Grab 75% Off This Black Friday: Use coupon code below to save on all exam bundles! - Ends in 0d 00h 00m 00s - Coupon code: 75only

LEED-AP-BD+C LEED AP Building Design + Construction (LEED v5 AP BD+C) Questions and Answers

Questions 4

A likely outcome of IPc1: Integrative Design Process would be to:

Options:

A.

Relocate the project to another site

B.

Decide to downsize an energy-related system

C.

Define the LEED boundary

D.

Finalize the credits to be pursued

Buy Now
Questions 5

In addition to Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Materials Reuse, salvaged materials contribute to the achievement of

Options:

A.

Materials and Resources Prerequisite, Storage and Collection of Recyclables

B.

Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients

C.

Materials and Resources Credit, Construction and Demolition Waste Management

D.

Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations

Buy Now

LEED-AP-BD+C Report Card

Questions 6

A project ' s massing and site orientation can have a direct impact on which of the following prerequisites?

Options:

A.

Minimum Energy Performance

B.

Minimum Indoor Air Quality Performance

C.

Construction Activity Pollution Prevention

D.

Fundamental Commissioning and Verification

Buy Now
Questions 7

How can the additional energy needed to increase the ventilation in a building be mitigated?

Options:

A.

Use economizer strategies

B.

Use higher-rated MERV filters

C.

Use high-pressure drop filters

D.

Reduce the size of the ventilation ductwork

Buy Now
Questions 8

The design team has specified products to achieve Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices for the project. At the end of the construction, it was discovered that the transporter who shipped a portion of the wood did not have chain-of-custody (CoC) certification. The design team should do which of the following?

Options:

A.

Submit a Credit Interpretation Ruling (CIR) to get clarification from USGBC

B.

Recalculate the percent of certified wood and consider the affected wood as non-certified

C.

Recalculate the percent of certified wood and delete the affected wood from the calculation

D.

Remove and replace the affected wood from the project site

Buy Now
Questions 9

To achieve LEED points under MRc2 Reduce Embodied Carbon, Option 3: Track Carbon Emissions from Construction Activities, it requires:

Options:

A.

On-site adherence to the AGC Playbook on Decarbonization and Carbon Reporting

B.

Documenting type and amounts of all on-site usage of fuel and utilities

C.

Creating a plan to achieve a reduction of on-site carbon emissions

Buy Now
Questions 10

Which of the following strategies will aid in reducing indoor water use?

Options:

A.

Design drip irrigation for landscape

B.

Use high-efficiency HVAC systems

C.

Exclude janitor closets in the building

D.

Optimize consumption of showerheads

Buy Now
Questions 11

Which of the following filtration methods is recommended for an infection risk management mode to enhance indoor air quality (IAQ) in healthcare facilities?

Options:

A.

Activated carbon filtration

B.

Plate-and-frame filters

C.

Ultraviolet germicidal irradiation (UVGI)

Buy Now
Questions 12

The goal of the design charrette during Integrative Process Prerequisite, Integrative Project Planning and Design is to:

Options:

A.

Develop the building energy model

B.

Optimize the green strategies across all aspects

C.

Calculate the life cycle cost of the building

D.

Choose an appropriate Commissioning Authority (CxA)

Buy Now
Questions 13

Which of the following statements is true for SSp1: Minimize Site Disturbance, Erosion and Sedimentation Control (ESC) plan compliance?

Options:

A.

A compliant ESC plan may be developed after construction

B.

A compliant ESC plan must be in place when the commissioning authority is appointed

C.

An ESC plan, or local equivalent, is not required for projects outside the U.S.

D.

The ESC plan requires a detailed site description outlining potential erosion risks

Buy Now
Questions 14

A comprehensive rainwater management plan may include design elements such as

Options:

A.

artificial turf, bioretention pond, cisterns and hay bales

B.

cisterns, porous pavement, swales and vegetated roofs

C.

soil compaction, swales, vegetated roofs and xeriscaping

D.

bioretention pond, cisterns, porous pavement and stabilized construction entrance

Buy Now
Questions 15

A new theater is being designed to enhance acoustical comfort for its audiences. One of the main challenges the design team faces is minimizing excessive reverberation. The team plans to incorporate various materials and design strategies to control sound reflections.

Which of the following design strategies should effectively enhance acoustical comfort?

Options:

A.

Install hard flooring surfaces throughout the theater

B.

Maximize the use of soundproof glass walls and windows

C.

Utilize ceiling baffles and wall panels made from sound-absorbing materials

Buy Now
Questions 16

The Lakeside Resort is located approximately 60 mi. (96.6 km) from the nearest town. Occupants are expected to arrive primarily by automobile, and existing public transportation consists of approximately one bus trip per day.

The project wants to earn as many Location and Transportation (LT) credits as possible. Which of the following strategies helps achieve points under LTc3: Compact and Connected Development, Option 2. Access to Transit?

Options:

A.

Offer a private shuttle that runs occupants into the nearest town and to local attractions with a minimum three-year commitment. Build a covered transit shelter for occupants to use while they wait for the shuttle.

B.

Implement a carpool incentive program that gives guests and employees incentives to carpool to the project and from the project to local attractions and into town.

C.

Count the bus trip(s) from the project to the local town and the bus trips occupants can connect with once they are in town. The project anticipates 70 possible rides per day on weekdays and 27 on weekends with all bus options combined.

Buy Now
Questions 17

The owner has stated a desire to provide a variety of non-automobile commuting options for the future occupants.

What credits should the LEED AP suggest to meet this goal?

Options:

A.

Sustainable Sites Credit, Heat Island Reduction and Location and Transportation Credit, Bicycle Facilities

B.

Location and Transportation Credit, Access to Quality Transit and Location and Transportation Credit, Sensitive Land Protection

C.

Location and Transportation Credit, Surrounding Density and Diverse Uses and Sustainable Sites Credit, Open Space

D.

Location and Transportation Credit, Reduced Parking Footprint and Location and Transportation Credit, Access to Quality Transit

Buy Now
Questions 18

Which group of chemicals emitted by some building materials is linked to asthma, chronic obstructive pulmonary disease, and cancer?

Options:

A.

Nitrogen Oxides (NOx)

B.

Polyvinyl Chlorides (PVCs)

C.

Chlorofluorocarbons (CFCs)

D.

Volatile Organic Compounds (VOCs)

Buy Now
Questions 19

To ensure long-term energy efficiency and grid resilience, which strategy should the project team prioritise first?

Options:

A.

Provide a high-performance building envelope

B.

Enrol in a demand-response programme with the local utility

C.

Purchase 100% Renewable Energy Certificates to offset projected electricity use

Buy Now
Questions 20

A mixed-use development is located 1/2 mi. (0.80 km) from a future commuter rail line station. Which of the following pieces of information is needed when determining whether the rail line station can contribute to Location and Transportation Credit, Access to Quality Transit?

Options:

A.

Discounted rail pass availability

B.

Rail line station construction completion date

C.

Connections to transfer routes

D.

Passenger capacity

Buy Now
Questions 21

A building owner installs a building automation system (BAS) to allow programmable load control. Which of the

following credits can be pursued because of the installation?

Options:

A.

Energy and Atmosphere Credit, Demand ResponseB Energy and Atmosphere Credit, Ongoing Commissioning

B.

Energy and Atmosphere Credit, Enhanced Commissioning

C.

Energy and Atmosphere Credit, Enhanced Refrigerant Management

Buy Now
Questions 22

A LEED Building Design and Construction: New Construction office building ' s HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level

Energy Metering, an energy meter must be installed for

Options:

A.

natural gas

B.

hot water at the main service point

C.

nothing, because the flat fee is included as part of the lease

D.

nothing, because the energy source is outside of the project ' s scope

Buy Now
Questions 23

Which of the following sinks is classified as a private lavatory faucet under Water Efficiency Credit, Indoor Water Use Reduction?

Options:

A.

A sink in an office restroom

B.

A sink in a school classroom

C.

A sink in a hotel room bathroom

D.

A sink in a shared office restroom

Buy Now
Questions 24

Which of the following characteristics of a biophilic environment supports occupant quality of life?

Options:

A.

Direct line of sight to natural environments

B.

Use of artificial lighting throughout the space

C.

Mechanical ventilation systems

Buy Now
Questions 25

When should collaboration start for the integrative process?

Options:

A.

Before finalizing the design

B.

During predesign

C.

Before competitive project bidding

D.

Before construction

Buy Now
Questions 26

The project landscape architect suggests reducing the area planned for surface parking and replacing it with additional vegetated space. What benefit would this strategy provide to the owner?

Options:

A.

Increases the rainwater infiltration capacity

B.

Decreases the amount of bicycle parking that must be provided

C.

Increases the overall SR (solar reflectance) of the hardscape area

D.

Decreases the required amount of on-street parking that must be provided

Buy Now
Questions 27

One point can be achieved through Sustainable Sites Credit, Heat Island Reduction by providing:

Options:

A.

Preferred parking for green vehicles

B.

A minimum of 75% of parking spaces under cover

C.

Access to public transportation stops

D.

A roof with artificial turf grass

Buy Now
Questions 28

The required minimum scope of analysis for a product-specific declaration that contributes toward Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations, Option 1. Environmental Product Declaration is

Options:

A.

gate-to-gate

B.

cradle-to-gate

C.

cradle-to-grave

D.

cradle-to-cradle

Buy Now
Questions 29

Which of the following requires standard appliances for indoor water reduction?

Options:

A.

CEE Tier 3A

B.

GreenSeal

C.

ASHRAE Standard 62.1-2010

D.

ISO 14044-2006

Buy Now
Questions 30

Which of the following components is critical for developing a successful water-balance model for WEc2: Enhanced Water Efficiency, Option 1. Whole-Project Water Use?

Options:

A.

Identify all end uses within the project scope, including fixtures and fittings

B.

Prioritise alternative water sources to offset overall water demand

C.

Require equipment specifications to align with the contract documents

Buy Now
Questions 31

A project team is designing a new mixed-use development that aims to achieve LEED certification. To encourage electric-vehicle use, the team plans to install EV charging stations in the parking garage. The project site is in a region where 70% of electricity comes from renewable sources.

To align with LEED strategies for sustainable transportation, what consideration should the project team prioritize when installing the EV charging stations?

Options:

A.

Availability of real-time energy-consumption monitoring at the charging stations

B.

Provision of free parking for EV users near the charging stations

C.

Number of charging stations in proportion to the total number of parking spaces

Buy Now
Questions 32

Which of the following projects are eligible for LEED certification?

Options:

A.

Prefabricated sandwich panel house

B.

New office building900 ft² (83.6 m²)

C.

Houseboat

D.

Mobile home

Buy Now
Questions 33

What is the first step to earn the Water Efficiency Credit, Cooling Tower Water Use?

Options:

A.

Select air-conditioner condensate for cooling

B.

Calculate cycles of concentration

C.

Identify the maximum number of cycles for the cooling tower or evaporative condenser

D.

Engage a water treatment professional to perform a chemical analysis

Buy Now
Questions 34

Which of the following strategies is allowed under Energy Atmosphere Credit, Renewable Energy Production, and will help a project achieve Energy Atmosphere Credit, Optimize Energy Performance?

Options:

A.

Install an on-site photovoltaic array

B.

Purchase Green-e certified carbon offsets

C.

Purchase Green-e certified Renewable Energy Certificates (RECs)

D.

Install a ground-source heat pump

Buy Now
Questions 35

Which of the following credit categories identifies environmental issues that are most relevant for a project ' s chapter area or country?

Options:

A.

Location and Transportation

B.

Energy and Atmosphere

C.

Sustainable Sites

D.

Regional Priority

Buy Now
Questions 36

A project has total waste of 20 tons (18.1 tonnes) that includes the following:

· 8 tons (7.3 tonnes) of recycled demolition steel and concrete

· 2 tons (1.8 tonnes) of trees cleared from the site

. 3 tons (2.7 tonnes) of commingled scrap with 40% diverted

. 6 tons (5.4 tonnes) of used furniture donated to a non-profit organization

· 1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the manufacturer

What is the percentage of diverted waste for Materials and Resources Credit, Construction and Demolition Waste

Management?

Options:

A.

60%

B.

75%

C.

90%

D.

100%

Buy Now
Questions 37

The use of lead, mercury, copper and cadmium should be limited because they all

Options:

A.

are persistent bioaccumulative toxins

B.

reduce the life cycle assessment of a building

C.

take an unreasonable amount of energy to recycle

D.

interfere with the magnetic instruments in a medical building

Buy Now
Questions 38

A project ' s installed water fixtures do not exceed WaterSense maximum levels. Which compliance path should the LEED AP select under Water Efficiency Prerequisite, Indoor Water Use Reduction, and what type of documentation is required to demonstrate compliance with this path?

Options:

A.

Compliance Path 2: Usage-Based Calculation; prescriptive compliance confirmation

B.

Compliance Path 2: Usage-Based Calculation; appliance water calculations

C.

Compliance Path 1: Prescriptive Achievement; indoor water use calculations

D.

Compliance Path 1: Prescriptive Achievement; product cutsheets

Buy Now
Questions 39

During a design charrette, community neighbors raise a concern about potential glare resulting from a project ' s highly reflective roof. Which option should the LEED AP recommend to best address these concerns?

Options:

A.

Install a vegetative roofing system

B.

Change the design to reduce the amount of roofing area

C.

Change the roofing material to a dark material to eliminate the issue

D.

Increase the parapet height

Buy Now
Questions 40

Which of the following is a source reduction strategy to eliminate waste produced by a project?

Options:

A.

Custom design

B.

Design-build

C.

Material science

D.

Prefabrication

Buy Now
Questions 41

Which of the following criteria does a project need to implement in order to qualify for Sustainable Sites Credit: Site Development - Protect or Restore Habitat, Option 1?

Options:

A.

Use of natural plants rated for their effect in reducing the heat island effect, while also restoring a minimum of 20% (including the building footprint) of all portions of the site identified as previously disturbed

B.

Use of only native or adapted vegetation, along with not restoring a minimum of 36% (including the building footprint) of all portions of the site identified as previously disturbed

C.

Use of native or adapted vegetation, restoring a minimum of 30% (including the building footprint) of all portions of the site identified as previously disturbed

D.

Use of natural vegetation and not artificial greenery, restoring a minimum of 25% (including the building footprint) of all portions of the site identified as previously disturbed

Buy Now
Questions 42

In pursuit of the Materials and Resources Credit, Building Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices, which of the following statements is true related to products purchased for temporary use (formwork, bracing and scaffolding) on the project?

Options:

A.

Temporary wood products cannot be included in the calculations

B.

If any temporary wood materials are included in the calculation, all wood materials must be included in the calculation

C.

Only Forest Stewardship Council (FSC)-certified wood materials are included in the calculation; non-certified wood materials contribute to other credits

D.

FSC-certified wood materials purchased for more than one project can be applied to other projects seeking LEED Certification

Buy Now
Questions 43

Which of the following features is commonly included in a building’s leak-detection system to enhance water efficiency?

Options:

A.

Real-time monitoring and alerts

B.

Water-use prediction algorithms based on weather data

C.

Monthly water-use analysis reports

Buy Now
Questions 44

An owner has requested that the project team redesign a large office building. As part of the redesign, the owner would like to move the main entrance to the opposite side of the building. Achievement of which credit may be affected by the move?

Options:

A.

Location and Transportation Credit, High-Priority Site

B.

Location and Transportation Credit, Sensitive Land Protection

C.

Location and Transportation Credit, Surrounding Density and Diverse Uses

D.

Location and Transportation Credit, LEED for Neighborhood Development Location

Buy Now
Questions 45

What is the sequence of the process for LEED certification?

Options:

A.

Submit documentation through LEED Online, Choose Rating System, Review, Register, Certify

B.

Submit documentation through LEED Online, Choose Rating System, Register, Review, Certify

C.

Choose Rating System, Register, Submit documentation through LEED Online, Review, Certify

D.

Choose Rating System, Register, Submit documentation through LEED Online, Certify, Review

Buy Now
Questions 46

Which of the following is an example of a nonroof measure for Sustainable Sites Credit, Heat Island Reduction?

Options:

A.

A playground with artificial turf

B.

A vegetated shading structure

C.

A shade structure with a three-year aged Solar Reflectance Index (SRI) value of 0.2

D.

A paving material with a three-year aged SRI value of 0.2

Buy Now
Questions 47

The gross floor area of a LEED project should be no less than what percent of the gross land area within the LEED project boundary?

Options:

A.

3%

B.

1%

C.

2%

D.

4%

Buy Now
Questions 48

Which of the following criteria must a Commissioning Authority (CxA) comply with in order to meet the requirements of the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification of Building Energy Systems?

Options:

A.

Document commissioning authority experience for at least one building project

B.

Review the owner ' s project requirements (OPR) for project goals and expectations

C.

Be a part of the project ' s design and construction management team

D.

Report results, findings, and recommendations directly to the architect

Buy Now
Questions 49

Which of the following strategies can be used to reduce the internal load of a building?

Options:

A.

Decreasing lighting power

B.

Oversize the HVAC systems

C.

Install low reflective exterior facade

D.

Increase the insulating value of the glazing and window frame system

Buy Now
Questions 50

A project team member has prepared a map and accompanying table as documentation for the Location and Transportation Credit. Surrounding Density and Diverse Uses. Option 2. Diverse Uses. The map includes the location of each diverse use. the location of the project and the main entrance of the building. The table includes the distance to each use. the name of each use and the category of each use The team lead reviews the documentation and notes an important missing item. Which of the following is the most important item to add to the documentation?

Options:

A.

A description of each use

B.

The location of parking lots near each use

C.

Walking routes from the project to each use

D.

A calculation of the expected number of project occupants who will visit each use

Buy Now
Questions 51

Qualifying spaces for the Sustainable Sites Credit, Places of Respite must

Options:

A.

be located outdoors near a water feature

B.

be located at least 20 ft. (6 m) from a smoking area

C.

have provisions for direct medical care to be delivered in the area

D.

have options for shade or indirect sun for a portion of seating spaces

Buy Now
Questions 52

Which of the following strategies is essential for a project to comply with EQc2: Occupant Experience, Option 1. Biophilic Environment?

Options:

A.

Incorporate the five principles adapted fromThe Practice of Biophilic Design

B.

Encourage positive interactions between people and nature

C.

Select only the most relevant principles adapted fromThe Practice of Biophilic Design

Buy Now
Questions 53

A corporate office pursuing LEED BD+C has two functional entries serving different transit stops.

• Entry 1: Bus Stop A (380 m, 52 daily trips), Light Rail Stop B (720 m, 84 daily trips)

• Entry 2: Bus Stop C (420 m, 48 daily trips), BRT Stop D (760 m, 210 daily trips)

How many points can the project earn for LTc3: Compact and Connected Development, considering distance requirements and diversity bonus eligibility?

Options:

A.

5

B.

4

C.

3

Buy Now
Questions 54

The material cost for a project is $100,000. What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction

Practices?

Options:

A.

$10,000

B.

$12,500

C.

$22,500

D.

$25,000

Buy Now
Questions 55

An accessible garden planted with native plants contributes to the achievement of which of the following credit pairs?

Options:

A.

Sustainable Sites Credit, Sensitive Land Protection; Sustainable Sites Credit, Site Development - Protect or Restore Habitat

B.

Sustainable Sites Credit, Open Space; Sustainable Sites Credit, Rainwater Management

C.

Water Efficiency Credit, Water Metering; Sustainable Sites Credit, Tenant Design and Construction Guidelines

D.

Location and Transportation Credit, Surrounding Density and Diverse Uses; Sustainable Sites Credit, Site Assessment

Buy Now
Questions 56

A Core and Shell developer pursuing the IPc2 Green Leases credit has drafted lease language. Which provision meets the intent of the credit for binding tenant sustainability commitments?

Options:

A.

Tenant shall submit quarterly energy and water consumption reports and achieve a minimum 50% waste diversion rate verified through waste hauler documentation.

B.

Owner will provide tenant with LEED design guidelines and green building best-practices handbook within 30 days of lease execution for reference.

C.

Tenant acknowledges that the building has achieved LEED certification and agrees to maintain awareness of sustainable building operations during occupancy.

Buy Now
Questions 57

If a commercial building is considered to have 100 peak visitors in a day, what is the minimum number of short-term

bicycle storage spaces that must be provided to earn one point under Location and Transportation Credit, Bicycle

Facilities?

Options:

A.

Three

B.

Four

C.

Five

D.

Ten

Buy Now
Questions 58

A design team is evaluating strategies to ensure that a healthcare facility remains operational for critical services during frequent power outages. The building currently relies on a diesel generator for emergency power, but the owner is interested in sustainable alternatives that can also contribute to the project’s energy efficiency during normal operations.

Which of the following strategies should the design team recommend to provide energy resilience for the healthcare facility while enhancing energy efficiency during regular operations?

Options:

A.

Install a new natural-gas generator as the primary source of backup power

B.

Implement solar photovoltaic panels with a battery energy-storage system

C.

Increase the capacity of the existing diesel generator

Buy Now
Questions 59

Which rating system is being used if all of the credits below have been submitted towards certification?

- Location and Transportation Credit, Reduced Parking Footprint

- Energy and Atmosphere Credit, Fundamental Refrigerant Management

- Indoor Environmental Quality Credit, Acoustic Performance

- Materials and Resources Credit, Persistent, Bio accumulative, and Toxic (PBT) Source Reduction - Lead, Cadmium, and Copper

Options:

A.

Building Design and Construction: Schools

B.

Building Design and Construction: Healthcare

C.

Building Design and Construction: Hospitality

D.

Building Design and Construction: Data Centers

Buy Now
Questions 60

During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?

Options:

A.

Innovation Credit, Innovation

B.

Integrative Process Credit

C.

Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control

D.

Materials and Resources Credit, Interiors Life-Cycle Impact Reduction

Buy Now
Questions 61

A design team working on a new building in a coastal city is considering climate resilience strategies. The team refers to the Intergovernmental Panel on Climate Change (IPCC) Sixth Assessment Report to incorporate different emissions scenarios on projected climate changes.

The design team can use emissions scenarios to enhance the climate resilience of their building project by utilizing the:

Options:

A.

Scenarios consistent with current global policies and historical emissions trends

B.

Mid-range scenarios, as they are most likely to occur

C.

Scenarios appropriate for the geographic location of the project that take into account local climate action plans

Buy Now
Questions 62

Selecting a high-reflectance interior paint which is compliant with South Coast Air Quality Management District (SCAQMD) Rule 1113 can help contribute towards which two credits?

Options:

A.

Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Interior Lighting

B.

Indoor Environmental Quality Credit, Low-Emitting Materials and Sustainable Sites Credit, Site Assessment

C.

Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Minimum Indoor Environmental Quality Performance

D.

Indoor Environmental Quality Credit, Enhanced Indoor Environmental Quality Strategies and Indoor Environmental Quality Prerequisite, Minimum Indoor Environmental Quality Performance

Buy Now
Questions 63

Operable windows contribute to resilient planning and design in extreme climate conditions by:

Options:

A.

Increasing the thermal mass of the building for heat retention

B.

Allowing natural ventilation to improve indoor air quality

C.

Facilitating seasonal thermal adaptation for occupants

Buy Now
Questions 64

Which of the following is the location of CO2 sensors in naturally ventilated spaces to comply with the Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

Options:

A.

At least 6 ft. (2 m) above the floor

B.

At least 3 ft. (1 m) away from windows

C.

Between 3 ft. and 6 ft. (1 m and 2 m) above the floor

D.

On the ceiling 3 ft. (1 m) away from adjacent walls

Buy Now
Questions 65

A new facility has a comprehensive advanced energy metering system that measures energy consumption across multiple subsystems. The facilities manager aims to use this data to enhance energy management practices and improve overall building performance.

The facilities manager can utilize the advanced energy metering system to optimize energy use and reduce costs in the new student center by:

Options:

A.

Adjusting the setpoints of the HVAC system based solely on outdoor temperature changes

B.

Using automated alerts from the metering system to address sudden spikes in energy use

C.

Scheduling regular audits for all installed lighting systems to ensure compatibility with energy meters

Buy Now
Questions 66

Which of the following water management practices can be applied to identify and address hidden leaks in the water system of a commercial building?

Options:

A.

Implement a comprehensive reporting system for water usage

B.

Set up a separate meter for each floor of the building

C.

Install an advanced system with sensors throughout the plumbing network

Buy Now
Questions 67

A topographic assessment of a project site located 150 ft. (45 m) from a water body was conducted. The results of the slope analysis show that the site is generally sloping 6% to 8% to the northwest over most of the site, with some steep slopes located at the eastern edge of the property, which may impact the runoff volume. Which one of the following LEED credits or prerequisites will be affected by these results?

Options:

A.

Sustainable Sites Credit, Rainwater Management

B.

Sustainable Sites Prerequisite, Environmental Site Assessment

C.

Location and Transportation Credit, Sensitive Land Protection

D.

Location and Transportation Credit, High-Priority Site

Buy Now
Questions 68

Which of the following products are eligible for a WaterSense label?

Options:

A.

Tankless toilets

B.

Waterless urinals

C.

Public lavatory faucets

D.

Private lavatory faucets

Buy Now
Questions 69

Innovation credits for exemplary performance can be awarded for

Options:

A.

achieving one pilot credit

B.

achieving double the credit requirements

C.

demonstrating significant environmental benefits

D.

demonstrating a qualitative improvement in environmental performance

Buy Now
Questions 70

When should a preliminary water budget analysis be conducted?

Options:

A.

At the time the design development is completed

B.

At the time the plumbing contractor is selected

C.

After completion of schematic design

D.

Before completion of schematic design

Buy Now
Questions 71

Green Infrastructure (GI) and Low-Impact Development (LID) rainwater management strategies improve upon the conventional approach for rainwater management by

Options:

A.

replicating a site ' s natural hydrology

B.

discharging rainwater at a faster rate

C.

increasing a site ' s impervious surface

D.

providing a greater volume of rainwater detention

Buy Now
Questions 72

A project team seeking certification for a new school is attempting to achieve Materials and Resources Credit, Construction and Demolition Waste Management, Option 2. Reduction of Total Waste Material. What strategy can be taken to meet the requirements of this credit?

Options:

A.

Track waste materials per occupant

B.

Track waste materials used on site

C.

Document total waste by project cost

D.

Document total waste per building floor area

Buy Now
Questions 73

What percentile of runoff from a regional development of an office building must a project manage on site by using low-impact development and green infrastructure to achieve three points under the Sustainable Sites Credit-Rainwater Management, Option 1. Percentile of Rainfall Events?

Options:

A.

98th percentile

B.

85th percentile

C.

95th percentile

D.

100th percentile

Buy Now
Questions 74

A coastal mixed-use development pursuing LEED BD+C certification is evaluating flood-resilience strategies to protect against sea-level rise. Which of the following strategies most comprehensively addresses flood resilience for IPp1: Climate Resilience Assessment?

Options:

A.

Elevate all critical mechanical, electrical, and plumbing systems above the 500-year flood elevation and design ground-floor spaces with flood-tolerant materials, drainage infrastructure, and resilient finishes

B.

Design foundation walls with reinforced concrete, waterproof membranes, and active dewatering pumps to keep below-grade spaces dry and functional during flooding

C.

Specify native flood-tolerant vegetation with bioswales and rain gardens throughout the site to absorb stormwater runoff and reduce peak flow rates

Buy Now
Questions 75

A project elects to pursue Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 2. Diverse Uses because of the project ' s location in an amenity-rich area. The project features 18 uses overall, including at least four uses in three of the five use type categories. What threshold must the project surpass in order to demonstrate exemplary performance for Option 2?

Options:

A.

Exemplary Performance is not available for Option 2

B.

15 uses, including two uses in each of the five categories

C.

15 uses, including at least one Food Retail and one Community Anchor use

D.

18 uses, including uses in at least four of the five use type categories

Buy Now
Questions 76

In the context of Core and Shell projects, which of the following strategies effectively aligns tenant spaces with LEED goals for sustainability?

Options:

A.

Mandating quarterly indoor air quality assessments for tenant areas

B.

Implementing a shared lighting control system throughout the entire building

C.

Developing comprehensive tenant guidelines outlining sustainable practices

Buy Now
Questions 77

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following must be included in the Basis of Design (BOD)?

Options:

A.

Training requirements

B.

Allowable tolerance for facility operations

C.

Facility, system and assembly performance assumptions

D.

Environmental, energy efficiency and sustainability goals

Buy Now
Questions 78

A corporate office building is implementing a comprehensive waste management program aimed at achieving zero-waste operations. The building management is evaluating strategies to efficiently manage recyclables, compost organics on-site, and safely store hazardous materials such as batteries and mercury-containing lamps. Which of the following actions should the building management take to further improve the waste management program?

Options:

A.

Implement educational workshops on waste sorting and recycling

B.

Mandate individual desk-side recycling bins at all workstations

C.

Centralize waste collection areas to encourage recycling behavior

Buy Now
Questions 79

Which principal areas must the LEED AP focus on to attain the Integrative Process Credit, Integrative Process?

Options:

A.

Materials and resources

B.

Location and site selection

C.

Regional priority and innovation

D.

Energy and water related systems

Buy Now
Questions 80

During the early design phase of a new commercial office building, what action should the project team take to reduce the Global Warming Potential (GWP) of refrigerants?

Options:

A.

Select an HVAC system that uses refrigerants with a GWP of 700 or less

B.

Delay addressing refrigerant concerns until the commissioning phase, when system performance can be evaluated

C.

Specify any HVAC system and offset refrigerant emissions through carbon credits later, if needed

Buy Now
Questions 81

Which of the following products must always be included in Materials and Resources credits?

Options:

A.

Faucets

B.

Furniture

C.

Interior Paint

D.

Fire suppression system

Buy Now
Questions 82

When following the LEED Building Design and Construction Integrative Process credit, which of the following is the approach for the design team to follow?

Options:

A.

Locate a solid waste provider that has sorting capabilities

B.

Assure the aesthetics will match existing neighborhood conditions

C.

Identify synergies among building systems and equipment

D.

Determine if green vehicles will be applicable to the project

Buy Now
Questions 83

Which of the following is a leadership extraction practice that rewards projects for choosing materials with closed-loop recycling and take-back programs in LEED?

Options:

A.

Material reuse

B.

Bio-based elements

C.

Extended producer responsibility

D.

Forest Stewardship Council (FSC) wood products

Buy Now
Questions 84

A hospital certified underLEED V5in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.

The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.

The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.

The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.

The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.

The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.

The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.

Which LEED v5 rating system is appropriate for this project?

Options:

A.

LEED for New Construction and Major Renovations

B.

LEED for Commercial Interiors

C.

LEED for Healthcare

Buy Now
Questions 85

LEED project boundaries that include multiple similar buildings which are all eligible for certification can be registered as which of the following?

Options:

A.

Batch project

B.

Group project

C.

Master Site project

D.

Neighborhood project

Buy Now
Questions 86

A project team is providing additional ventilation under Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies. What credit could this adversely affect?

Options:

A.

Energy and Enhanced Commissioning

B.

Indoor Environmental Quality, Thermal Comfort

C.

Energy and Atmosphere, Optimize Energy Performance

D.

Indoor Environmental Quality, Interior Lighting

Buy Now
Questions 87

For Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan, which of the following

items is required for credit compliance?

Options:

A.

MERV 13 (F7) filtration media

B.

Indoor Environmental Quality test results

C.

Photographic documentation

D.

Separating construction waste

Buy Now
Questions 88

Commissioning (Cx) and verification are requirements to qualify for LEED certification. What are the basic systems that need to be commissioned?

Options:

A.

Electrical, Mechanical, Plumbing, and Renewable Energy

B.

Electrical, Structural, Mechanical, and Lighting

C.

Electrical, Structural, Audio Visual, and Envelope

D.

Electrical, Plumbing, Telecommunications, and Fire Suppression

Buy Now
Questions 89

A project team is using the whole building simulation model to quantify the percentage of energy savings for the project. Which of the following should remain the same for both the baseline building and the proposed building?

Options:

A.

Building operating schedule and occupancy hours

B.

Building operating schedule and total window area

C.

Building envelope construction and occupancy hours

D.

Total window area and building envelope construction

Buy Now
Questions 90

In an area where carbon-emission regulations are becoming progressively stricter, the goal is to future-proof the building for complete electrification and eliminate on-site fossil-fuel combustion. Which of the following measures can the project team use to maximize the building’s readiness for electrification while minimizing on-site combustion sources?

Options:

A.

Install natural-gas boilers as a backup heating source

B.

Plan for an electric heat-pump water-heating system

C.

Integrate rooftop solar panels to generate renewable electricity on-site

Buy Now
Questions 91

Which individual occupant lighting control meets the requirements of Indoor Environmental Quality Credit, Interior Lighting?

Options:

A.

Two Level (on, off)

B.

Three Level (on, 25%, off)

C.

Three Level (on, 50%, off)

D.

Three Level (on, 75%, off)

Buy Now
Questions 92

Which of the following statements is correct when defining the project boundary?

Options:

A.

The LEED project boundary cannot include non-contiguous land

B.

The LEED project boundary cannot include more than one building

C.

The land associated with the project supports typical operation

D.

The gross floor area of the LEED project should be no less than 1% of the gross land area within the LEED project boundary

Buy Now
Questions 93

A real estate development company plans to build a mixed-use facility in an urban area. Which of the following strategies should the developer implement to support the local economy?

Options:

A.

Provide location-efficient affordable housing

B.

Provide workforce training

C.

Employ individuals from the local community

Buy Now
Questions 94

During the early stages of a LEED project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected a paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?

Options:

A.

IPc1: Integrative Design Process

B.

PRc1: Project Priorities

C.

EQc2: Occupant Experience

D.

MRc5: Construction and Demolition Waste Diversion

Buy Now
Questions 95

A building owner is considering the installation of a solar thermal panel on the roof of the building. The initial cost of the system is higher than a conventional natural gas system. Which of the following is true to make the renewable energy option economically feasible?

Options:

A.

Utility cost savings over the lifetime of the system must offset the higher initial cost

B.

Higher initial cost must exceed the cost of the utility over the lifetime of the system

C.

Higher initial cost must exceed the savings on the utility cost over the lifetime of the system

D.

Utility cost savings over the lifetime of the system must be lower than the higher initial cost of the system

Buy Now
Questions 96

Which system is eligible for EAc4: Renewable Energy?

Options:

A.

Tidal energy conversion

B.

Municipal solid waste combustion

C.

Ground-source heat pumps

D.

Passive solar and daylighting strategies

Buy Now
Questions 97

Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to exclude what type of land area from the calculations?

Options:

A.

Buildable land within 1/4 mi. (0.40 km) of the project boundary

B.

Public right-of-way areas within 1/4 mi. (0.40 km) of the project boundary

C.

Surface parking areas within 1/2 mi. (0.80 km) of the project boundary

D.

University campus land areas within 1/2 mi. (0.80 km) of the project boundary

Buy Now
Questions 98

The LEED AP is leading the first design charrette for a new LEED project with the project ' s owners. What document should be used to record the project goals to be used throughout the design of the project?

Options:

A.

Owner ' s Project Requirements (OPR)

B.

Owner ' s list of wants and needs

C.

Criteria for contractor selection

D.

Basis of Design (BOD)

Buy Now
Questions 99

What issue must be present on the project site to achieve Location and Transportation Credit, High-Priority Site, Option 3. Brownfield Remediation?

Options:

A.

Mercury containing lamps

B.

Contaminated soil or groundwater

C.

Asphalt construction waste

D.

Asbestos tile and glue

Buy Now
Questions 100

Which of the following could be considered diverted construction waste?

Options:

A.

Excavated soil

B.

Land-clearing debris

C.

Alternative daily cover

D.

Asphalt with aggregate

Buy Now
Questions 101

A contractor is building a retirement community project. 30% of the building ' s product costs were derived from reused/salvaged materials or met recycled content criteria. Which of the following credits can the LEED AP submit towards certification?

Options:

A.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials

B.

Materials and Resources Prerequisite, Construction and Demolition - Waste Management Planning

C.

Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients

D.

Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations

Buy Now
Questions 102

Which of the following is true regarding LEED Pilot Credits?

Options:

A.

Pilot Credits are not specific to the rating systems

B.

Pilot Credits can be attempted in the design review stage only

C.

A registered Pilot Credit must be replaced on the LEED project ' s scorecard if that pilot credit is removed from the Pilot Credit Library

D.

Pilot Credit feedback surveys must be completed

Buy Now
Questions 103

U.S. Green Building Council (USGBC) ' s vision for using LEED internationally includes

Options:

A.

allowing more stringent credit requirements for countries outside of the U.S. so that all projects can achieve LEED

B.

creating multiple LEED rating systems for different countries

C.

modifying U.S. reference standards, such as ASHRAE 90.1, to be more appropriate for regions outside the U.S.

D.

providing opportunities for alternative compliance paths that meet the unique needs of a particular region

Buy Now
Questions 104

What is the best strategy for a LEED AP to suggest in order to quantify the impact of increasing the window-to-wall ratio on a Building Design and Construction project?

Options:

A.

Compare the current project to other similar projects

B.

Monitor the HVAC loads throughout the life of the project

C.

Perform a simple box energy model before the completion of the schematic phase

D.

Review Green Business Certification Inc. (GBCI) ' s comments on the energy model submission

Buy Now
Questions 105

What requirement must be met when creating a Demand Response Program that satisfies Energy and Atmosphere Credit, Demand Response?

Options:

A.

Permanently reduce the energy consumption in the building by 5%

B.

Demonstrate submetering of the two highest electrical end uses

C.

Demonstrate a load shift reduction of 5% in the building

D.

Create a comprehensive plan for meeting a demand response event

Buy Now
Questions 106

Which of the following strategies under LTc2: Equitable Development, Option 3: Equitable Construction helps achieve the goal of enhancing the economic and social vitality of a community?

Options:

A.

Providing job-related skills training through a registered apprenticeship program

B.

Establishing affordable housing units within the project

C.

Engaging local business owners in the project design process

Buy Now
Questions 107

What is the basis of energy consumption in determining the percentage of green power or carbon offsets?

Options:

A.

Quality

B.

Quantity

C.

Efficiency

D.

Performance

Buy Now
Questions 108

A commercial new construction project consists of mixed space usage. When deciding which LEED rating system to use, the LEED AP should follow which of the following rules?

Options:

A.

If a rating system is appropriate for less than 50% of the gross area of the LEED project space then the rating system must not be used

B.

If a rating system is appropriate for more than 50% of the gross floor area of LEED project space, then that rating system must be used

C.

If a rating system is appropriate for 30% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

D.

If a rating system is appropriate for 40% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

Buy Now
Questions 109

Which of the following methods is the referenced standard for demonstrating compliance with Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

Options:

A.

ASHRAE 62.2 - 2007

B.

ASHRAE 90.1 - 2010

C.

ASHRAE 55 - 2010

D.

ASHRAE 62.1 - 2010

Buy Now
Questions 110

What stage of LEED for Neighborhood Development certification listed below is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location?

Options:

A.

LEED V5, LEED for Neighborhood Development Conditional Approval

B.

LEED for Neighborhood Development Pilot, Stage 3 LEED for Neighborhood Development Certified Project

C.

LEED for Neighborhood Development Pilot, Stage 1 LEED for Neighborhood Development Pre-reviewed Plan

D.

LEED 2009, Stage 1 Conditional Approval of LEED for Neighborhood Development Plan

Buy Now
Questions 111

Which of the following scenarios contributes to earning credit under MRc1: Materials and Resources, Option 2. Materials Reuse?

Options:

A.

Donate salvaged wood to a local nonprofit organisation that repurposes materials

B.

Reuse salvaged metal beams in the construction of the new project

C.

Sell recovered bricks to a salvage retailer for off-site reuse

Buy Now
Questions 112

Which of the following standards is used to perform a Whole-Building Life-Cycle Assessment to measure the Global Warming Potential of materials in LEED projects?

Options:

A.

ISO 50001:2018

B.

ISO 14044:2006

C.

ISO 21930:2017

Buy Now
Questions 113

During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the contractor substituted a higher efficiency piece of equipment. Which of the following is the priority for the CxA to consider?

Options:

A.

Energy meter location

B.

Equipment Maintenance Plan

C.

Owner ' s Project Requirements

D.

Coordination of other contractors

Buy Now
Questions 114

Which of the following credits can be awarded an Innovation point for Exemplary Performance?

Options:

A.

Indoor Environmental Quality Credit, Daylight

B.

Indoor Environmental Quality Credit, Low-Emitting Materials

C.

Indoor Environmental Quality Credit, Minimum Indoor Air Quality Performance

D.

Indoor Environmental Quality Credit, Acoustic Performance

Buy Now
Questions 115

A new athletic facility contains a laundry room which is adjacent to the locker rooms. Which strategy will contribute toward the Interior Cross-Contamination Prevention strategy in Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies?

Options:

A.

Relocate the laundry facility to the basement

B.

Naturally ventilate the laundry space per ASHRAE 62.1-2010

C.

Install particle filters, with a MERV of 13 or higher or F7

D.

Provide a ventilation system specifically for the laundry facility that has no recirculating air

Buy Now
Questions 116

How much value would these two doors contribute toward Material and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?

Options:

A.

$150.00

B.

$50.00

C.

$100.00

D.

$125.00

Buy Now
Questions 117

A new Science Education Center is pursuing LEED certification. Which of the following strategies could be submitted to earn an Innovation in Design credit?

Options:

A.

The selection of energy-efficient LED fixtures for all of the building ' s lighting

B.

The installation of an air-purifying facade material on the front entrance of the building

C.

The integration of rainwater management strategies to achieve a Regional Priority Credit

D.

The implementation of a comprehensive metering strategy to measure three individual energy end uses

Buy Now
Questions 118

The project team has decided to substitute the flooring in the school gym with natural rubber flooring that has met the Sustainable Agriculture Standard. The cost of the substituted flooring is $80,000. The project will achieve

Options:

A.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials,Option 2. Leadership Extraction Practices

B.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials,Option 1. Raw Material Source and Extraction Reporting

C.

Materials and Resources Credit, Building Product Disclosure and Optimization Environmental ProductDeclarations, Option 1. Environmental Product Declarations

D.

Materials and Resources Credit, Construction and Demolition Waste Management, Option 1. Diversion

Buy Now
Questions 119

Which of the following Sustainable Sites credits are eligible to be used as a campus approach?

Options:

A.

Light Pollution Reduction, Places of Respite, Open Space

B.

Heat Island Reduction, Places of Respite, Site Master Plan

C.

Direct Exterior Access, Heat Island Reduction, Rainwater Management

D.

Heat Island Reduction, Light Pollution Reduction, Rainwater Management

Buy Now
Questions 120

The project team wants to modify the design of an office building copy room to minimize the risk of airborne contamination to the surrounding space. The design includes a separate exhaust, but due to design constraints the partition walls of the room cannot run deck-to-deck. What can the team do to achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies?

Options:

A.

Use MERV 8 (F5), or higher, filters

B.

Provide a hard-lid ceiling

C.

Create positive pressure in the room

D.

Provide a large opening to dilute air contaminates

Buy Now
Questions 121

A project team reviews office chairs with a Type III environmental product declaration (EPD) for the five different categories of environmental impact reduction. Which of the following must the chairs demonstrate for product optimization?

Options:

A.

A reduction in at least two categories

B.

A reduction below the industry average in at least three categories

C.

A 5% reduction in all categories

D.

A 10% reduction in GHG emissions and a 10% reduction in at least two other categories

Buy Now
Questions 122

Which of the following actions should be taken to ensure that project team members understand and prioritize the selection of materials compliant with the Materials and Resources Credit: Building Product Disclosure and Optimization?

Options:

A.

Select locally sourced and manufactured materials

B.

Procure materials directly from raw material suppliers

C.

Include all building materials in a whole-building life-cycle analysis

D.

Include the material requirements in the project specifications

Buy Now
Questions 123

A tenant of a new office building will require 100 workstations per floor. Each floor will have two bathroom facilities and one conference room. How many lighting control devices with at least three lighting levels per floor are required to comply with Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control?

Options:

A.

91 lighting control devices

B.

93 lighting control devices

C.

100 lighting control devices

D.

103 lighting control devices

Buy Now
Questions 124

Which of the following statements are true for Erosion and Sedimentation Control (ESC) plan prerequisite compliance?

Options:

A.

The ESC plan cannot be modified during the design phase of the LEED certification

B.

The ESC plan can be developed or modified during the design phase of LEED certification

C.

A compliant ESC plan may be developed during construction

D.

A compliant ESC plan must be in place when the commissioning authority is appointed

Buy Now
Questions 125

A project team is planning a new office building in a cold climate. The team aims to achieve significant reductions in peak thermal loads. Which strategy should it apply to minimise peak thermal loads associated with infiltration?

Options:

A.

Increase wall-insulation thickness

B.

Install high-performance windows with low-emissivity coatings

C.

Seal potential air-leakage points and openings

Buy Now
Questions 126

Which of these is a method to assess the regional context of a building ' s design for sustainability?

Options:

A.

Conducting a site analysis

B.

Consulting with neighbors

C.

Improving a design threshold

D.

Performing an energy analysis of the building

Buy Now
Questions 127

Which of the following standards is used to perform a Whole-Building Life-Cycle Assessment (LCA) to measure the Global Warming Potential (GWP) of materials in LEED projects?

Options:

A.

ISO 21930:2017

B.

ISO 50001:2018

C.

ISO 14044:2006

Buy Now
Questions 128

A project pursuing LEED BD+C certification is designed with an electric air-source heat pump as the primary heating system to meet EAp1: Operational Carbon Projection and Decarbonization Plan. However, the client is considering adding a small natural-gas boiler for backup heating during extreme weather.

To earn maximum points under EAp1 while maintaining heating-system reliability, what should the LEED AP recommend regarding supplemental heating?

Options:

A.

Design an all-electric supplemental heating system using electric-resistance elements or auxiliary heat-pump capacity to eliminate on-site fossil-fuel combustion

B.

Install a natural-gas boiler with automated controls that limit operation to extreme conditions and include provisions for future conversion to an all-electric system

C.

Implement a wood-pellet biomass boiler as secondary heating because it qualifies as carbon-neutral without penalizing on-site combustion

Buy Now
Questions 129

In new construction projects, EQc4: Resilient Spaces allows designs to earn points from which of the following management modes?

Options:

A.

Seismic risks

B.

Hurricane and tornado risks

C.

Infection risks

Buy Now
Questions 130

The Required Breathing Zone Outdoor Airflow Vbz for a new banking facility is 0.120 CFM/ft2 (0.6 L/s/m2). If the team decides to attempt Increased Ventilation under Option 2 in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies, what is the minimum Design Zone Outdoor Airflow?

Options:

A.

0.144 CFM/ft2 (0.73 (L/s)/m2)

B.

0.156 CFM/ft2 (0.79 (L/s)/m2)

C.

0.168 CFM/ft2 (0.85 (L/s)/m2)

D.

0.30 CFM/ft2 (1.5 (L/s)/m2)

Buy Now
Questions 131

What are the three phases within the Integrative Process Credit, Integrative Process?

Options:

A.

Pre-design, Discovery, Design and Construction

B.

Discovery, Design and Construction, Operations and Feedback

C.

Schematic Design, Design and Construction, Operations and Feedback

D.

Design Charrette, Schematic Design, Operations and Feedback

Buy Now
Questions 132

What is the reference standard that defines the requirements for LEED energy modeling?

Options:

A.

ASHRAE 62.1-2010

B.

Core Performance Guide

C.

ASHRAE Advanced Energy Design Guide

D.

ASHRAE 90.1-2010 Appendix G

Buy Now
Questions 133

Which of the following project types is required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations?

Options:

A.

Retail

B.

Schools

C.

Healthcare

D.

Core and Shell

Buy Now
Questions 134

A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?

Options:

A.

Revise the documentation and resubmit the form

B.

Abandon meeting this prerequisite

C.

Submit an appeal to Green Business Certification Inc.

D.

Ask the General Contractor to be more aggressive with recycling goals

Buy Now
Questions 135

What LEED Building Design and Construction rating system mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit?

Options:

A.

Healthcare

B.

Schools

C.

Data centers

D.

Hospitality

Buy Now
Questions 136

Which of the following prerequisites or credits are affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit. Thermal Comfort?

Options:

A.

Energy and Atmosphere Credit. Demand Response

B.

Energy and Atmosphere Credit. Advanced Energy Metering

C.

Energy and Atmosphere Prerequisite. Minimum Energy Performance

D.

Energy and Atmosphere Prerequisite. Building Level Energy Metering

Buy Now
Exam Code: LEED-AP-BD+C
Exam Name: LEED AP Building Design + Construction (LEED v5 AP BD+C)
Last Update: Nov 19, 2026
Questions: 454

PDF + Testing Engine

$42.5  $169.99

Testing Engine

$32.5  $129.99
buy now LEED-AP-BD+C testing engine

PDF (Q&A)

$27.5  $109.99
buy now LEED-AP-BD+C pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 20 Nov 2026