remained alert for evidence that could contradict or question the reliability of the documented information received. During the audit at Techvology, the auditors upheld this approach by critically assessing the incident resolution records and conducting thorough interviews with employees at different levels and functions. They did not merely take the word of Techvology's representatives for facts; instead, they sought concrete evidence to support the representatives' claims about the incident management processes.

Based on the scenario above, answer the following question:

Question:

Were the auditors diligent in adhering to the auditing process for outsourced operations?

Options:

A.

Yes, they demonstrated diligence and judgment in their auditing practices

B.

No, the auditors did not request a sample of employment contracts until the end of the audit

C.

No, the auditors did not interview any of Techvology’s top management during the audit

Buy Now
Questions 102

Scenario 2: Knight is an electronics company from Northern California, US that develops video game consoles. Knight has more than 300 employees worldwide. On the

fifth anniversary of their establishment, they have decided to deliver the G-Console, a new generation video game console aimed for worldwide markets. G-Console is

considered to be the ultimate media machine of 2021 which will give the best gaming experience to players. The console pack will include a pair of VR headset, two

games, and other gifts.

Over the years, the company has developed a good reputation by showing integrity, honesty, and respect toward their customers. This good reputation is one of the

reasons why most passionate gamers aim to have Knight's G-console as soon as it is released in the market. Besides being a very customer-oriented company, Knight

also gained wide recognition within the gaming industry because of the developing quality. Their prices are a bit higher than the reasonable standards allow.

Nonetheless, that is not considered an issue for most loyal customers of Knight, as their quality is top-notch.

Being one of the top video game console developers in the world, Knight is also often the center of attention for malicious activities. The company has had an

operational ISMS for over a year. The ISMS scope includes all departments of Knight, except Finance and HR departments.

Recently, a number of Knight's files containing proprietary information were leaked by hackers. Knight's incident response team (IRT) immediately started to analyze

every part of the system and the details of the incident.

The IRT's first suspicion was that Knight's employees used weak passwords and consequently were easily cracked by hackers who gained unauthorized access to their

accounts. However, after carefully investigating the incident, the IRT determined that hackers accessed accounts by capturing the file transfer protocol (FTP) traffic.

FTP is a network protocol for transferring files between accounts. It uses clear text passwords for authentication.

Following the impact of this information security incident and with IRT's suggestion, Knight decided to replace the FTP with Secure Shell (SSH) protocol, so anyone

capturing the traffic can only see encrypted data.

Following these changes, Knight conducted a risk assessment to verify that the implementation of controls had minimized the risk of similar incidents. The results of

the process were approved by the ISMS project manager who claimed that the level of risk after the implementation of new controls was in accordance with the

company's risk acceptance levels.

Based on this scenario, answer the following question:

Based on scenario 2, Knight decided to replace the FTP with Secure Shell (SSH) protocol. Should the Statement of Applicability (SoA) be updated in this case?

Options:

A.

No, the usage of SSH protocol is not an ISO/IEC 27001 requirement and; therefore, does not need to be included in the SoA

B.

No, because the SoA should be updated only when new controls are added, not when old ones are canceled

C.

Yes, the implementation of the new control should be justified and included in the SoA

Buy Now
Questions 103

Select the word that best completes the sentence:

ISO-IEC-27001-Lead-Auditor Question 103

Options:

Buy Now
Questions 104

Scenario 4

SendPay is a financial services company specializing in global money transfers through a network of agents and institutions. As a new company in the market, SendPay aims to deliver top-quality services with its fee-free digital platform, launched last year, enabling clients to send and receive money anytime via smartphones and laptops. At that time, SendPay outsourced software operations to an external team, which also managed the company's technology infrastructure.

Recently, the company applied for ISO/IEC 27001 certification after having an ISMS in place for almost a year.

During the audit, the auditors focused on reviewing SendPay’s outsourced operations, specifically looking at the software development and technology infrastructure maintenance handled by the outsourced company. They followed a structured approach, which included reviewing and evaluating SendPay’s processes for monitoring the quality of these outsourced operations. This included verifying if the company met its contractual obligations, ensuring proper governance procedures for engaging outsourced entities, and assessing SendPay’s plans in case of expected or unexpected termination of outsourcing agreements.

However, the auditors subtly noted that SendPay’s protocols did not fully address contingencies for unanticipated cancellations of outsourcing agreements. Additionally, a technical expert appointed by SendPay assisted the auditors, providing specific knowledge and expertise related to the outsourced operations being audited.

The audit team calculated the number of training hours employees received on ISMS to ensure alignment with established objectives. They also computed the average resolution time of information security incidents based on a sample taken during the audit, which provided valuable insights into SendPay’s incident management practices. In addition, the auditors evaluated the reliability of the evidence collected during the audit. They considered several factors influencing the reliability of audit evidence. For example, evidence from surveillance cameras provided more objective proof compared to photos. Timing also played a crucial role in reliability, with mechanisms like transaction recording enhancing the credibility of the evidence.

SendPay uses cloud-based platforms to make its operations more efficient and scalable. However, during the audit, the auditors did not request SendPay to provide an inventory of their cloud activities due to resource limitations, relying instead on SendPay’s representations.

Question

Did the audit at SendPay include all the necessary steps for auditing outsourced operations?

Options:

A.

Yes, the audit examined all aspects of outsourced operations.

B.

No, the audit overlooked crucial steps, such as reviewing termination plans.

C.

No, as the audit team only focused on the steps related to monitoring the quality of outsourced operations.

Buy Now
Questions 105

Scenario 3: Rebuildy is a construction company located in Bangkok.. Thailand, that specializes in designing, building, and maintaining residential buildings. To ensure the security of sensitive project data and client information, Rebuildy decided to implement an ISMS based on ISO/IEC 27001. This included a comprehensive understanding of information security risks, a defined continual improvement approach, and robust business solutions.

The ISMS implementation outcomes are presented below

•Information security is achieved by applying a set of security controls and establishing policies, processes, and procedures.

•Security controls are implemented based on risk assessment and aim to eliminate or reduce risks to an acceptable level.

•All processes ensure the continual improvement of the ISMS based on the plan-do-check-act (PDCA) model.

•The information security policy is part of a security manual drafted based on best security practices Therefore, it is not a stand-alone document.

•Information security roles and responsibilities have been clearly stated in every employees job description

•Management reviews of the ISMS are conducted at planned intervals.

Rebuildy applied for certification after two midterm management reviews and one annual internal audit Before the certification audit one of Rebuildy’s former employees approached one of the audit team members to tell them that Rebuildy has several security problems that the company is trying to conceal. The former employee presented the documented evidence to the audit team member Electra, a key client of Rebuildy, also submitted evidence on the same issues, and the auditor determined to retain this evidence instead of the former employee's. The audit team member remained in contact with Electra until the audit was completed, discussing the nonconformities found during the audit. Electra provided additional evidence to support these findings.

At the beginning of the audit, the audit team interviewed the company’s top management They discussed, among other things, the top management's commitment to the ISMS implementation. The evidence obtained from these discussions was documented in written confirmation, which was used to determine Rebuildy’s conformity to several clauses of ISO/IEC 27001

The documented evidence obtained from Electra was attached to the audit report, along with the nonconformities report. Among others, the following nonconformities were detected:

•An instance of improper user access control settings was detected within the company's financial reporting system.

•A stand-alone information security policy has not been established. Instead, the company uses a security manual drafted based on best security practices.

After receiving these documents from the audit team, the team leader met Rebuildy’s top management to present the audit findings. The audit team reported the findings related to the financial reporting system and the lack of a stand-alone information security policy. The top management expressed dissatisfaction with the findings and suggested that the audit team leader's conduct was unprofessional, implying they might request a replacement. Under pressure, the audit team leader decided to cooperate with top management to downplay the significance of the detected nonconformities. Consequently, the audit team leader adjusted the report to present a more favorable view, thus misrepresenting the true extent of Rebuildy's compliance issues.

Based on the scenario above, answer the following question:

Question:

Based on the last paragraph of Scenario 3, what did the audit team leader commit?

Options:

A.

Ordinary negligence

B.

Gross negligence

C.

Fraud

Buy Now
Questions 106

You are an experienced ISMS audit team leader conducting a third-party surveillance audit of an internet services provider. You are reviewing the organization's risk assessment processes for conformity with ISO/IEC 27001:2022.

Which three of the following audit findings would prompt you to raise a nonconformity report?

Options:

A.

Both systems contain additional information security risks which are not associated with preserving the confidentiality, integrity and accessibility of information

B.

The organisation is treating information security risks in the order in which they are identified

C.

The organisation's information security risk assessment process suggests each risk is allocated a risk owner

D.

The organisation has not used RAG (Red, Amber, Green) to classify its' information security risks. Instead, it has used a smiling emoji, a neutral face emoji and a sad face emoji

E.

The organisation's risk assessment criteria have not been reviewed and approved by top management

F.

The organisation's information security risk assessment process is based solely on an assessment of the impact of each risk

G.

The organisation has assessed the probability of all of its information security risks as either 0%, 25%, 50%, 75% or 100%

Buy Now
Questions 107

Implement plan on a test basis - this comes under which section of PDCA

Options:

A.

Plan

B.

Do

C.

Act

D.

Check

Buy Now
Questions 108

What is meant by the term 'Corrective Action'? Select one

Options:

A.

Action is taken to prevent a nonconformity or an incident from occurring

B.

Action is taken to eliminate the cause(s) of a nonconformity or an incident

C.

Action is taken by management to respond to a nonconformity

D.

Action is taken to fix a nonconformity or an incident

Buy Now
Questions 109

Scenario 9

CloudFort, a small networking company, provides network security, cloud computing, and virtualization solutions. The company has recently been certified in an information security management system (ISMS) based on the ISO/IEC 27001 standard, which has resulted in a spike in its recognition, confirming the maturity of CloudFort’s operations.

CloudFort continually reviewed and enhanced its security controls and the overall effectiveness and efficiency of the ISMS by conducting internal audits. Due to its size and desire for greater objectivity, top management decided to outsource the internal audit function to ensure the internal audit is independent of the audited activities and holds an advisory role in the continual improvement of the ISMS.

After the initial certification audit, the company created a new department specializing in data storage solutions. It offered routers and switches optimized for data centers and software-based networking devices, such as network virtualization and network security appliances. Because of the new department, CloudFort initiated a risk assessment process and an internal audit. Following the internal audit results, the company confirmed the effectiveness and efficiency of the new processes and controls.

After determining that the new department fully complies with ISO/IEC 27001 requirements, top management decided to include it in the certification scope. They submitted a request to the certification body for an extension of the certification scope to ensure that the department’s processes and security measures fully align with the overall ISMS.

One year after the initial certification audit, the certification body conducted another audit of CloudFort's ISMS. This audit aimed to determine CloudFort’s ISMS fulfillment of specified ISO/IEC 27001 requirements and ensure continual improvement. The audit team confirmed that the certified ISMS fulfills the standard requirements. Nonetheless, the new department introduced changes that significantly affected how the overall management system was governed, requiring updates to existing processes and controls.

Moreover, although CloudFort requested an extension of the certification scope, they failed to provide timely updates on the impact of the new department on the ISMS to the certification body. Thus, CloudFort’s certification was suspended.

Question

Based on Scenario 9, why was CloudFort’s certification suspended?

Options:

A.

Because it applied the certification beyond its approved scope, despite submitting a request for scope extension

B.

Because it outsourced the internal audit function

C.

Because its ISMS does not fulfill the requirements of the standard

Buy Now
Questions 110

Scenario 9: UpNet, a networking company, has been certified against ISO/IEC 27001. It provides network security, virtualization, cloud computing, network hardware, network management software, and networking technologies.

The company's recognition has increased drastically since gaining ISO/IEC 27001 certification. The certification confirmed the maturity of UpNefs operations and its compliance with a widely recognized and accepted standard.

But not everything ended after the certification. UpNet continually reviewed and enhanced its security controls and the overall effectiveness and efficiency of the ISMS by conducting internal audits. The top management was not willing to employ a full-time team of internal auditors, so they decided to outsource the internal audit function. This form of internal audits ensured independence, objectivity, and that they had an advisory role about the continual improvement of the ISMS.

Not long after the initial certification audit, the company created a new department specialized in data and storage products. They offered routers and switches optimized for data centers and software-based networking devices, such as network virtualization and network security appliances. This caused changes to the operations of the other departments already covered in the ISMS certification scope.

Therefore. UpNet initiated a risk assessment process and an internal audit. Following the internal audit result, the company confirmed the effectiveness and efficiency of the existing and new processes and controls.

The top management decided to include the new department in the certification scope since it complies with ISO/IEC 27001 requirements. UpNet announced that it is ISO/IEC 27001 certified and the certification scope encompasses the whole company.

One year after the initial certification audit, the certification body conducted another audit of UpNefs ISMS. This audit aimed to determine the UpNefs ISMS fulfillment of specified ISO/IEC 27001 requirements and ensure that the ISMS is being continually improved. The audit team confirmed that the certified ISMS continues to fulfill

the requirements of the standard. Nonetheless, the new department caused a significant impact on governing the management system. Moreover, the certification body was not informed about any changes. Thus, the UpNefs certification was suspended.

Based on the scenario above, answer the following question:

UpNet announced that the ISMS certification scope encompasses the whole company once ensuring that the new department also complies with the ISO/IEC 27001 requirements. How would you classify this situation illustrated in scenario 9?

Options:

A.

Unacceptable, the internal auditor should have approved the extension audit, not the top management

B.

Unacceptable, UpNet should have requested and granted an extension audit prior to making the announcement

C.

Acceptable, the internal audit confirmed the effectiveness and efficiency of the existing and new processes and controls

Buy Now
Questions 111

In the context of a third-party certification audit, it is very important to have effective communication. Select an option that contains the correct answer about communication in an audit context.

Options:

A.

During the audit, each auditor should periodically communicate any concerns to the auditee and audit client

B.

During the audit, the responibility for communication rests with the audit team leader

C.

The formal communication channels between the audit team and the auditee can be established during the opening meeting

D.

There is no need to establish a formal communication arrangement because an auditee can communicate with the auditor at any time during the audit

Buy Now
Questions 112

You receive the following mail from the IT support team: Dear User,Starting next week, we will be deleting all inactive email accounts in order to create spaceshare the below details in order to continue using your account. In case of no response, 

Name:

Email ID:

Password:

DOB:

Kindly contact the webmail team for any further support. Thanks for your attention.

Which of the following is the best response?

Options:

A.

Ignore the email

B.

Respond it by saying that one should not share the password with anyone

C.

One should not respond to these mails and report such email to your supervisor 

Buy Now
Questions 113

You are an experienced ISMS auditor conducting a third-party surveillance audit at an organisation which offers ICT reclamation services. ICT equipment which companies no longer require is processed by the organisation. It Is either recommissioned and reused or is securely destroyed.

You notice two servers on a bench in the corner of the room. Both have stickers on item with the server's name, IP address and admin password. You ask the ICT Manager about them, and he tells you they were part of a shipment received yesterday from a regular customer.

Which one action should you take?

Options:

A.

Ask the ICT Manager to record an information security incident and initiate the information security incident management process

B.

Note the audit finding and check the process for dealing with incoming shipments relating to customer IT security

C.

Record what you have seen in your audit findings, but take no further action

D.

Raise a nonconformity against control 5.31 Legal, staturary, regulatory and contractual requirements'

E.

Raise a nonconformity against control 8.20 'network security’ (networks and network devices shall be secured, managed and controlled to protect information in systems and applications)

F.

Ask the auditee to remove the labels, then carry on with the audit

Buy Now
Questions 114

Scenario 3: Rebuildy is a construction company located in Bangkok.. Thailand, that specializes in designing, building, and maintaining residential buildings. To ensure the security of sensitive project data and client information, Rebuildy decided to implement an ISMS based on ISO/IEC 27001. This included a comprehensive understanding of information security risks, a defined continual improvement approach, and robust business solutions.

The ISMS implementation outcomes are presented below

•Information security is achieved by applying a set of security controls and establishing policies, processes, and procedures.

•Security controls are implemented based on risk assessment and aim to eliminate or reduce risks to an acceptable level.

•All processes ensure the continual improvement of the ISMS based on the plan-do-check-act (PDCA) model.

•The information security policy is part of a security manual drafted based on best security practices Therefore, it is not a stand-alone document.

•Information security roles and responsibilities have been clearly stated in every employees job description

•Management reviews of the ISMS are conducted at planned intervals.

Rebuildy applied for certification after two midterm management reviews and one annual internal audit Before the certification audit one of Rebuildy’s former employees approached one of the audit team members to tell them that Rebuildy has several security problems that the company is trying to conceal. The former employee presented the documented evidence to the audit team member Electra, a key client of Rebuildy, also submitted evidence on the same issues, and the auditor determined to retain this evidence instead of the former employee's. The audit team member remained in contact with Electra until the audit was completed, discussing the nonconformities found during the audit. Electra provided additional evidence to support these findings.

At the beginning of the audit, the audit team interviewed the company’s top management They discussed, among other things, the top management's commitment to the ISMS implementation. The evidence obtained from these discussions was documented in written confirmation, which was used to determine Rebuildy’s conformity to several clauses of ISO/IEC 27001

The documented evidence obtained from Electra was attached to the audit report, along with the nonconformities report. Among others, the following nonconformities were detected:

•An instance of improper user access control settings was detected within the company's financial reporting system.

•A stand-alone information security policy has not been established. Instead, the company uses a security manual drafted based on best security practices.

After receiving these documents from the audit team, the team leader met Rebuildy’s top management to present the audit findings. The audit team reported the findings related to the financial reporting system and the lack of a stand-alone information security policy. The top management expressed dissatisfaction with the findings and suggested that the audit team leader's conduct was unprofessional, implying they might request a replacement. Under pressure, the audit team leader decided to cooperate with top management to downplay the significance of the detected nonconformities. Consequently, the audit team leader adjusted the report to present a more favorable view, thus misrepresenting the true extent of Rebuildy's compliance issues.

Based on the scenario above, answer the following question:

Question:

Which action described in Scenario 3 indicates that the audit team leader violated the independence principle?

Options:

A.

The audit team leader sent a favorable report after discussing the audit conclusions with the top management

B.

The audit team included the former employee’s evidence in the audit report without revealing the source

C.

The audit team leader revealed confidential information about Rebuildy to the former employee

Buy Now
Questions 115

Auditor competence is a combination of knowledge and skills. Which two of the following activities are predominately related to "knowledge"?

Options:

A.

Understanding how to identify findings

B.

Designing a checklist

C.

Follow an audit trail deviating from the prepared checklist

D.

Communicate with the auditee

E.

Determining how to seek evidence from the auditee

F.

Determining what evidence to gather

Buy Now
Questions 116

Which three of the following phrases are objectives' in relation to an audit?

Options:

A.

International Standard

B.

Identify opportunities for improvement

C.

Confirm the scope of the management system

D.

Management policy

E.

Complete audit on time

F.

Regulatory requirements

Buy Now
Questions 117

Scenario 6

Sinvestment is an insurance provider that offers a wide range of coverage options, including home, commercial, and life insurance. Originally established in North California, the company has expanded its operations to other locations, including Europe and Africa. In addition to its growth, Sinvestment is committed to complying with laws and regulations applicable to its industry and preventing any information security incident. They have implemented an information security management system (ISMS) based on ISO/IEC 27001 and have applied for certification.

A team of auditors was assigned by the certification body to conduct the audit. After signing a confidentiality agreement with Sinvestment, they started the audit activities. For the activities of the stage 1 audit, it was decided that they would be performed on site, except the review of documented information, which took place remotely, as requested by Sinvestment.

The audit team started the stage 1 audit by reviewing the documentation required, including the declaration of the ISMS scope, information security policies, and internal audit reports. The evaluation of the documented information was based on the content and procedure for managing the documented information.

In addition, the auditors found out that the documentation related to information security training and awareness programs was incomplete and lacked essential details. When asked, Sinvestment’s top management stated that the company has provided information security training sessions to all employees.

The stage 2 audit was conducted three weeks after the stage 1 audit. The audit team observed that the marketing department (not included in the audit scope) had no procedures to control employees’ access rights. Since controlling employees' access rights is one of the ISO/IEC 27001 requirements and was included in the company's information security policy, the issue was included in the audit report.

Question

Was Sinvestment’s request for reviewing documented information remotely acceptable?

Options:

A.

Yes, documented information can be reviewed remotely.

B.

No, as it can lead to a breach of confidentiality.

C.

No, as the combination of different locations can negatively impact the audit efficiency.

Buy Now
Questions 118

Question:

When multiple offices of a certification body are involved, what must be ensured?

Options:

A.

Each office has a separate legally enforceable agreement with the client

B.

A legally enforceable agreement that covers all sites within the certification scope

C.

Only the main office has a legally enforceable agreement with the client

Buy Now
Questions 119

Scenario 6

Sinvestment is an insurance provider that offers a wide range of coverage options, including home, commercial, and life insurance. Originally established in North California, the company has expanded its operations to other locations, including Europe and Africa. In addition to its growth, Sinvestment is committed to complying with laws and regulations applicable to its industry and preventing any information security incident. They have implemented an information security management system (ISMS) based on ISO/IEC 27001 and have applied for certification.

A team of auditors was assigned by the certification body to conduct the audit. After signing a confidentiality agreement with Sinvestment, they started the audit activities. For the activities of the stage 1 audit, it was decided that they would be performed on site, except the review of documented information, which took place remotely, as requested by Sinvestment.

The audit team started the stage 1 audit by reviewing the documentation required, including the declaration of the ISMS scope, information security policies, and internal audit reports. The evaluation of the documented information was based on the content and procedure for managing the documented information.

In addition, the auditors found out that the documentation related to information security training and awareness programs was incomplete and lacked essential details. When asked, Sinvestment’s top management stated that the company has provided information security training sessions to all employees.

The stage 2 audit was conducted three weeks after the stage 1 audit. The audit team observed that the marketing department (not included in the audit scope) had no procedures to control employees’ access rights. Since controlling employees' access rights is one of the ISO/IEC 27001 requirements and was included in the company's information security policy, the issue was included in the audit report.

Question

According to Scenario 6, was it appropriate for the audit team to include in the audit report the observed deficiency in the marketing department's access rights control procedures?

Options:

A.

Yes, it is a requirement to include in the audit report any findings.

B.

No, it should have been only communicated to the representatives of the auditee.

C.

No, because the marketing department's activities do not pose a potential risk to the ISMS.

Buy Now
Questions 120

Question

A security analyst is performing a penetration test on an organization’s internal network. A vulnerability scanning tool detects a high-risk vulnerability in a critical server, suggesting it could allow remote code execution. However, the penetration tester is unable to exploit the vulnerability successfully due to unknown system configurations and patch levels.

Should the company immediately consider this vulnerability as a confirmed security risk?

Options:

A.

Yes, because findings from vulnerability scanning tools must always be considered confirmed security risks.

B.

No, because failed exploitation means that the vulnerability does not exist.

C.

No, because penetration tools can give false results unless the vulnerability is successfully exploited.

Buy Now
Questions 121

Question:

Which of the following statements regarding documented information in an organization's ISMS is incorrect?

Options:

A.

The purpose of documented information is to guide the ISMS operation and provide evidence of process effectiveness

B.

The collection of documented information should be a target in itself

C.

Documented information should not be detailed and complex to ensure thoroughness

Buy Now
Questions 122

Select the words that best complete the sentence below to describe audit resources:

ISO-IEC-27001-Lead-Auditor Question 122

Options:

Buy Now
Questions 123

Scenario 9: UpNet, a networking company, has been certified against ISO/IEC 27001. It provides network security, virtualization, cloud computing, network hardware, network management software, and networking technologies.

The company's recognition has increased drastically since gaining ISO/IEC 27001 certification. The certification confirmed the maturity of UpNefs operations and its compliance with a widely recognized and accepted standard.

But not everything ended after the certification. UpNet continually reviewed and enhanced its security controls and the overall effectiveness and efficiency of the ISMS by conducting internal audits. The top management was not willing to employ a full-time team of internal auditors, so they decided to outsource the internal audit function. This form of internal audits ensured independence, objectivity, and that they had an advisory role about the continual improvement of the ISMS.

Not long after the initial certification audit, the company created a new department specialized in data and storage products. They offered routers and switches optimized for data centers and software-based networking devices, such as network virtualization and network security appliances. This caused changes to the operations of the other departments already covered in the ISMS certification scope.

Therefore. UpNet initiated a risk assessment process and an internal audit. Following the internal audit result, the company confirmed the effectiveness and efficiency of the existing and new processes and controls.

The top management decided to include the new department in the certification scope since it complies with ISO/IEC 27001 requirements. UpNet announced that it is ISO/IEC 27001 certified and the certification scope encompasses the whole company.

One year after the initial certification audit, the certification body conducted another audit of UpNefs ISMS. This audit aimed to determine the UpNefs ISMS fulfillment of specified ISO/IEC 27001 requirements and ensure that the ISMS is being continually improved. The audit team confirmed that the certified ISMS continues to fulfill

the requirements of the standard. Nonetheless, the new department caused a significant impact on governing the management system. Moreover, the certification body was not informed about any changes. Thus, the UpNefs certification was suspended.

Based on the scenario above, answer the following question:

Based on scenario 9, why was UpNefs certification suspended?

Options:

A.

Because UpNet used and applied the certification out of its scope

B.

Because UpNet outsourced the internal audit function

C.

Because UpNefs ISMS does not fulfill the requirements of the standard

Buy Now
Questions 124

Phishing is what type of Information Security Incident?

Options:

A.

Private Incidents

B.

Cracker/Hacker Attacks

C.

Technical Vulnerabilities

D.

Legal Incidents

Buy Now
Questions 125

Scenario 7

Lawsy is a leading law firm with offices in Bangkok, Thailand. It has over 50 attorneys offering sophisticated legal services to clients in business and commercial law, intellectual property, banking, and financial services. They believe they have a comfortable position in the market thanks to their commitment to implementing information security best practices and remaining up to date with technological developments.

Lawsy has rigorously implemented, evaluated, and conducted internal audits for the information security management system (ISMS) for two years. Now, they have applied for ISO/IEC 27001 certification at ISMA, a well-known and trusted certification body.

During the stage 1 audit, the audit team reviewed all the ISMS documents created during the implementation phase. They also reviewed and evaluated the records from management reviews and internal audits. Lawsy submitted records of evidence that corrective actions on nonconformities were performed when necessary, so the audit team interviewed the internal auditor. The interview validated the adequacy and frequency of the internal audits by providing insight into the internal audit plan and procedures.

The audit team continued verifying strategic documents, including the information security policy and risk evaluation criteria. During the information security policy review, the team noticed inconsistencies between the documented information describing the governance framework and the procedures. Following the completion of stage 1, the audit team leader prepared the audit plan, which addressed the audit objectives, scope, criteria, and procedures.

During the stage 2 audit, the audit team interviewed the information security manager, who drafted the information security policy. He justified the issue identified in stage 1 by stating that Lawsy conducts mandatory information security training and awareness sessions every three months.

Later, the audit team found that Lawsy did not have procedures for using laptops outside the workplace, even though employees were allowed to take laptops outside the workplace. The company only provided general information about the use of laptops and relied on employees’ common knowledge to protect the confidentiality and integrity of information stored on the laptops.

Following the interview, the audit team examined 15 employee training records (out of 50) and concluded that Lawsy meets the requirements of ISO/IEC 27001 related to training and awareness. To support this conclusion, the auditor photocopied and archived the examined employee training records after completing the audit.

Question

During the audit, the team reviewed a sample of training records from 15 out of 50 employees. What does this situation represent? Refer to the scenario.

Options:

A.

Risk related to auditor

B.

Sampling error

C.

Inherent risk

Buy Now
Exam Name: PECB Certified ISO/IEC 27001 2022 Lead Auditor exam
Last Update: Apr 5, 2026
Questions: 418

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now ISO-IEC-27001-Lead-Auditor testing engine

PDF (Q&A)

$31.5  $104.99
buy now ISO-IEC-27001-Lead-Auditor pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 05 Apr 2026