PSP Planning & Scheduling Professional (PSP) Exam Questions and Answers

Questions 4

Determine the correct formula and date for the late finish for Activity 2001.

PSP Question 4

Options:

A.

LF.2001 - 1 day -> 08-28-01.

B.

LS.2002- 1 day-> 08-29-01.

C.

LS.2002 + 1 day -> 08-30-01.

D.

LS.2002 - 1 day -> 08-28-01.

Buy Now
Questions 5

Which statement is true?

Options:

A.

Where compensability cannot be established, excusability is assumed.

B.

Where compensability can be established, excusabltity cannot be assumed.

C.

Where compensability cannot be established, excusability is a given.

D.

Where compensability can be established, excusability is assumed.

Buy Now
Questions 6

Free float is the

Options:

A.

Difference between the early dates and late dates of an activity.

B.

Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.

C.

Difference between the early finish dates and late finish dates of an activity.

D.

Difference In float value of the critical path activities and the float value of the specific activity being analyzed.

Buy Now
Questions 7

Why does activity 11001 not show successor activities?

PSP Question 7

Options:

A.

The early finish and late finish are circular

B.

It is the penultimate work required for the project

C.

The scheduler forgot to add the successor activities

D.

It is the final activity for the required work for the project

Buy Now
Questions 8

Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

Options:

A.

407 days

B.

255 days

C.

267 days

D.

477 days

Buy Now
Questions 9

In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

Options:

A.

The schedule has too much detail to reflect an accurate critical path.

B.

Different calendars are assigned to certain activities in the logical chain.

C.

The schedule is projecting an "early completion".

D.

Certain activities in the critical path have no successors.

Buy Now
Questions 10

Which of the following is NOT input data to the construction planning process?

Options:

A.

Input from the owner

B.

The contract

C.

Bonding capacity of subcontractors

D.

Input from the contractor

Buy Now
Questions 11

What is accurate about Activity 7001 in the precedence diagram?

Options:

A.

The successor FF lag from 7001 to 11001 is not shown

B.

The LF is correct

C.

The TF is not calculated correctly

D.

The LF is not correct

Buy Now
Questions 12

What are Phases based on and derived from?

Options:

A.

Resources

B.

Constructability

C.

Score of Work

D.

Budget

Buy Now
Questions 13

What is a critical path method schedule?

Options:

A.

List of work to be accomplished by responsible party and when it is to be accomplished

B.

The timeline of the riskiest work

C.

A graphical means of showing the important work

D.

A network diagram of logically interconnected activities

Buy Now
Questions 14

The data date or status date of a schedule represents the:

Options:

A.

date the monthly update is performed

B.

date the project manager turns in the schedule update

C.

system date when the software calculates the update

D.

date on which progress is based

Buy Now
Questions 15

When a fragnet of activities represents a known schedule risk, which activity will most likely change the overall outcome?

Options:

A.

The activity with the highest sensitivity.

B.

The activity with the longest duration.

C.

The activity with the lowest total float value.

D.

The activity with the highest resource loading.

Buy Now
Questions 16

Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

PSP Question 16

Options:

A.

8 work days

B.

18 work days

C.

7 work days

D.

15 workdays

Buy Now
Questions 17

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Options:

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Buy Now
Questions 18

Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

Options:

A.

C.

B.

B.

C.

S.

D.

W.

Buy Now
Questions 19

For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?

Options:

A.

Additional extended overhead is also being shown in this activity

B.

Some costs resulting from the crashed efforts were forgotten in previous activities

C.

Generally, more equipment is used for a crashed project; therefore, it costs more to demobilize

D.

Management bonuses for early completion were included in this activity

Buy Now
Questions 20

Is activity 7001 pictured correctly in the precedence diagram?

PSP Question 20

Options:

A.

No, the total float is not shown correctly.

B.

Yes, except the early finish date is not shown.

C.

No, the start-to-start and finish-to-finish relationships are backwards.

D.

Yes, the duration is 48 days.

Buy Now
Questions 21

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

Options:

A.

Is a milestone.

B.

It is on the critical path.

C.

Was completed in the past.

D.

Has yet to be completed.

Buy Now
Questions 22

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?

Options:

A.

3 workdays

B.

18 workdays

C.

8 workdays

D.

7 workdays

Buy Now
Questions 23

Which of the following is NOT required when performing weekly or monthly schedule updates?

Options:

A.

Percent complete.

B.

Remaining duration of activities.

C.

Actual finish of activities.

D.

Original duration of activities.

Buy Now
Questions 24

Time-scaled logic diagrams are

Options:

A.

Only calculated using a computer.

B.

The same as a pure-logic diagram.

C.

Used to calculate the most probable activity duration.

D.

Logic networks that are drawn to match the calendar.

Buy Now
Questions 25

What is a key first step in developing a critical path method schedule?

Options:

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations.

D.

Drawing the logic diagram.

Buy Now
Questions 26

Determine the correct formula and date for the late finish for Activity 9004.

PSP Question 26

Options:

A.

LS.10002 + 1 day -> 11-29-03.

B.

LS.10002^ Lag.7 + i day -> 11-20-03.

C.

LS.10002 - 1 day -> 11-27-03.

D.

LS.10002 - Lag.7 - l day -> 11-20-03.

Buy Now
Questions 27

Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

Options:

A.

Estimating remaining durations of activities.

B.

The correct recording of actual start dates.

C.

Making "downstream" logic revisions as required.

D.

Entering the time impacts of delays and change orders.

Buy Now
Questions 28

What does the narrow band at "Y" represent?

PSP Question 28

Options:

A.

Resource limitation period.

B.

A rework period.

C.

Activity inactivity.

D.

You cannot tell with the information supplied.

Buy Now
Questions 29

The schedule or budget at completion less the estimate at completion is___________.

Options:

A.

the schedule variance

B.

the variance at completion

C.

the cost variance

D.

the profit or loss for the project

Buy Now
Questions 30

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

PSP Question 30

Options:

A.

06-11-02.

B.

06-04-02.

C.

06-18-02.

D.

06-05-02.

Buy Now
Questions 31

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Options:

A.

Projected crew size

B.

Estimated labor hours

C.

Hours in a standard work day

D.

Estimated cost

Buy Now
Questions 32

Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

Options:

A.

Multiple calendars.

B.

Start and finish constraints.

C.

Preferential logic.

D.

Front end loading.

Buy Now
Questions 33

Who will receive the most benefit from a master schedule of the Spring Highway project?

Options:

A.

ALPHA

B.

GOUGE. Inc

C.

BILCO

D.

SDOT

Buy Now
Questions 34

Which of the following will always describe the critical path? The path with

Options:

A.

The longest duration through the network.

B.

Zero float.

C.

Negative float.

D.

The shortest duration and negative float.

Buy Now
Questions 35

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS of 2003 less 1 day equaling to 06 Oct 2021

B.

LS of 2003 less 1 day equaling to 06 Nov 2021

C.

LS of 2003 plus 1 day equaling to 07 Oct 2021

D.

LS of 2003 less 1 day equaling to 05 Oct 2021

Buy Now
Questions 36

In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

Options:

A.

Budgeted cost of work scheduled

B.

Budgeted cost of work performed

C.

Schedule performance index

D.

Actual cost of work scheduled

Buy Now
Questions 37

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Options:

A.

Not suitable for complicated projects with multiple planned critical paths.

B.

Accuracy is increased by inserting delaying events into the as-planned schedule.

C.

Not suitable for projects with long durations.

D.

Less accurate as the analysis advances through the project.

Buy Now
Questions 38

What activities are concurrent to Activity 2001 in the "normal" schedule?

PSP Question 38

Options:

A.

7001.

B.

1001.

C.

1000.

D.

2003.

Buy Now
Questions 39

Should you verify the as-built schedule before proceeding with a schedule analysis?

Options:

A.

Yes, every dale needs to be verified but to not waste client money it should be restricted to just a few dates

B.

Yes. the accuracy of the analysis depends on the accuracy of the dates

C.

No. the contractor/owner dates should be reliable

D.

No the analysis should use the dates provided

Buy Now
Questions 40

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

Options:

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Buy Now
Questions 41

Control Level Schedule activities are NOT one of the following:

Options:

A.

always analogous with Control Accounts

B.

always used to establish the scope and track the status of automation control systems

C.

may be composed form multiple WBS deliverable packages

D.

always reporting the status of phase deliverables

Buy Now
Questions 42

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor has included several reports with its submittal, including a report that sorts all activities by total float. What is the value of this report?

Options:

A.

Allows you to review activities in the order they could start

B.

Allows you to confirm the current logical flow of the work

C.

Allows you to determine which activities will take the longest

D.

Allows you to determine which activities will be performed by the owner

Buy Now
Questions 43

Which of the following is NOT required when initially planning a project?

Options:

A.

Resource Identification and leveling.

B.

The duration of each task.

C.

A schedule that identifies tasks required on a project.

D.

Logical relationships between the tasks.

Buy Now
Questions 44

Resource planning must take all of the following into account except for:

Options:

A.

Types of materials, equipment and labor skills required to complete the project.

B.

Earned value techniques established for the project.

C.

Time available to complete the project.

D.

Cash flow (expenditure) limitations for completing work on the project.

Buy Now
Questions 45

A driving relationship is _____________________.

Options:

A.

A critical relationship.

B.

A finish-to-start relationship.

C.

The link between two related activities.

D.

The link between a predecessor and the activity whose dates it controls.

Buy Now
Questions 46

Determine the correct formula and date for the late finish for Activity 9004.

Options:

A.

LF of 10002 less 24 days

B.

LS of 9004 plus 72 days

C.

LF of 8001 plus 72 days

D.

LS of 10002 less lag of 7 days plus 1 day equaling 20 Nov 2023

Buy Now
Questions 47

During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

PSP Question 47

Options:

A.

Delay product release by 5 days.

B.

Expedite packaging by 5 days.

C.

Expedite printing by 5 days.

D.

Delay manufacturing by 5 days.

Buy Now
Questions 48

What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

Options:

A.

ADM is limited to finish-to-start logic relationships, while PDM is not.

B.

PDM is a bar chart with network logic, while ADM is a pure logic network.

C.

ADM is manual CPM calculations, while PDM is computerized.

D.

ADM uses arrows, while PDM uses boxes.

Buy Now
Questions 49

What portion of Activity B is on the critical path?

Options:

A.

Last half of the activity

B.

None of it

C.

First half of the activity

D.

The whole activity

Buy Now
Questions 50

Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

PSP Question 50

Options:

A.

Predecessor is activity 5001, successor is activity 8001

B.

Predecessor is activity 4001, successor is activity 8001

C.

Predecessor is activity 9001, successor is activity 9002

D.

Predecessor is activity 5001, successor is activity 8002

Buy Now
Questions 51

Which of the following parties is NOT a stakeholder of the Spring Highway project?

Options:

A.

ALPHA

B.

GOUGE

C.

BILCO

D.

DEVCO

Buy Now
Questions 52

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

Options:

A.

The delay must affect the critical path.

B.

The delay must be concurrent with the delay attributable to both parties.

C.

The delay must not cause monetary harm to the defendant.

D.

The delay must affect the contractor's planned construction schedule.

Buy Now
Questions 53

What was the original planned duration for Activity A through Activity G?

PSP Question 53

Options:

A.

26.

B.

28.

C.

24.

D.

25.

Buy Now
Questions 54

EBS is an acronym for:

Options:

A.

Elongated Budget Synopsis

B.

European Basic Schedule

C.

Enterprise Breakdown Structure

D.

Eventual Base Structure

Buy Now
Questions 55

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

Options:

A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

Buy Now
Questions 56

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

PSP Question 56

Options:

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Buy Now
Questions 57

Determine the correct formula and date for the late finish for Activity 2002.

PSP Question 57

Options:

A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.

Buy Now
Questions 58

Value engineering is:

Options:

A.

targeted at the design itself

B.

intended to provide the least life-cycle cost

C.

established to provide the greatest value

D.

intended to determine if the project will be completed economically

Buy Now
Questions 59

Budgeted cost of work scheduled is _______________________.

Options:

A.

The value of the completed work expressed in terms of the budget assigned to that work

B.

The total authorized budget for accomplishing the project scope

C.

The expected total cost of an activity, group of activities or the project

D.

The sum of all budgets for work scheduled to be accomplished within a given time period

Buy Now
Questions 60

Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

PSP Question 60

Options:

A.

80 lifts

B.

50 lifts

C.

5 lifts

D.

20 lifts

Buy Now
Questions 61

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

Options:

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Buy Now
Questions 62

The work breakdown structure is used to organize

Options:

A.

"Smart activity ID codes" representing similar items of scheduled work

B.

The chart of accounts

C.

Similar activity coding of schedule activities

D.

The smallest defined work packet

Buy Now
Questions 63

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

Options:

A.

3.3%

B.

2.2%

C.

23%

D.

2 4%

Buy Now
Questions 64

Which of the following is the most important scheduling consideration for the BILCO contractual scope?

Options:

A.

Logical phasing lies

B.

Update frequency

C.

Conforming CPM schedule to SDOT standards

D.

Cost loading

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Oct 31, 2025
Questions: 216

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now PSP testing engine

PDF (Q&A)

$31.5  $104.99
buy now PSP pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 31 Oct 2025