Summer Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpm65

PK0-005 CompTIA Project+ Certification (2025) Questions and Answers

Questions 4

Which of the following activities should a project manager perform during the closing phase? (Select three).

Options:

A.

Lessons learned

B.

Risk analysis

C.

Removing resources

D.

Acquiring resources

E.

Statement of work sign-off

F.

Stakeholder analysis

G.

Removing access

Buy Now
Questions 5

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

Options:

A.

Synchronous

B.

Informal

C.

Asynchronous

D.

Formal

Buy Now
Questions 6

Which of the following statements best represents a network issue?

Options:

A.

The development team on the fourth floor is unable to access servers and email services.

B.

Cell phones served by a specific telecom company are getting a "no service" message.

C.

A user cannot connect to Wi-Fi because of a wrong ID or password.

D.

A user is receiving an automatic reply message saying that an email address does not exist.

Buy Now
Questions 7

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Options:

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix

Buy Now
Questions 8

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

Options:

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team's hard work

Buy Now
Questions 9

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

Options:

A.

Waterfall

B.

SDLC

C.

XP

D.

Scrum

Buy Now
Questions 10

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

Options:

A.

Information disposal

B.

Information classification

C.

Information access administration

D.

Information backup

Buy Now
Questions 11

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

Options:

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

Buy Now
Questions 12

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

Options:

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Buy Now
Questions 13

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

Options:

A.

Exploit the risk.

B.

Accept the risk.

C.

Avoid the risk.

D.

Transfer the risk.

Buy Now
Questions 14

Which of the following demonstrates awareness of regulations and standards when conducting a project?

Options:

A.

Establishing a measurement system for the team members' performance

B.

Controlling project costs to fall within the company-approved variance

C.

Reviewing advertising trends in the market before launching a new product

D.

Submitting architectural plans for approval before commencing construction

Buy Now
Questions 15

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

Options:

A.

Process moving

B.

Brainstorming

C.

Interview

D.

Focus group

Buy Now
Questions 16

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Buy Now
Questions 17

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

Options:

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

Buy Now
Questions 18

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Buy Now
Questions 19

A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?

Options:

A.

Scrum

B.

Extreme programming

C.

Waterfall

D.

Kanban

Buy Now
Questions 20

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

PK0-005 Question 20

PK0-005 Question 20

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23

B.

5

C.

10

D.

15

Buy Now
Questions 21

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Buy Now
Questions 22

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

Options:

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Buy Now
Questions 23

A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?

Options:

A.

Lead architect

B.

Project sponsor

C.

Program manager

D.

Scrum master

Buy Now
Questions 24

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

Options:

A.

Discovery

B.

Execution

C.

Initiating

D.

Planning

Buy Now
Questions 25

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Buy Now
Questions 26

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

Options:

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

Buy Now
Questions 27

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

Options:

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

Buy Now
Questions 28

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Options:

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Buy Now
Questions 29

Which of the following is a typical characteristic of Scrum?

Options:

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Buy Now
Questions 30

Which of the following is a reason to use a SOW on a project?

Options:

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Buy Now
Questions 31

While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?

Options:

A.

Reassess the resource pool.

B.

Review the QA plan from a similar project.

C.

Check on available resources for additional team members.

D.

Escalate the issue to the project sponsor.

Buy Now
Questions 32

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

Options:

A.

Performance testing

B.

User acceptance testing

C.

Stress testing

D.

Unit testing

Buy Now
Questions 33

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

Options:

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

Buy Now
Questions 34

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

Options:

A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Buy Now
Questions 35

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

Options:

A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Buy Now
Questions 36

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

Options:

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Buy Now
Questions 37

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

Options:

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

Buy Now
Questions 38

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

Options:

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Buy Now
Questions 39

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

Options:

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Buy Now
Questions 40

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

Options:

A.

SLA

B.

TOR

C.

SOW

D.

NDA

Buy Now
Questions 41

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

Options:

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Buy Now
Questions 42

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

Options:

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Buy Now
Questions 43

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

Options:

A.

Request a change control ticket.

B.

Review the schedule plan.

C.

Refine the project documentation.

D.

Revise the communication plan.

Buy Now
Questions 44

A company is starting a new implementation project The stakeholders are reviewing RFP responses to help make a decision about which project management consulting firm to hire. Given the following information:

PK0-005 Question 44

Which of the following is the best consulting firm for the company to hire?

Options:

A.

Consulting firm 1

B.

Consulting firm 2

C.

Consulting firm 3

D.

Consulting firm 4

Buy Now
Questions 45

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

Options:

A.

Change the precedence of the tasks to "finish-to-start".

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Buy Now
Questions 46

While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

Options:

A.

It highlights the performance issues of the project manager and team members.

B.

It lets the project manager know which stakeholders are allies for future projects.

C.

It helps the project manager create a more structured lessons-learned session.

D.

It identifies the stakeholders' real opinions about the project.

Buy Now
Questions 47

Which of the following software programs would be BEST to use lo store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Buy Now
Questions 48

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

Options:

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

Buy Now
Questions 49

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

Options:

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

Buy Now
Questions 50

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Options:

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Buy Now
Questions 51

A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:

Options:

A.

the preferred sponsor's communication channel.

B.

the preferred project manager's communication channel.

C.

the preferred reported communication channel.

D.

email communication as the preferred communication channel.

Buy Now
Questions 52

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?

Options:

A.

Stand-up

B.

Monthly status

C.

Gap analysis

D.

Gate review

Buy Now
Questions 53

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Options:

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

Buy Now
Questions 54

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Options:

A.

Development

B.

Production

C.

Testing

D.

QA

Buy Now
Questions 55

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

Options:

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Buy Now
Questions 56

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

Options:

A.

Risk register

B.

Change log

C.

Traceability matrix

D.

Project status report

Buy Now
Questions 57

Which of the following best describes the reason a waterfall approach would be used for a project?

Options:

A.

The executive team still has no clear requirements for the product.

B.

The executive team is looking to review the product only once after the product is finalized.

C.

The executive team is expecting constant delivery of components.

D.

The executive team wants to reduce the budget for development.

Buy Now
Questions 58

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

Options:

A.

Train users on the proper use of the system.

B.

Escalate the issue to the CCB

C.

Hold sessions to understand user challenges.

D.

Track system usage and report user activity.

E.

Log the issue in the project risk register.

F.

Create a memorandum of acceptable use.

Buy Now
Questions 59

Which of the following requires the MOST availability from the business team?

Options:

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Buy Now
Questions 60

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

Options:

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

Buy Now
Questions 61

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Buy Now
Questions 62

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

Options:

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Buy Now
Questions 63

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

Options:

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Buy Now
Questions 64

Which of the following statements best describes a content management system?

Options:

A.

A system to manage electronic signatures and document workflow

B.

A system to manage database integration and provide messaging services

C.

A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish

D.

A system to manage documents archival, such as emails, spreadsheets, and support tickets

Buy Now
Questions 65

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

Options:

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Buy Now
Questions 66

A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?

Options:

A.

Awareness of the company vision, mission statement, and values

B.

Impact of the project on the company's brand value

C.

Awareness of applicable regulations and standards

D.

Impact of the project on the local and global environments

Buy Now
Questions 67

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

Options:

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

Buy Now
Questions 68

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Buy Now
Questions 69

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

Options:

A.

Use only full-time employees even if the project is delayed.

B.

Hire all team members to avoid any delay in the project.

C.

Close the contract and pay the contractors cash for the remainder of the project.

D.

Look for an overseas vendor to finalize the project work.

Buy Now
Questions 70

Which of the following BEST illustrates how team members with different roles should interact on the team?

Options:

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Buy Now
Questions 71

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

Options:

A.

The retrospective session feedback was not communicated properly.

B.

The project resources were released ahead of time.

C.

The documentation was not archived as per the PMO standards.

D.

The validation of deliverables is running behind schedule.

Buy Now
Questions 72

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

Options:

A.

Assemble a new project with existing resources.

B.

Obtain the final report from release management.

C.

Notify the functional manager that resources are released.

D.

Allocate resources in a different project

Buy Now
Questions 73

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

Options:

A.

Issue log

B.

Gantt chart

C.

Milestone chart

D.

Change control log

Buy Now
Questions 74

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

Options:

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Buy Now
Questions 75

Which of the following best describes why conducting lessons learned sessions is important?

Options:

A.

To discuss as a team how to improve and eliminate all the issues in the project

B.

To conduct the team’s performance evaluation and document the results

C.

To report all the mistakes and ensure others do not make the same ones

D.

To document what went right and wrong, as well as possible improvements

Buy Now
Questions 76

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Options:

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Buy Now
Questions 77

A new project manager was assigned to a project during the execution phase. The project manager discovers a lot of potential areas that may prevent the project from completing deliverables Which of the following should the project manager do first?

Options:

A.

Review the project risk register.

B.

Update the defect tracker.

C.

Meet with stakeholders to discuss concerns.

D.

Add the potential blockers to the issues list.

Buy Now
Questions 78

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

Options:

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

Buy Now
Questions 79

During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?

Options:

A.

Milestone chart

B.

Velocity chart

C.

Task board

D.

Burndown chart

Buy Now
Questions 80

A member keeps bringing up unrelated topics during a team meeting. Which of the following should the protect manager do to keep the discussion on track?

Options:

A.

Remind the team member about the meeting agenda and invite the member to add the topic to the next meeting's agenda.

B.

Ask the team member to leave the meeting and create a new meeting to discuss these topics.

C.

Adjust the current meeting's agenda to accommodate the team member's topics.

D.

Allow the team member to bring up the topics, which could lead to important discussions and insights.

Buy Now
Questions 81

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

PK0-005 Question 81

B)

PK0-005 Question 81

C)

PK0-005 Question 81

D)

PK0-005 Question 81

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 82

Which of the following best describes the role of a PM for a CRM system?

Options:

A.

To track sales

B.

To store customer information

C.

To implement new features

D.

To pay vendors

Buy Now
Questions 83

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

Options:

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Buy Now
Questions 84

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options:

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Buy Now
Questions 85

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

Options:

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Buy Now
Questions 86

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

Options:

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.

Buy Now
Questions 87

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

Options:

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Buy Now
Questions 88

Which of the following BEST identifies the intent and purpose of a project closeout report?

Options:

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Buy Now
Questions 89

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

Options:

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Buy Now
Questions 90

During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?

Options:

A.

Issue log

B.

Defect log

C.

Risk register

D.

Change log

Buy Now
Questions 91

Which of the following is the main reason for documenting artifacts?

Options:

A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Buy Now
Questions 92

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

Options:

A.

Continuous integration

B.

Rollback plan

C.

Customer notification

D.

Automated testing

Buy Now
Questions 93

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

Options:

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Buy Now
Questions 94

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Options:

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Buy Now
Questions 95

The goal of a project is to fulfill specific technical features requested by customers. Which of the following actions should the product owner take?

Options:

A.

Define the success criteria.

B.

Create a communication plan.

C.

Use a task board.

D.

Perform a root cause analysis.

Buy Now
Questions 96

Which of the following is a characteristic that defines a project?

Options:

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

Buy Now
Questions 97

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

Options:

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

Buy Now
Questions 98

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

Options:

A.

Milestone chart

B.

Work breakdown structure

C.

Project charter

D.

Detailed scope statement

Buy Now
Questions 99

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

Options:

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Buy Now
Questions 100

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

Options:

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Buy Now
Questions 101

A product manager is producing a project status report for key stakeholders Which of the following should most likely be included? (Select two).

Options:

A.

Feedback

B.

Financial summary

C.

Project schedule

D.

Organizational chart

E.

Approval

F.

Risks

Buy Now
Questions 102

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

Options:

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Buy Now
Questions 103

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Options:

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Buy Now
Questions 104

Which of the following is the best example of a breach of physical security?

Options:

A.

System user IDs being used by multiple individuals

B.

Printers that do not request user authentication

C.

Developers having full access to both development and production environments

D.

Project documentation that is only kept on a removable device

Buy Now
Questions 105

Which of the following are primary features provided by a standard laaS solution? (Select two).

Options:

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Buy Now
Questions 106

Which of the following should occur first when planning maintenance windows?

Options:

A.

Diagnose potential areas for concern.

B.

Notify the customer base.

C.

Determine a rollback plan.

D.

Understand the organization's production cycle.

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2025)
Last Update: Jun 15, 2025
Questions: 362

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now PK0-005 testing engine

PDF (Q&A)

$36.75  $104.99
buy now PK0-005 pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 18 Jun 2025