Summer Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

LEED-AP-BD+C LEED AP Building Design + Construction (LEED AP BD+C) Questions and Answers

Questions 4

Which of the following is required for a cooling tower or evaporative condenser in Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

Alkalinity testing and ENERGY STAR® rating

B.

Non potable water sources and bacteria testing

C.

Water treatment calculations and system performance narrative

D.

Makeup water meters, conductivity controllers and overflow alarms

Buy Now
Questions 5

A critical factor in determining a project’s eligibility for LTc3: Compact and Connected Development, Option 2. Access to Transit, Path 1. Public Transit Service is the:

Options:

A.

Number of regularly scheduled weekend transit trips available

B.

Accessibility of safe sidewalks and pedestrian pathways

C.

Frequency of on-site shuttle services provided to the transit stop

Buy Now

LEED-AP-BD+C Report Card

Questions 6

A project's massing and site orientation can have a direct impact on which of the following prerequisites?

Options:

A.

Minimum Energy Performance

B.

Minimum Indoor Air Quality Performance

C.

Construction Activity Pollution Prevention

D.

Fundamental Commissioning and Verification

Buy Now
Questions 7

How much value would these two doors contribute toward Material and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?

Options:

A.

$150.00

B.

$50.00

C.

$100.00

D.

$125.00

Buy Now
Questions 8

During a review of the HVAC equipment submittal, the Commissioning Authority (CxA) determined that the contractor substituted a higher efficiency piece of equipment. Which of the following is the priority for the CxA to consider?

Options:

A.

Energy meter location

B.

Equipment Maintenance Plan

C.

Owner's Project Requirements

D.

Coordination of other contractors

Buy Now
Questions 9

An urban office building project is installing a cooling tower. To save on potable water, the project would like to use a nonpotable water source to provide 20% of the cooling tower makeup water to achieve the maximum number of points under Water Efficiency Credit, Cooling Tower Water Use. Which nonpotable water source would be the most appropriate for use?

Options:

A.

Municipally supplied tap water

B.

Ground surface stormwater runoff

C.

Rainwater collected from the building roof

D.

Graywater from the building's hand-washing sinks

Buy Now
Questions 10

Which of these is a method to assess the regional context of a building's design for sustainability?

Options:

A.

Conducting a site analysis

B.

Consulting with neighbors

C.

Improving a design threshold

D.

Performing an energy analysis of the building

Buy Now
Questions 11

Which of the following activities must be prohibited within a building as a prerequisite to LEED certification?

Options:

A.

Burning fossil fuels

B.

Smoking tobacco products

C.

Preparing non-organic foods

D.

Manufacturing toxic chemicals

Buy Now
Questions 12

What LEED Building Design and Construction rating system mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit?

Options:

A.

Healthcare

B.

Schools

C.

Data centers

D.

Hospitality

Buy Now
Questions 13

A design team pursuing LEED for a new office building project calculated that with the water fixtures specified for the project, a 24% water reduction can be achieved compared to the LEED baseline. What does this mean to the team in terms of pursuing LEED?

Options:

A.

The project cannot pursue LEED

B.

The project may pursue Water Efficiency Credit, Indoor Water Use Reduction

C.

The project does not meet Water Efficiency Prerequisite, Indoor Water Use Reduction, but can make up the points elsewhere in the rating system

D.

The project can meet the Water Efficiency Prerequisite, Indoor Water Use Reduction, but cannot earn any points under Water Efficiency Credit, Indoor Water Use Reduction

Buy Now
Questions 14

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, when should the Owner’s Project Requirements (OPR) be created and updated?

Options:

A.

Prior to beginning design and are generally not updated

B.

Once the project design is completed and edited throughout the project

C.

During predesign and are edited throughout the project

D.

After the design is completed and are generally not updated

Buy Now
Questions 15

Showers are addressed under which prerequisites and/or credits within LEED Building Design and Construction?

Options:

A.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Credit, Indoor Water Use Reduction; and Location and Transportation Credit, Bicycle Facilities

B.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Prerequisite, Outdoor Water Use Reduction; and Water Efficiency Credit, Water Metering

C.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Prerequisite, Outdoor Water Use Reduction; and Location and Transportation Credit, Bicycle Facilities

D.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Credit, Cooling Tower Water Use; and Water Efficiency Credit, Water Metering

Buy Now
Questions 16

For a project located on a greenfield site and attempting the Location and Transportation Credit, Sensitive Land Protection, Option 2, what must the development footprint avoid?

Options:

A.

Land that is within 200 ft. (61 m) of a local government wetland demonstration project

B.

Soils that are to be restored according to the SITES Guidelines and Performance Benchmarks 2009. Credit 7.3

C.

Areas not able to meet the criteria for Location and Transportation Credit LEED for Neighborhood Development Location

D.

Prime farmland as defined by the U.S. Code of Federal Regulations or local equivalent outside the US

Buy Now
Questions 17

In the Indoor Environmental Quality Credit, Low-Emitting Materials, what types of products need to be evaluated for

both Volatile Organic Compound (VOC) content of the material and VOC emissions of the material?

Options:

A.

Flooring

B.

Furniture

C.

Composite wood

D.

Wet applied products

Buy Now
Questions 18

Which of the following statements are true for Erosion and Sedimentation Control (ESC) plan prerequisite compliance?

Options:

A.

The ESC plan cannot be modified during the design phase of the LEED certification

B.

The ESC plan can be developed or modified during the design phase of LEED certification

C.

A compliant ESC plan may be developed during construction

D.

A compliant ESC plan must be in place when the commissioning authority is appointed

Buy Now
Questions 19

What is a common strategy to minimize thermal bridging in building design to reduce peak thermal loads?

Options:

A.

Incorporate continuous insulation throughout the building envelope

B.

Use heavier construction materials to delay heat transfer

C.

Install thicker wall assemblies with thermal breaks

Buy Now
Questions 20

Which of the following should be analyzed when pursuing an Integrative Design Process focusing on Energy-Related

Systems?

Options:

A.

Site conditions

B.

Potable water availability

C.

Acoustic performance of the project

D.

Applicability of Green Vehicles to the project

Buy Now
Questions 21

The owner of a large multi-building property is seeking LEED certification. In determining the LEED project boundaries the LEED AP may include non-contiguous parcels of land if

Options:

A.

the parcels are used for temporary uses such as parking or staging that is owned and managed by a third party

B.

the parcels directly support or are associated with normal building operations and are accessible to the project's occupants

C.

the parcels are part of an existing public preservation easement or resource protection area that is directly adjacent to the LEED project boundary

D.

the parcels are part of a land trust or conservation organization for which the LEED project provides financial support for in the Sustainable Sites Credit, Site Development Credit, Protect or Restore Habitat, Option 2. Financial Support

Buy Now
Questions 22

What is the system boundary that a building life cycle analysis must be defined to account for?

Options:

A.

Cradle-to-gate

B.

Cradle-to-grave

C.

Cradle-to-cradle

D.

Cradle-to-building

Buy Now
Questions 23

A project has total waste of 20 tons (18.1 tonnes) that includes the following:

· 8 tons (7.3 tonnes) of recycled demolition steel and concrete

· 2 tons (1.8 tonnes) of trees cleared from the site

. 3 tons (2.7 tonnes) of commingled scrap with 40% diverted

. 6 tons (5.4 tonnes) of used furniture donated to a non-profit organization

· 1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the manufacturer

What is the percentage of diverted waste for Materials and Resources Credit, Construction and Demolition Waste

Management?

Options:

A.

60%

B.

75%

C.

90%

D.

100%

Buy Now
Questions 24

Which of the following could be considered diverted construction waste?

Options:

A.

Excavated soil

B.

Land-clearing debris

C.

Alternative daily cover

D.

Asphalt with aggregate

Buy Now
Questions 25

Which of the following strategies reflects a synergy between EQc2: Occupant Experience, Option 5. Lighting Environment and Energy and Atmosphere credits?

Options:

A.

Design open spaces to support community interaction and connectivity while preserving natural site topography and ecological balance

B.

Introduce light pipes into enclosed areas that do not have direct exposure to the exterior

C.

Use double-glazed windows to improve thermal comfort while ensuring uniform temperature distribution

Buy Now
Questions 26

What information must be provided to demonstrate compliance with the Owner’s Project Requirements (OPR)?

Options:

A.

Preliminary data collection

B.

Basis of Design (BOD)

C.

Design charrette plan

D.

Renewable Energy Certificates (RECs)

Buy Now
Questions 27

A new mixed-use development includes residential units and commercial spaces. The project is in an urban area with existing pedestrian paths and public transportation infrastructure. How can the project team minimize exposure to emissions from vehicle traffic around the property while ensuring compliance with LEED strategies?

Options:

A.

Establish mandatory carpooling arrangements for residents and employees

B.

Integrate indoor plants to absorb carbon dioxide

C.

Designate a no-idling zone around the building perimeter

Buy Now
Questions 28

A furniture manufacturer is designing a new line of office chairs and wants to ensure that the products align with circular-economy principles. Which of the following strategies should the manufacturer prioritize to align with the principles of material stewardship?

Options:

A.

Use virgin materials for all chair components to ensure reliability

B.

Implement a take-back program for end-of-life chairs

C.

Source only locally available materials to reduce transportation impacts

Buy Now
Questions 29

Which of the following is a source reduction strategy to eliminate waste produced by a project?

Options:

A.

Custom design

B.

Design-build

C.

Material science

D.

Prefabrication

Buy Now
Questions 30

A project team reviews office chairs with a Type III environmental product declaration (EPD) for the five different categories of environmental impact reduction. Which of the following must the chairs demonstrate for product optimization?

Options:

A.

A reduction in at least two categories

B.

A reduction below the industry average in at least three categories

C.

A 5% reduction in all categories

D.

A 10% reduction in GHG emissions and a 10% reduction in at least two other categories

Buy Now
Questions 31

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner's Project Requirements (OPR)?

Options:

A.

All applicable codes and standards

B.

Interior finishes related to the project

C.

All project team members and applicable roles

D.

Energy efficiency goals and training requirements

Buy Now
Questions 32

What aspects of each space should the LEED consultant consider to identify the regularly occupied spaces on a project to ensure that floor area values are utilized consistently across credits?

Options:

A.

Rate of outdoor air provided per person

B.

Fire ratings of installed wall and ceiling assemblies

C.

Average number of occupants standing or seated

D.

Typical duration of occupancy in each space per day

Buy Now
Questions 33

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?

Options:

A.

Change the orientation of the design case building

B.

Optimize the slab depth of the design case building

C.

Decrease the gross floor area of the baseline building

D.

Increase the wall mass and types of windows in the baseline building

Buy Now
Questions 34

A developer is building a new shopping mall in a temperate climate. The developer wants to reduce operating costs and improve occupant experience. Which design scheme should the project team present?

Options:

A.

A design that increases peak thermal loads in the office and administrative spaces

B.

A design that reduces the overall parking footprint and provides preferred parking for electric-vehicle charging

C.

A design with a narrow floor plate that maximizes daylight in retail areas and minimizes the need for electric lighting

D.

A design with a large roof that collects rainwater to reduce stormwater runoff

Buy Now
Questions 35

An accessible garden planted with native plants contributes to the achievement of which of the following credit pairs?

Options:

A.

Sustainable Sites Credit, Sensitive Land Protection; Sustainable Sites Credit, Site Development - Protect or Restore Habitat

B.

Sustainable Sites Credit, Open Space; Sustainable Sites Credit, Rainwater Management

C.

Water Efficiency Credit, Water Metering; Sustainable Sites Credit, Tenant Design and Construction Guidelines

D.

Location and Transportation Credit, Surrounding Density and Diverse Uses; Sustainable Sites Credit, Site Assessment

Buy Now
Questions 36

A Healthcare Project is constructing a new building adjacent to an existing LEED Certified hospital facility. The new building's location is on the same hospital campus as the certified facility. The entire hospital campus was analyzed with an Environmental Site Assessment (ESA) as part of the certified facility's project scope. The new building project needs to complete a new Phase I ESA if

Options:

A.

the Phase II ESA uncovers suspected contamination

B.

contamination was identified by the certified facility

C.

the certified facility's Phase I ESA is older than 180 days

D.

the local equivalent standard is more stringent than ASTM E1527-05

Buy Now
Questions 37

If a commercial building is considered to have 100 peak visitors in a day, what is the minimum number of short-term

bicycle storage spaces that must be provided to earn one point under Location and Transportation Credit, Bicycle

Facilities?

Options:

A.

Three

B.

Four

C.

Five

D.

Ten

Buy Now
Questions 38

A project is designed to remodel an existing warehouse into multi-family housing. The exterior facade of the warehouse will remain, but 40% of the interior will be demolished and replaced for interior new construction. New materials will be used for the new construction. To achieve points in the Materials and Resources Credit, Building Life-Cycle Impact Reduction, which credit path option would apply?

Options:

A.

Historic Building Reuse

B.

Building and Material Reuse

C.

Whole-Building Life-Cycle Assessment

D.

Renovation of Abandoned or Blighted Building

Buy Now
Questions 39

An electrical team installs photovoltaic panels over a parking lot. This action contributes to which of the following credits?

Options:

A.

Optimize Energy Performance

B.

Light Pollution Reduction

C.

Low-Emitting Materials

D.

Demand Response

Buy Now
Questions 40

Which of the following actions should be taken to ensure that project team members understand and prioritize the selection of materials compliant with the Materials and Resources Credit: Building Product Disclosure and Optimization?

Options:

A.

Select locally sourced and manufactured materials

B.

Procure materials directly from raw material suppliers

C.

Include all building materials in a whole-building life-cycle analysis

D.

Include the material requirements in the project specifications

Buy Now
Questions 41

Which of the following types of water should a project team focus on utilizing to achieve water savings and acquire points under WEc2: Enhanced Water Efficiency, Option 6. Water Reuse, Path 1. Reuse-Ready System, while reducing reliance on potable water?

Options:

A.

Desalinated ocean water provided by a utility company

B.

Graywater collected and treated on-site

C.

Harvested and stored rainwater

Buy Now
Questions 42

Which of the following criteria does a project need to implement in order to qualify for Sustainable Sites Credit: Site Development - Protect or Restore Habitat, Option 1?

Options:

A.

Use of natural plants rated for their effect in reducing the heat island effect, while also restoring a minimum of 20% (including the building footprint) of all portions of the site identified as previously disturbed

B.

Use of only native or adapted vegetation, along with not restoring a minimum of 36% (including the building footprint) of all portions of the site identified as previously disturbed

C.

Use of native or adapted vegetation, restoring a minimum of 30% (including the building footprint) of all portions of the site identified as previously disturbed

D.

Use of natural vegetation and not artificial greenery, restoring a minimum of 25% (including the building footprint) of all portions of the site identified as previously disturbed

Buy Now
Questions 43

The energy-related systems analysis for Integrative Process credit for Core and Shell projects should include all system loads and occupants required by which Energy and Atmosphere prerequisite?

Options:

A.

Building-level energy metering

B.

Fundamental commissioning and verification

C.

Minimum energy performance

D.

Fundamental refrigerant management

Buy Now
Questions 44

For an emergency care facility project, which of the following credits can be achieved if the total cost of

permanently installed products are 25% cradle-to-cradle V3 Gold and 25% GreenScreen List Translator?

Options:

A.

Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Material Reuse

& Innovation Credit, Innovation, Exemplary Performance

B.

Materials and Resources Credit, Furniture and Medical Furnishing, Option 3. Multi-Attribute Assessment of

Products & Innovation Credit, Innovation, Exemplary Performance

C.

Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2.

Material Ingredient Optimization & Innovation Credit, Innovation, Exemplary Performance

D.

Materials and Resources Credit, Furniture and Medical Furnishings, Option 3. Multi-Attribute Assessment of

Products & Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2. Material Ingredient Optimization

Buy Now
Questions 45

In order for a product to contribute to Materials and Resources Credit, Building Product Disclosure and Optimization, Environmental Product Declarations, Option 1. Environmental Product Declaration, the product needs to be

Options:

A.

Forest Stewardship Council (FSC)-certified

B.

cradle-to-cradle certified

C.

third-party verified in a Corporate Sustainability Report (CSR)

D.

critically reviewed life-cycle assessment conforming to ISO 14044

Buy Now
Questions 46

Short-term bicycle storage in Location and Transportation Credit, Bicycle Facilities must be within 100 ft. (30 m) walking distance of any:

Options:

A.

Bicycle network

B.

Emergency access

C.

Main entrance

D.

Shower room

Buy Now
Questions 47

Which of the following is required to earn Energy and Atmosphere Credit, Renewable Energy Production if using a Solar Photovoltaic System?

Options:

A.

Carbon offsets

B.

Daylighting strategies

C.

Passive solar strategies

D.

Produced electricity consumed on-site

Buy Now
Questions 48

In the energy modeling of a building envelope, which of the following U-values should be considered as an assembly U-value?

Options:

A.

Wall

B.

Steel

C.

Glass

D.

Concrete

Buy Now
Questions 49

Which of the following is an example of nonpotable water that can be effectively used for landscape irrigation to improve water efficiency?

Options:

A.

Well water from a private borehole

B.

Dechlorinated swimming-pool water

C.

Street runoff taken directly from storm drains

Buy Now
Questions 50

Which of the following standards needs to be followed to comply with Indoor Environmental Quality Credit, Thermal Comfort?

Options:

A.

ASHRAE 55-2010

B.

ASHRAE 62.1-2010

C.

ASHRAE 90.1-2010

D.

ASHRAE 189.1-2010

Buy Now
Questions 51

Which of the following categories is included in a human impact assessment for LEED projects to guide planning, design, and operations?

Options:

A.

Historical landmarks

B.

Demographics

C.

Soil composition

Buy Now
Questions 52

Which practice is recommended for protecting HVAC systems during construction to maintain indoor environmental quality and enhance occupant quality of life?

Options:

A.

Maintain extreme-heat protection

B.

Use low-emitting materials

C.

Install temporary air filters

Buy Now
Questions 53

Which of the following strategies is essential for a project to comply with EQc2: Occupant Experience, Option 1. Biophilic Environment?

Options:

A.

Incorporate the five principles adapted from The Practice of Biophilic Design

B.

Encourage positive interactions between people and nature

C.

Select only the most relevant principles adapted from The Practice of Biophilic Design

Buy Now
Questions 54

When required to measure residential and non-residential densities, Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to measure the residential and non-residential densities in what way?

Options:

A.

Measure densities within a ¼ mile (0.40 km) radius of the project boundary

B.

Measure densities within a ¾ mile (1.20 km) radius of the project boundary

C.

Measure densities within a ⅓ mile (0.53 km) radius of the project boundary

D.

Measure densities within a ½ mile (0.80 km) radius of the project boundary

Buy Now
Questions 55

Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

Options:

A.

50,000 ft2 (4 645 m2) office project

B.

80,000 ft2 (7 432 m2) hospital project

C.

110,000 ft2 (10 219 m2) school project

D.

140,000 ft2 (13 006 m2) retail project

Buy Now
Questions 56

Which of the following is a leadership extraction practice that rewards projects for choosing materials with closed-loop recycling and take-back programs in LEED?

Options:

A.

Material reuse

B.

Bio-based elements

C.

Extended producer responsibility

D.

Forest Stewardship Council (FSC) wood products

Buy Now
Questions 57

A school wants to incorporate natural daylighting in classrooms on all sides of the building. What can the project design team explain to the school district about how this strategy will affect the operational energy cost?

Options:

A.

Heat gain will reduce the air conditioning load

B.

Having the lights off reduces the electricity use

C.

Reduction in lighting fixture use reduces re-lamping

D.

There would be passive solar heating benefits to all of the classrooms

Buy Now
Questions 58

A new Science Education Center is pursuing LEED certification. Which of the following strategies could be submitted to earn an Innovation in Design credit?

Options:

A.

The selection of energy-efficient LED fixtures for all of the building's lighting

B.

The installation of an air-purifying facade material on the front entrance of the building

C.

The integration of rainwater management strategies to achieve a Regional Priority Credit

D.

The implementation of a comprehensive metering strategy to measure three individual energy end uses

Buy Now
Questions 59

In an area where carbon-emission regulations are becoming progressively stricter, the goal is to future-proof the building for complete electrification and eliminate on-site fossil-fuel combustion. Which of the following measures can the project team use to maximize the building’s readiness for electrification while minimizing on-site combustion sources?

Options:

A.

Install natural-gas boilers as a backup heating source

B.

Plan for an electric heat-pump water-heating system

C.

Integrate rooftop solar panels to generate renewable electricity on-site

Buy Now
Questions 60

Several Materials and Resources credits give a bonus location valuation factor, which allows products extracted,

manufactured and produced within 100 mi. (161 km) of the project to take double valuation in credit calculations. The

intent of this bonus is

Options:

A.

to shorten construction duration by reducing shipping times

B.

to avoid spreading products with potentially invasive non-native pests

C.

to incentivize the purchase of products that support the local economy

D.

to promote design with indigenous materials in order to maintain local aesthetic quality

Buy Now
Questions 61

A project includes an automatic transfer switch and controls that enable the building’s on-site renewable-energy systems, energy storage, and critical equipment to operate during a power outage. What is this capability called?

Options:

A.

Load management

B.

Islanding

C.

Demand response

Buy Now
Questions 62

For a bicycle network to demonstrate compliance with Location and Transportation Credit, Bicycle Facilities, the bicycle network must connect to

Options:

A.

five bicycle trails

B.

at least eight diverse uses

C.

a restaurant, a grocery shop, a post office and two bus lines

D.

a rapid transit stop that is within 3 mi. (5 km) biking distance of the project boundary

Buy Now
Questions 63

To ensure long-term energy efficiency and grid resilience, which strategy should the project team prioritise first?

Options:

A.

Provide a high-performance building envelope

B.

Enrol in a demand-response programme with the local utility

C.

Purchase 100% Renewable Energy Certificates to offset projected electricity use

Buy Now
Questions 64

Questions 1–5 are based on the same project scenario. Please use the scenario information when answering.

A hospital certified under LEED V5 in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.

The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.

The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.

The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.

The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.

The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.

The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.

In addition to the vegetated terraces, the project team is considering installing a green roof with walkways, fountains, and seating areas for patients, visitors, and staff. If the project attempts SSc2: Accessible Outdoor Space, what percentage of the required outdoor space must be vegetated?

Options:

A.

20%

B.

25%

C.

30%

Buy Now
Questions 65

An owner has requested that the project team redesign a large office building. As part of the redesign, the owner would like to move the main entrance to the opposite side of the building. Achievement of which credit may be affected by the move?

Options:

A.

Location and Transportation Credit, High-Priority Site

B.

Location and Transportation Credit, Sensitive Land Protection

C.

Location and Transportation Credit, Surrounding Density and Diverse Uses

D.

Location and Transportation Credit, LEED for Neighborhood Development Location

Buy Now
Questions 66

A commercial building aims to reduce potable-water use by utilizing alternative water sources for appropriate applications. The architect must plan water distribution efficiently while considering the quality and treatment requirements of each water source.

Which of the following strategies will efficiently reduce the building’s potable-water consumption while maintaining safe and appropriate water use?

Options:

A.

Use potable water for all purposes and retain alternative water sources only as backup supplies

B.

Use graywater for HVAC cooling-tower makeup water and harvested rainwater for drinking fountains

C.

Use graywater for potable applications after comprehensive treatment

Buy Now
Questions 67

The WaterSense label or local equivalent requirement in Water Efficiency Prerequisite, Indoor Water Use Reduction ensures that eligible newly installed plumbing fixtures will

Options:

A.

be advertised as LEED compliant

B.

be both water efficient and high performing

C.

comply with mandatory federal government regulations

D.

comply with all international plumbing system requirements

Buy Now
Questions 68

What is the maximum walking distance allowed between short-term bicycle storage and a main entrance according to LTc4: Transportation Demand Management?

Options:

A.

600 ft. (182.88 m)

B.

800 ft. (243.84 m)

C.

400 ft. (121.92 m)

Buy Now
Questions 69

Which of the following LEED credit data should be used for a comprehensive 25-year carbon-emissions projection for a new building project?

Options:

A.

EAp5: Fundamental Refrigerant Management

B.

WEp1: Water Metering and Reporting

C.

MRc4: Building Product Selection and Procurement

Buy Now
Questions 70

Which of the following project types is required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations?

Options:

A.

Retail

B.

Schools

C.

Healthcare

D.

Core and Shell

Buy Now
Questions 71

A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?

Options:

A.

No action is necessary as the PV system is not required to be commissioned

B.

The PV system installer should commission his own installations and share the results with the project owner

C.

The Cx agent for the project must conduct or oversee the Cx of the PV system

D.

The building's mechanical engineer should commission his own installations and share the results with the project owner

Buy Now
Questions 72

Discussing the project goals to help identify the credits and options that the team should attempt is an example of

Options:

A.

documenting LEED credits

B.

creating the Basis of Design (BOD)

C.

developing the LEED Scorecard

D.

implementing the Commissioning (Cx) Plan

Buy Now
Questions 73

Which approach will contribute to maintaining compliance with Sustainable Sites Credit, Rainwater Management?

Options:

A.

Installing bioretention area

B.

Installing on-site renewable power generation facility

C.

Substituting impervious surface area with high-albedo paving materials

D.

Increase artificial turf on the roof

Buy Now
Questions 74

The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced

Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?

Options:

A.

Verify that training requirements are completed

B.

Develop systems manual for the commissioned systems

C.

Review contractor submittals for the commissioned systems

D.

Verify installation and performance of the commissioned systems

Buy Now
Questions 75

What LEED Building Design and Construction project type should exclude weekend transit service from the transit service level calculations for Location and Transportation Credit, Access to Quality Transit, if the project occupants do not commute to the building during weekends?

Options:

A.

Schools

B.

Data centers

C.

Hospitality

D.

Warehouses and distribution centers

Buy Now
Questions 76

Which of the following Materials and Resources credits or prerequisites is reviewed under the design phase documentation submission?

Options:

A.

PBT Source Reduction - Lead, Cadmium, and Copper

B.

PBT Source Reduction - Mercury

C.

Building Product Disclosure and Optimization - Environmental Product Declarations

D.

Building Product Disclosure and Optimization - Sourcing of Raw Materials

Buy Now
Questions 77

The project team achieved a strategy not addressed in the LEED Green Building Rating System, which proved to be a significant, measurable environmental benefit for the project. What can the project team do in order to get a benefit for this strategy?

Options:

A.

Submit a regional priority credit

B.

No benefit can be achieved since the strategy is not included in the rating system

C.

Submit the manufacturer's product declaration

D.

Submit an innovation credit

Buy Now
Questions 78

What supporting material is required for all LEED Building Design and Construction projects in order to document Location and Transportation Credit, Bicycle Facilities for the bicycle network?

Options:

A.

Photographs of bicycle network signage and directional signposts

B.

Photographs of the installed bicycle storage and shower facilities

C.

Vicinity map showing bicycle network, route and distance along network to eligible destination(s)

D.

Manufacturer specifications for the chosen bicycle storage facilities, including the number of bicycles supported by each bike rack

Buy Now
Questions 79

What building classification requires the energy model to determine the predicted power usage effectiveness (PUE) for Energy and Atmosphere Prerequisite, Minimum Energy Performance?

Options:

A.

Office

B.

Hospital

C.

Warehouse

D.

Data Center

Buy Now
Questions 80

An office project has the following items in its break room kitchen: a kitchen sink, a residential-style dishwasher, and a coffee machine. How would these items be addressed in Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

The kitchen sink is included in fixture calculations, the dishwasher and coffee machine must be ENERGY STAR® or performance equivalent

B.

The kitchen sink is included in fixture calculations, the dishwasher must be ENERGY STAR® or performance equivalent, and the coffee machine is not included in the prerequisite

C.

The kitchen sink and dishwasher must be WaterSense labeled and the coffee machine is not included in the prerequisite

D.

The kitchen sink and dishwasher must be WaterSense labeled and the coffee machine should be included in fixture calculations

Buy Now
Questions 81

A comprehensive rainwater management plan may include design elements such as

Options:

A.

artificial turf, bioretention pond, cisterns and hay bales

B.

cisterns, porous pavement, swales and vegetated roofs

C.

soil compaction, swales, vegetated roofs and xeriscaping

D.

bioretention pond, cisterns, porous pavement and stabilized construction entrance

Buy Now
Questions 82

In the step-by-step guidance for Location and Transportation Credit, Bicycle Facilities, which of the following requirements can define a bicycle network?

Options:

A.

One-way streets

B.

Bike share

C.

Slow speed roadways

D.

Traffic lights

Buy Now
Questions 83

Which of the following is true regarding LEED Pilot Credits?

Options:

A.

Pilot Credits are not specific to the rating systems

B.

Pilot Credits can be attempted in the design review stage only

C.

A registered Pilot Credit must be replaced on the LEED project's scorecard if that pilot credit is removed from the Pilot Credit Library

D.

Pilot Credit feedback surveys must be completed

Buy Now
Questions 84

What is the average flush rate for a dual flush toilet with a high flush rate of 1.6 gpf (6 lpf) and a low flush rate of 1.05 gpf (4 lpf)?

Options:

A.

1.05 gpf (4 lpf)

B.

1.19 gpf (4.5 lpf)

C.

1.23 gpf (4.66 lpf)

D.

1.32 gpf (5 lpf)

Buy Now
Questions 85

A core and shell project is located in a dense urban area that is known to have frequent fluctuations in the power supply grid (brown-outs). The project team is seeking LEED Platinum certification. Which credit should be pursued when considering the regional context?

Options:

A.

Energy and Atmosphere Credit, Demand Response

B.

Energy and Atmosphere Credit, Advanced Energy Metering

C.

Energy and Atmosphere Credit, Green Power and Carbon Offset

D.

Energy and Atmosphere Credit, Enhanced Refrigerant Management

Buy Now
Questions 86

Which of the following actions is aligned with EQc3: Accessibility and Inclusion?

Options:

A.

Provide lactation rooms or lactation pods

B.

Install automated door systems for all entryways

C.

Incorporate visual contrast between architectural elements

Buy Now
Questions 87

EAp1: Operational Carbon Projection and Decarbonization Plan requires a 25-year forecast. What is the primary purpose of this forecast?

Options:

A.

Prove that the building will be net-zero energy

B.

Estimate utility-cost savings to secure project financing

C.

Map future carbon emissions as the local electrical grid is projected to become cleaner

Buy Now
Questions 88

A coastal mixed-use development pursuing LEED BD+C certification is evaluating flood-resilience strategies to protect against sea-level rise. Which of the following strategies most comprehensively addresses flood resilience for IPp1: Climate Resilience Assessment?

Options:

A.

Elevate all critical mechanical, electrical, and plumbing systems above the 500-year flood elevation and design ground-floor spaces with flood-tolerant materials, drainage infrastructure, and resilient finishes

B.

Design foundation walls with reinforced concrete, waterproof membranes, and active dewatering pumps to keep below-grade spaces dry and functional during flooding

C.

Specify native flood-tolerant vegetation with bioswales and rain gardens throughout the site to absorb stormwater runoff and reduce peak flow rates

Buy Now
Questions 89

Which additional requirement must a project team meet to earn a second point for reducing carbon emissions from construction activities, beyond tracking all fuel and utility usage for contractor jobsite operations?

Options:

A.

Install a temporary solar-panel system on the construction site to offset emissions

B.

Track and report all combustion-fuel and energy use for the contractor and all subcontractors

C.

Submit a life-cycle assessment of all building materials used in the project

Buy Now
Questions 90

A new five-story building with a 30,000 ft2 (2 800 m2) footprint is being designed on a previously disturbed100,000 ft2 (9 290 m2) site. The remaining on-grade surface will be 35,000 ft2 (3 250 m2) of asphalt parking, and 35,000 ft2 (3 250 m2) of native vegetated open space. To achieve a point for exemplary performance under Option 1 of Sustainable Sites Credit, Site Development - Protect or Restore Habitat, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of

Options:

A.

12,500 ft2 (1 160 m2)

B.

15,000 ft2 (1 400 m2)

C.

25,000 ft2 (2 300 m2)

D.

35,000 ft2 (3 250 m2)

Buy Now
Questions 91

Which of the following strategies supports energy resilience by enhancing the grid interactivity of a building?

Options:

A.

Install smart meters to provide real-time data on energy consumption

B.

Install energy-storage systems that can deploy energy during peak-demand periods

C.

Use occupancy sensors to turn lights on and off automatically

Buy Now
Questions 92

For major renovation and new construction projects, the required energy and water-related system analyses should be the same except for

Options:

A.

site conditions

B.

massing and orientation

C.

plug and process load needs

D.

building envelope performance

Buy Now
Questions 93

A project attempting to meet the preferred parking requirements for Location and Transportation Credit, Green Vehicles may provide what incentive to meet the requirements and highlight the project sustainable vehicle strategy?

Options:

A.

Three years of free parking for green vehicles

B.

Preferred parking decals for 5% of occupants utilizing carpool vehicles

C.

A permanent discounted parking rate of at least 20% for all green vehicles

D.

An annual maintenance voucher for at least 5% of occupants driving green vehicles

Buy Now
Questions 94

A community center will be built on a plot in two phases. Phase 1 will include the building with a pool and gymnasium, while Phase 2 will include the outdoor grass soccer fields. For Phase 1 to achieve certification, where can the project set the LEED boundary?

Options:

A.

Around Phase 1 and 2

B.

Around Phase 1 and 2 while committing to keep the Phase 2 grounds undisturbed

C.

Around Phase 1

D.

Around Phase 1 while committing to keep the Phase 2 grounds undisturbed

Buy Now
Questions 95

What role does the LEED AP have when creating the Owner's Project Requirements (OPR) document?

Options:

A.

Oversees the design team writing the OPR

B.

Authors the OPR with the design team

C.

Publishes the completed OPR

D.

Helps the owner develop the OPR

Buy Now
Questions 96

During the early design phase of a new commercial office building, what action should the project team take to reduce the Global Warming Potential (GWP) of refrigerants?

Options:

A.

Select an HVAC system that uses refrigerants with a GWP of 700 or less

B.

Delay addressing refrigerant concerns until the commissioning phase, when system performance can be evaluated

C.

Specify any HVAC system and offset refrigerant emissions through carbon credits later, if needed

Buy Now
Questions 97

A downtown office building is unable to construct dedicated parking for its occupants. However, the building developer has partnered with a parking garage to offer discounted parking for its occupants. If the discounted parking rate is $450 per month, how much must the rate be for green vehicles for the building to receive one point for Location and Transportation Credit, Green Vehicles?

Options:

A.

$90

B.

$225

C.

$360

D.

$405

Buy Now
Questions 98

Which of the following design features enhances accessibility for physical diversity in a mixed-use development project?

Options:

A.

Use high-contrast colours for signage and wayfinding

B.

Provide non-text diagrams and symbols for signage

C.

Create meeting spaces that accommodate mobility devices

Buy Now
Questions 99

A large residential building project is exploring strategies to reduce reliance on the municipal water supply. The design must ensure that reused water meets local health and safety standards and remains feasible within the project’s operating budget.

Which of the following considerations should the project team prioritize to effectively implement the water-reuse system while maximizing water efficiency?

Options:

A.

Install water meters to monitor the use of reclaimed water

B.

Conduct a feasibility study regarding the availability of alternative water sources on-site

C.

Assess the energy use of water-treatment technologies

Buy Now
Questions 100

The Exemplary Performance threshold for Sustainable Sites Credit, Rainwater Management requires:

Options:

A.

Utilizing a rain garden to manage the 98th percentile rainfall event

B.

Managing 100% of rainfall that falls within the project boundary

C.

Achievement of both Option 1. Percentile of Rainfall Events and Option 2. Natural Land Cover Conditions

D.

Utilizing a combination of both structural and non-structural measures to manage the 98th percentile rainfall event

Buy Now
Questions 101

Which energy efficient lamp type is free from mercury?

Options:

A.

Compact Fluorescent

B.

High Pressure Sodium

C.

Light Emitting Diode

D.

T-8 Fluorescent

Buy Now
Questions 102

The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?

Options:

A.

Verify installation and performance of the commissioned systems

B.

Review the building 10 months after substantial completion

C.

Verify that training requirements are completed

D.

Develop a systems manual for the commissioned systems

Buy Now
Questions 103

Which federal agency designates Federal Renewal Community sites, which can be considered High Priority Sites for

project development?

Options:

A.

U.S. Internal Revenue Service

B.

U.S. Department of Agriculture

C.

U.S. Environmental Protection Agency

D.

U.S. Department of Housing and Urban Development

Buy Now
Questions 104

Which of the following credits can be awarded an Innovation point for Exemplary Performance?

Options:

A.

Indoor Environmental Quality Credit, Daylight

B.

Indoor Environmental Quality Credit, Low-Emitting Materials

C.

Indoor Environmental Quality Credit, Minimum Indoor Air Quality Performance

D.

Indoor Environmental Quality Credit, Acoustic Performance

Buy Now
Questions 105

Which of the following will result in a higher demand for potable water use in irrigation?

Options:

A.

Sparsely planted area

B.

Drip irrigation system

C.

High evapotranspiration rate

D.

Rainwater harvesting system

Buy Now
Questions 106

A project team seeking certification for a new school is attempting to achieve Materials and Resources Credit, Construction and Demolition Waste Management, Option 2. Reduction of Total Waste Material. What strategy can be taken to meet the requirements of this credit?

Options:

A.

Track waste materials per occupant

B.

Track waste materials used on site

C.

Document total waste by project cost

D.

Document total waste per building floor area

Buy Now
Questions 107

Which of the following acoustical units are used in Indoor Environmental Quality Credit, Acoustic Performance to measure reverberation time?

Options:

A.

T60

B.

STC

C.

Hz

D.

dBA

Buy Now
Questions 108

In Sustainable Sites Credit, Light Pollution Reduction, which factor is included in the lamp lumen uplight calculation?

Options:

A.

Total fixture power

B.

Site area of the project

C.

Quantity of installed luminaires

D.

Total fixture lumens below 90 degrees

Buy Now
Questions 109

The design team is comparing a conventional concrete frame with a mass-timber hybrid structure. When calculating the benefit for MRc2: Reduce Embodied Carbon, how does LEED treat the biogenic carbon of the mass-timber option?

Options:

A.

Subtract it from the upfront Module A1–A3 emissions to create a larger credit for the project

B.

Track it separately and count it as a benefit when sustainable harvesting is documented and Module C is included

C.

Exclude it because only fossil-fuel emissions from manufacturing and transportation are included

Buy Now
Questions 110

A commercial office building with a footprint of 70,000 ft2 (6 503.2 m2) has an overall site area of 200,000 ft2 (18 580.6 m2). The project design includes 15,000 ft2 (1 393.5 m2) of pedestrian oriented hardscape and 18,000 ft2 (1 672.3 m2) of vegetated open space. Which of the following is necessary to satisfy the requirement for the outdoor space to be physically accessible when calculating the Sustainable Sites Credit, Open Space?

Options:

A.

A garden space dedicated to industrial food production for use by local communities

B.

A garden space with only one vegetation type and species during the summer for visual interest

C.

A dark paving area with site elements to encourage parking near wetlands or naturally designed ponds

D.

A pedestrian-oriented paving or turf area with physical site elements that accommodate outdoor social activities

Buy Now
Questions 111

A design team is evaluating strategies to ensure that a healthcare facility remains operational for critical services during frequent power outages. The building currently relies on a diesel generator for emergency power, but the owner is interested in sustainable alternatives that can also contribute to the project’s energy efficiency during normal operations.

Which of the following strategies should the design team recommend to provide energy resilience for the healthcare facility while enhancing energy efficiency during regular operations?

Options:

A.

Install a new natural-gas generator as the primary source of backup power

B.

Implement solar photovoltaic panels with a battery energy-storage system

C.

Increase the capacity of the existing diesel generator

Buy Now
Questions 112

A project team is designing an office building and wants to ensure thermal comfort for occupants, especially in naturally conditioned spaces. How should the design team enhance thermal comfort in the naturally conditioned areas?

Options:

A.

Introduce radiant heating panels

B.

Increase air speed

C.

Use low-emissivity windows

Buy Now
Questions 113

What is the maximum number of points a project pursuing LEED for New Construction can achieve under Location

and Transportation Credit, Access to Quality Transit?

Options:

A.

Two points

B.

Three points

C.

Four points

D.

Five points

Buy Now
Questions 114

When designing a building that includes Electric Vehicle Supply Equipment (EVSE), which capability is needed to ensure maximum energy efficiency and cost savings?

Options:

A.

Install EVSE that operates only during peak hours to ensure availability

B.

Integrate EVSE with demand-response programs and load-management strategies

C.

Install Level 1 charging stations with 120-volt service for all spaces

Buy Now
Questions 115

A project team is planning a new office building in a cold climate. The team aims to achieve significant reductions in peak thermal loads. Which strategy should it apply to minimise peak thermal loads associated with infiltration?

Options:

A.

Increase wall-insulation thickness

B.

Install high-performance windows with low-emissivity coatings

C.

Seal potential air-leakage points and openings

Buy Now
Questions 116

The Chartered Institute of Building Services Engineers (CIBSE) Applications Manual 10 - 2005 provides guidance for which of the following?

Options:

A.

Replacing inefficient lighting fixtures

B.

Adopting natural ventilation as the sole servicing strategy

C.

Phasing out of equipment that uses CFC-based refrigerants

D.

Renovating with materials low in volatile organic compounds

Buy Now
Questions 117

What is the minimum number of members of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

Options:

A.

One

B.

Two

C.

Four

D.

Six

Buy Now
Questions 118

In the calculations for Water Efficiency Credit, Outdoor Water Use Reduction, food gardens

Options:

A.

must be calculated using at least 20% from an alternative water source

B.

must be calculated using 100% potable water

C.

may be included or excluded from the calculations

D.

may be calculated using a standard 20% reduction from baseline

Buy Now
Questions 119

A project in a cold climate does not want a highly reflective roof because they want the heat absorption. How can this

project comply with Sustainable Sites Credit, Heat Island Reduction?

Options:

A.

The credit is not feasible for this project

B.

The credit may be achieved by using nonroof measures only

C.

The credit is applicable for projects that document this special condition

D.

The credit can only be achieved by using an alternative compliance path

Buy Now
Questions 120

Which of the following goals does selecting low-emitting materials serve in the context of MRc3: Low-Emitting Materials?

Options:

A.

Increase thermal insulation

B.

Enhance indoor air quality

C.

Extend the lifespan of building materials

Buy Now
Questions 121

A project team develops a site plan for a school project with an athletic field and a playground with real grass. In order to qualify for the Water Efficiency Prerequisite, Outdoor Water Use Reduction, the landscape area calculations:

Options:

A.

Must include the athletic field and playground

B.

May include the playground but must exclude the athletic field

C.

Must include the playground but exclude the athletic field

D.

May include or exclude the athletic field and the playground

Buy Now
Exam Code: LEED-AP-BD+C
Exam Name: LEED AP Building Design + Construction (LEED AP BD+C)
Last Update: Aug 20, 2026
Questions: 404

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now LEED-AP-BD+C testing engine

PDF (Q&A)

$31.5  $104.99
buy now LEED-AP-BD+C pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 20 Aug 2026