Pre-Summer Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

CAPM Certified Associate in Project Management (CAPM) Questions and Answers

Questions 4

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Options:

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Buy Now
Questions 5

Which enterprise environmental factors should be considered when creating a new procurement contract?

Options:

A.

Supply chains

B.

Trial engagements

C.

Lessons learned register

D.

Local laws and regulalk

Buy Now
Questions 6

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

Options:

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Buy Now
Questions 7

A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release.

What should the project manager do next to engage the new stakeholder?

Options:

A.

Add the stakeholder to the communications management plan.

B.

Conduct a one-on-one interview with the stakeholder.

C.

Invite the stakeholder to the sprint-planning meeting.

D.

Send the stakeholder a questionnaire.

Buy Now
Questions 8

An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two)

Options:

A.

Daily scrum

B.

Increments

C.

Sprint retrospective

D.

Sprint backlog

E.

Product backlog

Buy Now
Questions 9

Which actions should a project manager follow to manage stakeholders?

Options:

A.

Identify the key stakeholders and keep them informed at all times.

B.

Identify the stakeholders, planning, managing and monitoring their engagement

C.

Meet and keep informed any person related to the project, at all times

D.

Identify the stakeholders and monitor their level of satisfaction

Buy Now
Questions 10

Which of the following statements correctly characterizes pull communication?

Options:

A.

It includes letters, memos, reports, emails, and faxes.

B.

It requires recipients to access communication content at their own discretion.

C.

It is the most efficient way to ensure a common understanding among all participants.

D.

It is primarily used when the volume of information to be transferred is minimal.

Buy Now
Questions 11

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

Options:

A.

Iteration planning

B.

Retrospective

C.

Backlog refinement review

D.

Daily standup

Buy Now
Questions 12

When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what should the practitioner do first?

Options:

A.

Develop the feature as a parallel work package.

B.

Shorten the current work period and begin the new work.

C.

Ask a dedicated team member to complete it immediately.

D.

Prioritize it in the requirements list for the next work period.

Buy Now
Questions 13

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

Options:

A.

Static payback period = 6 + 1300 / 500 = 6.6

B.

Static payback period = 3 + 1200 / 500 = 5.4

C.

Static payback period = 5 + 700 / 500 = 5.4

D.

Static payback period = 5 + 200 / 500 = 5.4

Buy Now
Questions 14

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

Options:

A.

Cost-reimbursable contracts

B.

Time and Material contracts (TandM)

C.

Fixed-price contracts

D.

Cost Plus Fixed Fee Contracts (CPFF)

Buy Now
Questions 15

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

Options:

A.

-700

B.

-200

C.

200

D.

500

Buy Now
Questions 16

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Options:

A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management

Buy Now
Questions 17

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Buy Now
Questions 18

Which three techniques can be estimate costs?

Options:

A.

Financing, bottom-up estimating, and expert judgment

B.

Cost aggregation, analogous estimating, and financing

C.

Expert judgment, financing, and cost aggregation

D.

Expert judgment, analogous estimating, and bottom-up estimating

Buy Now
Questions 19

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

Options:

A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

Buy Now
Questions 20

Which tool and technique is used in Conduct Procurements?

Options:

A.

Teaming agreements

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Buy Now
Questions 21

Which of the following is used as input to prepare a cost management plan?

Options:

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Buy Now
Questions 22

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Options:

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Buy Now
Questions 23

What tern describes an intentional activity to modify a nonconforming product or product component?

Options:

A.

Preventive action

B.

Corrective action

C.

Defect repair

D.

Updates

Buy Now
Questions 24

At the start of a typical project life cycle, costs are:

Options:

A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Buy Now
Questions 25

Why is tailoring required in a project?

Options:

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required.

Buy Now
Questions 26

Which is the communication method used in the Report Performance process?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Stakeholder analysis

D.

Status review meetings

Buy Now
Questions 27

Tailoring considerations for project scope management may include:

Options:

A.

requirements management, stability of requirements, development approach, and validation and control.

B.

WBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables.

C.

business needs, product descriptions, project restrictions, and project management plan.

D.

issues defining and controlling what is included in the project, vended deliverables, and quality reports.

Buy Now
Questions 28

Which type of managers do composite organizations involve?

Options:

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Buy Now
Questions 29

A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project.

How should the project manager report the status of the project?

Options:

A.

The project is at risk as the cost variance (CV) is negative.

B.

The project is within budget and within schedule.

C.

The project is within budget but is delayed.

D.

The project is tracking well as the cost variance (CV) is negative.

Buy Now
Questions 30

Which of the following statements is true regarding project and product lifecycles?

Options:

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.

Buy Now
Questions 31

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 32

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

Options:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Buy Now
Questions 33

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

Options:

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Buy Now
Questions 34

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Options:

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Buy Now
Questions 35

While working in an adaptive environment, a business analyst is collaborating with other roles in drafting a product roadmap. Which three roles are involved in establishing the product roadmap? (Choose three)

Options:

A.

Project sponsor

B.

Portfolio manager

C.

End user

D.

Program manager

E.

Internal inspector

Buy Now
Questions 36

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Buy Now
Questions 37

Which of the following projects is a quality candidate for adaptive approaches?

Options:

A.

Installing new computers across offices

B.

Retrofitting an old building

C.

Upgrading an information system

D.

Designing a new suspension bridge

Buy Now
Questions 38

What organizational process asset (OPA) might impact a project ' s outcome?

Options:

A.

Processes, polices, and procedures

B.

Legal restrictions

C.

Infrastructure, resource availability. and employee capability

D.

Financial considerations

Buy Now
Questions 39

Which grid shows which resources are tied to work packages?

Options:

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Project assignment chart

D.

Personnel assignment matrix

Buy Now
Questions 40

Which process determines the correctness of deliverables?

Options:

A.

Verify Deliverables

B.

Validate Deliverables

C.

Review Deliverables

D.

Analyze Deliverables

Buy Now
Questions 41

Which of the following is used as an input to prepare a cost management plan?

Options:

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Buy Now
Questions 42

A project manager is leading a project in a volatile industry. Industry standards are updated often, which requires the project team to make frequent adjustments to their work.

What should the project manager create to manage the possible changes?

Options:

A.

Communications management plan

B.

Cost management plan

C.

Risk management plan

D.

Quality management plan

Buy Now
Questions 43

Which of the following are outputs of Develop Project Team?

Options:

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Buy Now
Questions 44

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

Options:

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

Buy Now
Questions 45

Projects programs subsidiary portfolios.... objectives refer to?

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?

Options:

A.

Operations Management

B.

Project Management

C.

Program Management

D.

Portfolio Management

Buy Now
Questions 46

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

Options:

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Buy Now
Questions 47

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (TandM)

Buy Now
Questions 48

Which of the following technology platforms is most effective for sharing information when managing virtual project teams?

Options:

A.

Video conferencing

B.

Audio conferencing

C.

Shared portal

D.

Email/chat

Buy Now
Questions 49

A project manager is identifying the risks of a project. Which technique should the project manager use?

Options:

A.

Representations of uncertainty

B.

Prompt lists

C.

Audits

D.

Risk categorization

Buy Now
Questions 50

The diagram below is an example of a:

Options:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Buy Now
Questions 51

A project team of telecommuters located in three different time zones regularly misses project deadlines Daily meetings often start and end with the same person talking and the rest of the team listening The project manager determines that communication among team members must be addressed.

What communication step is missing from the daily meetings?

Options:

A.

Interpersonal communication

B.

Feedback response communication

C.

Push communication

D.

Pull communication

Buy Now
Questions 52

Which kind of communication should the project manager use when creating reports for government bodies?

Options:

A.

Hierarchical

B.

External

C.

Formal

D.

Official

Buy Now
Questions 53

Which sentence summarizes the salience model?

Options:

A.

Classifies stakeholders based on assessment of their power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Buy Now
Questions 54

Which activity is an input to the Conduct Procurements process?

Options:

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

Buy Now
Questions 55

Which of the following includes how requirements activities will be planned, tracked, and reported?

Options:

A.

Configuration management plan

B.

Scope baseline

C.

Requirements management plan

D.

Schedule baseline

Buy Now
Questions 56

Which of the following is an input to Control Scope?

Options:

A.

Project schedule

B.

Organizational process assets updates

C.

Project document updates

D.

Work performance information

Buy Now
Questions 57

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Buy Now
Questions 58

Which behavior is a management trait?

Options:

A.

Asking what and why

B.

Challenging the status quo

C.

Innovating

D.

Relying on control

Buy Now
Questions 59

A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?

Options:

A.

Create a risk in the risk register for each S1 defect and assign actions.

B.

Consult the risk register and implement the risk response actions.

C.

Ask the developers to work longer hours and resolve the defects.

D.

Review the organizational chart to find out who else can sign off UAT.

Buy Now
Questions 60

Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

Options:

A.

Program

B.

Functional

C.

Project

D.

Portfolio

Buy Now
Questions 61

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Buy Now
Questions 62

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

Options:

A.

updates.

B.

defect repairs.

C.

preventive actions.

D.

corrective actions.

Buy Now
Questions 63

Quality metrics are an output of which process?

Options:

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 64

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

Options:

A.

mitigate

B.

accept

C.

transfer

D.

avoid

Buy Now
Questions 65

During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?

Options:

A.

Move these user stories back to the product backlog for reprioritization.

B.

Remove these user stories as they are not important.

C.

Advance these user stories to the top of the next sprint backlog.

D.

Complete these user stories in the current sprint and extend the sprint length.

Buy Now
Questions 66

Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?

Options:

A.

Resource breakdown structure

B.

Physical resources assignment

C.

Team building activities

D.

Integrated Change Control

Buy Now
Questions 67

Which stakeholder approves a project ' s result?

Options:

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Buy Now
Questions 68

Which of the following is a tool and technique for Estimate Activity Durations?

Options:

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Buy Now
Questions 69

A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

Which of the following project delivery approaches should be recommended?

Options:

A.

Adaptive

B.

Hybrid

C.

Extreme

D.

Traditional

Buy Now
Questions 70

Administer Procurements is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Closing

Buy Now
Questions 71

During which process does the project team receive bids and proposals?

Options:

A.

Conduct Procurements

B.

Plan Procurements

C.

Estimate Costs

D.

Control Budget

Buy Now
Questions 72

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Buy Now
Questions 73

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

Options:

A.

Project sponsor

B.

Project manager

C.

Person responsible for project scheduling

D.

Person who is most familiar with the task

Buy Now
Questions 74

What process is performed periodically throughout the project as needed?

Options:

A.

Plan Risk Management

B.

Plan Communications Management

C.

Plan Resource Management

D.

Plan Cost Management

Buy Now
Questions 75

A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk. What should the team do next to deliver this project?

Options:

A.

Stop working on the project completely, even if the team can continue working on the tasks with the identified risk.

B.

Accept the project delay and add the risk to the lessons learned document for the next project.

C.

Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.

D.

Reprioritize the work based on the increased visibility of the current risks.

Buy Now
Questions 76

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

Options:

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Buy Now
Questions 77

An input used in developing the communications management plan is:

Options:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Buy Now
Questions 78

A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints.

Which elements are included in the DSDM framework?

Options:

A.

Time, integration, cost, and deliverables

B.

Schedule, risk, integration, and features

C.

Cost, time, quality, and functionality

D.

Cost, requirements, schedule, and outputs

Buy Now
Questions 79

Inputs to the Plan Risk Management process include the:

Options:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Buy Now
Questions 80

A newly developed project team is working together, building trust and adjusting its work habits to support the team What stage of the Tuckman ladder does this describe?

Options:

A.

Forming

B.

Norming

C.

Storming

D.

Performing

Buy Now
Questions 81

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Buy Now
Questions 82

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

Options:

A.

Close Procurements.

B.

Control Procurements.

C.

Plan Procurements.

D.

Conduct Procurements.

Buy Now
Questions 83

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 84

Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

Options:

A.

Cause and effect diagram

B.

Control charts

C.

Pareto chart

D.

Histogram

Buy Now
Questions 85

The Perform Integrated Change Control process occurs in which Process Group?

Options:

A.

Initiating

B.

Executing

C.

Monitoring and Controlling

D.

Planning

Buy Now
Questions 86

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Buy Now
Questions 87

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

Options:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Buy Now
Questions 88

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Buy Now
Questions 89

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

Options:

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (TandM)

D.

Cost Plus Incentive Fee Contract (CPIF)

Buy Now
Questions 90

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

Options:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Buy Now
Questions 91

What is an output of the plan resource management process

Options:

A.

Project charter

B.

Risk register

C.

Scope baseline

D.

Stakeholder register

Buy Now
Questions 92

What do top project managers do to maximize their sphere of influence within a project team?

Options:

A.

Consider management standards, economic factors, and sustainability strategies

B.

Contribute knowledge and expertise to others within the profession

C.

C Address political and strategic issues that impact the project ' s viability or quality

D.

D Demonstrate superior relationship and communication skills while displaying a positive attitude

Buy Now
Questions 93

Work performance information and cost forecasts are outputs of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 94

Which of the following tasks is related to perform the qualitative risk analysis process?

Options:

A.

Identify the project risks and assign a probability of occurrance

B.

Perform a sensitivity analysis to determine which risk has the most potential for impacting the project

C.

Analyze the effect of identified project risks as numerical data

D.

Prioritize each project risk and assign the probability of occurrence and impact for each one

Buy Now
Questions 95

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

Options:

A.

Determine Budget.

B.

Baseline Budget.

C.

Control Costs.

D.

Estimate Costs.

Buy Now
Questions 96

A tool and technique used during the Collect Requirements process is:

Options:

A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Buy Now
Questions 97

Which document in the project management plan can be updated in the Plan Procurement Management process?

Options:

A.

Budget estimates

B.

Risk matrix

C.

Requirements documentation

D.

Procurement documents

Buy Now
Questions 98

Portfolio Management is management of:

Options:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Buy Now
Questions 99

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Buy Now
Questions 100

A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.

Which technique is the team using?

Options:

A.

Checklists

B.

Interview

C.

Focus group

D.

Brainstorming

Buy Now
Questions 101

What describes the relationship between projects, programs, and portfolios?

Options:

A.

Portfolio management focuses on doing the " right " programs and projects.

B.

Project management focuses on doing the " right " programs and portfolios.

C.

Program management focuses on doing the " specific " portfolios and projects.

D.

Portfolio management focuses on doing the ' ' specific’’ programs and projects.

Buy Now
Questions 102

The completion of the project scope is measured against the:

Options:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Buy Now
Questions 103

What is an emerging practice in stakeholder engagement?

Options:

A.

Confirming that all identified stakeholders are engaged and actually affected by the work

B.

Assuring that team leadership is primarily involved in stakeholder engagement

C.

Ensuring that stakeholders do not change after stakeholder identification

D.

Ensuring that stakeholders most affected by the work are involved as collaborative team partners

Buy Now
Questions 104

Which type of estimating is used to improve the accuracy of an activity ' s duration?

Options:

A.

Analogous

B.

Parametric

C.

Three-point

D.

What-if scenario analysis

Buy Now
Questions 105

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

Options:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

Buy Now
Questions 106

A stakeholder asked the project manager to add an additional feature to the project scope. The project manager is unsure whether the project budget will allow this additional scope.

What component of the project management plan should the project manager reference to determine whether the budget will allow a new feature to be added?

Options:

A.

Risk management plan

B.

Cost estimate

C.

Risk register

D.

Cost management plan

Buy Now
Questions 107

Which roles does the project manager resemble best?

Options:

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

Buy Now
Questions 108

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

Options:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Buy Now
Questions 109

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Options:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Buy Now
Questions 110

What organizational process asset (OPA) can impact a project?

Options:

A.

Marketplace conditions

B.

Preapproved supplier lists

C.

Physical environmental elements

D.

Legal restrictions

Buy Now
Questions 111

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Buy Now
Questions 112

Which of the following is a tool and technique used in the Develop Schedule process?

Options:

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Buy Now
Questions 113

What is the primary purpose of Project Scope Management?

Options:

A.

Determining and managing stakeholder needs

B.

Contorting the status of the product scope and managing changes to its be seine

C.

Defining and controlling what is and is not included in the project

D.

Differentiating between the product scope and project scope

Buy Now
Questions 114

Which process is engaged when a proiect learn inember makes a change to project budget with the project manager ' s approval?

Options:

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 115

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Buy Now
Questions 116

Which Knowledge Areas include processes from the Closing Process Group?

Options:

A.

Project Quality Management and Project Time Management

B.

Project Scope Management and Project Risk Management

C.

Project Stakeholder Management and Project Cost Management

D.

Project Integration Management and Project Procurement Management

Buy Now
Questions 117

At what stages of project should the identify Stakeholder process be performed?

Options:

A.

When beginning each phase of the project

B.

At the beginning of the project only

C.

Only when the project manager is concerned about stakeholder satisfaction

D.

When the project charter is produced, at the beginning of each phase, and when significant changes occur

Buy Now
Questions 118

What is the purpose of the project schedule management.

Options:

A.

Estimates specific time and the deadline when the products, services and results will be delivered.

B.

Determines in details the resources and time that each task will require to be done

C.

Represents how and when the project will deliver the results defined in the project scope.

D.

It provides the relationships among the project activities and their risks.

Buy Now
Questions 119

An input to the Plan Stakeholder Management process is:

Options:

A.

The project charter.

B.

The stakeholder analysis.

C.

A communication management plan.

D.

A stakeholder register.

Buy Now
Questions 120

Which is an aspect of the requirements management plan?

Options:

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

Buy Now
Questions 121

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One

B.

Five

C.

Six

D.

Seven

Buy Now
Questions 122

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Buy Now
Questions 123

Which of the following describes the similarities of the process groups and project life cycle?

Options:

A.

The life cycle involves three project management process groups.

B.

Both provide a basic framework to manage the project.

C.

Each project must have a life cycle and all processes in the five process groups.

D.

The project life cycle is managed by executing the processes within the five process groups.

Buy Now
Questions 124

When can we say that a project is completed?

Options:

A.

When the planned time duration is completed

B.

When the project objectives have been reached

C.

When the project manager has left the team

D.

When the project team decides to stop the work on the project

Buy Now
Questions 125

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Buy Now
Questions 126

A project charter is an output of which Process Group?

Options:

A.

Executing

B.

Planning

C.

Initiating

D.

Closing

Buy Now
Questions 127

What process is included in Project Integration Management?

Options:

A.

Monitor and Control Project Work

B.

Control Scope

C.

Control Schedule

D.

Develop Team

Buy Now
Questions 128

What is purpose of using the building information model (BIM) in software tools in the construction field?

Options:

A.

Reduce significant amount of time and money

B.

Help manage risks in large projects

C.

Keep up with emerging trends

D.

Provide sellers with multiple sources for documents

Buy Now
Questions 129

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Buy Now
Questions 130

Scope, schedule, and cost parameters are integrated in the:

Options:

A.

Performance measurement baseline.

B.

Analysis of project forecasts,

C.

Summary of changes approved in a period,

D.

Analysis of past performance.

Buy Now
Questions 131

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Buy Now
Questions 132

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Buy Now
Questions 133

Which are inputs for the Plan Quality Management process?

Options:

A.

Quality metrics, project documents, and financial performance

B.

Quality management plan, project documents, and quality metrics

C.

Project management plan, project documents, and organizational process assets

D.

Project management plan, quality metrics. and project documents

Buy Now
Questions 134

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

Options:

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Buy Now
Questions 135

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

Options:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

Buy Now
Questions 136

A business analyst is evaluating solutions against the expected results and logging defects along the way. The next task is to analyze the discrepancies prior to facilitating a go/no-go decision.

Which technique should be used as a starting point to uncover problem areas?

Options:

A.

Elicitation

B.

Opportunity analysis

C.

Cost-benefit analysis

D.

Feasibility analysis

Buy Now
Questions 137

Which of the following sets are inputs to the Collect Requirements process?

Options:

A.

Project charter and requirements documentation

B.

Project charter and business documents

C.

Project charter and stakeholder requirements

D.

Business documents and requirements traceability matrix

Buy Now
Questions 138

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

Options:

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Buy Now
Questions 139

The organization ' s perceived balance between risk taking and risk avoidance is reflected in the risk:

Options:

A.

Responses

B.

Appetite

C.

Tolerance

D.

Attitude

Buy Now
Questions 140

During project execution, a team member has identified and then analyzed an opportunity that

will yield a net saving of 10% and reduce time in the schedule by 20%

Which strategy should the project manager adopt to accommodate this opportunity?

Options:

A.

Escalate to upper management to build awareness of the opportunity.

B.

Exploit the opportunity immediately, since the cost saving makes it worthwhile.

C.

Transfer the opportunity to a partner and start a partner contract.

D.

Create a trail of the opportunity before full adoption, because of the risk associated.

Buy Now
Questions 141

An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?

Options:

A.

Project charter

B.

Product roadmap

C.

Project management plan

D.

Product requirements

Buy Now
Questions 142

A project manager is creating a project charter to provide a direct link between the project and the organization ' s strategic objectives. What must be considered when creating this document?

Options:

A.

High-level requirements and the project team

B.

Key stakeholder list and contingency reserve

C.

Detailed milestone schedule and project objectives

D.

Project purpose and high-level project description

Buy Now
Questions 143

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

Options:

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Buy Now
Questions 144

Which Control Quality tool is also known as an arrow diagram?

Options:

A.

Matrix diagram

B.

Affinity diagram

C.

Tree diagram

D.

Activity network diagram

Buy Now
Questions 145

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Buy Now
Questions 146

Which tool or technique is used in the Plan Scope Management process?

Options:

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

Buy Now
Questions 147

The zero duration of milestones in project planning occurs because milestones:

Options:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Buy Now
Questions 148

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Buy Now
Questions 149

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?

Options:

A.

Activity level

B.

Deliverable level

C.

Task level

D.

Work package level

Buy Now
Questions 150

The project management processes presented in the PMBOK Guide® should:

Options:

A.

always be applied uniformly.

B.

be selected as appropriate by the sponsor.

C.

be selected as appropriate by the project team.

D.

be applied based on ISO guidelines.

Buy Now
Questions 151

A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Closes Project or Phase

D.

Perform itegrated Change Control

Buy Now
Questions 152

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Buy Now
Questions 153

Which of the following investigates the likelihood that each specific risk will occur?

Options:

A.

Risk register

B.

Risk audits

C.

Risk urgency assessment

D.

Risk probability and impact assessment

Buy Now
Questions 154

Which set of tools and techniques is useful for estimating activity durations for the project schedule?

Options:

A.

Brainstorming, Monte Carlo simulation, analogous estimation

B.

Three-point estimation, resources leveling, iteration burndown chart

C.

Milestone charts, parametric estimation, schedule baseline

D.

Parametric estimation, three-point estimation, meetings

Buy Now
Questions 155

To which knowledge area does the Collect Requirements process belong?

Options:

A.

Quality Management

B.

Scope Management

C.

Cost Management

D.

Integration Management

Buy Now
Questions 156

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 157

A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?

Options:

A.

Life cycle approaches

B.

Resource availability

C.

Project dimensions

D.

Technology support

Buy Now
Questions 158

Recently, the government published a new tax law giving companies one year to implement the changes. A project was initiated to change the accounting system. Which delivery approach is most suitable in this context?

Options:

A.

Predictive, because of the high risk that the company can be fined.

B.

Predictive, because the requirements are clearly defined up-front.

C.

Adaptive, because the government will provide constant feedback.

D.

Adaptive, because the changes have never been implemented before.

Buy Now
Questions 159

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

Options:

A.

Risk, resource, and communications management plans

B.

Scope, quality, and resource management plans

C.

Procurement, integration, and risk management plans

D.

Communications, schedule, and cost management plans

Buy Now
Questions 160

Who defines the scope of the product

Options:

A.

The client

B.

The project manager

C.

The team

D.

The program manager

Buy Now
Questions 161

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.

Buy Now
Questions 162

Which of the following is part of the project sponsor ' s responsibility?

Options:

A.

Monitoring the business value

B.

Advocating the business value

C.

Tracking the business value

D.

Auditing the business value

Buy Now
Questions 163

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Options:

A.

Organizational process updates

B.

Quality metrics

C.

Change requests

D.

Quality control measurements

Buy Now
Questions 164

What benefit does the Manage Stakeholder Engagement process offer?

Options:

A.

Allows the project manager to increase support and minimize resistance from stakeholders

B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes

C.

Provides an actionable plan to interact effectively with stakeholders

D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Buy Now
Questions 165

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Buy Now
Questions 166

Which of the following set of items belongs to the communications management plan?

Options:

A.

Escalation processes and meeting management

B.

Project schedule and glossary of common terminology

C.

Escalation processes and stakeholder communication requirements

D.

Interactive communication model and information to be communicated

Buy Now
Questions 167

Which action should a project manager take to ensure that the project management plan is effective and current?

Options:

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Buy Now
Questions 168

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

Options:

A.

Communication models.

B.

Stakeholder participation.

C.

Expert judgment

D.

Enterprise environmental factors.

Buy Now
Questions 169

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Buy Now
Questions 170

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

Options:

A.

Adaptive

B.

Predictive

C.

Incremental

D.

Iterative

Buy Now
Questions 171

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

Options:

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Buy Now
Questions 172

All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?

Options:

A.

Set up a meeting with the sponsor.

B.

Set up a go/no-go meeting.

C.

Wait for the next sprint.

D.

Deliver the product.

Buy Now
Questions 173

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03

B.

0.06

C.

0.10

D.

0.50

Buy Now
Questions 174

In which of the risk management processes is the processes is the project charter used as an input?

Options:

A.

Palm Risk Responses

B.

Implement Risk Responses

C.

Plan Risk Management

D.

Perform Quantitative Risk Responses

Buy Now
Questions 175

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

Options:

A.

Escalate this issue to the project management office (PMO).

B.

Escalate this issue to the chief financial officer (CFO).

C.

Escalate this issue to the procurement team.

D.

Escalate this issue to the project sponsor.

Buy Now
Questions 176

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?

Options:

A.

Predictive

B.

Hybrid

C.

Kanban

D.

Adaptive

Buy Now
Questions 177

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

Options:

A.

Informal

B.

Unofficial

C.

Formal

D.

Hierarchical

Buy Now
Questions 178

Which statement describes the Monitor Communications process?

Options:

A.

Evaluates the differences between the communications management plan and the reality of communications in a project

B.

Ensures that the information needs of the project and the stakeholders are met

C.

Ensures that project information is created, collected, and distributed in a timely and appropriate manner

D.

Develops an appropriate approach and plan for communication of project activities

Buy Now
Questions 179

An output of the Develop Project Team process is:

Options:

A.

change requests

B.

team performance assessments

C.

project staff assignments

D.

project documents updates

Buy Now
Questions 180

What are the identified risks for doing excessive decomposition in a WBS?

Options:

A.

Insufficient project funding and disqualification of sellers

B.

Insufficient project funding and ineffective use of resources

C.

Disqualification of sellers and non-productive management efforts

D.

Non-productive management effort and inefficient use of resources

Buy Now
Questions 181

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

Options:

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Buy Now
Questions 182

What is the Project Schedule Management practice used to deliver incremental value to the customer ' ?

Options:

A.

Resource optimization

B.

Iterative scheduling with a backlog

C.

On-demand scheduling

D.

Critical path method

Buy Now
Questions 183

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Buy Now
Questions 184

Project managers plan a key role performing integration on the project what are the three different levels of integration?

Options:

A.

Process, cognitive

B.

Complexity, understand and change

C.

Interact, insight and leadership

D.

Communication, knowledge and value

Buy Now
Questions 185

The probability and impact matrix is primarily used to:

Options:

A.

Quantify risk issues for trends during a quality audit.

B.

Develop a risk register for risk planning.

C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.

Buy Now
Questions 186

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure effective requirements elicitation. What should the business analyst do?

Options:

A.

Ask the project coordinator to facilitate some of the workshops.

B.

Invite both internal and external stakeholders to the workshops.

C.

Engage a consultant that is familiar with the community needs.

D.

Organize a workshop with the sponsor and major stakeholders.

Buy Now
Questions 187

What is a characteristic of the relationship among projects, programs, and portfolios?

Options:

A.

A portfolio is a group of programs, and a program is a large project

B.

Portfolios often engage with the same stakeholders as the programs and projects in the portfolio.

C.

Programs focus on the internal interdependencies within each project in a portfolio

D.

Portfolios focus on program results and project deliveries

Buy Now
Questions 188

In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

Options:

A.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.

B.

Make sure proper testing gets completed to minimize the risk highlighted.

C.

Add this risk to the lessons learned register on project completion.

D.

Add the stakeholder to the stakeholder register and add the risk to the risk register.

Buy Now
Questions 189

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Buy Now
Questions 190

The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?

Options:

A.

Team values, team agreements, and conflict resolution process

B.

Conflict resolution process, communication guidelines, and meeting schedules

C.

Team roles and responsibilities, team management, and training plan

D.

Resource requirements, resource assignments, and team performance assessments

Buy Now
Questions 191

A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?

Options:

A.

A diagram in which resource optimization has been applied.

B.

A diagram in which the critical path method has been applied.

C.

A diagram in which a predefined series of activities has been organized.

D.

A diagram which shows a combination of resource and time optimization.

Buy Now
Questions 192

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Buy Now
Questions 193

Which tool or technique is used to develop the human resource management plan?

Options:

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Buy Now
Questions 194

Match the method for categorizing stakeholders with its corresponding description

CAPM Question 194

Options:

Buy Now
Questions 195

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Buy Now
Questions 196

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

Options:

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Buy Now
Questions 197

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

Options:

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Buy Now
Questions 198

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

Options:

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Buy Now
Questions 199

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Buy Now
Questions 200

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

Options:

A.

triangular distribution

B.

tornado diagram

C.

beta distribution

D.

fishbone diagram

Buy Now
Questions 201

High-level project risks are included in which document?

Options:

A.

Business case

B.

Risk breakdown structure

C.

Project charter

D.

Risk register

Buy Now
Questions 202

A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity ' s prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

How should the project manager proceed?

Options:

A.

Perform Integrated Change Control.

B.

Conduct a risk assessment with the team.

C.

Update the schedule to include compliance.

D.

Manage Stakeholder Engagement.

Buy Now
Questions 203

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client ' s overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Buy Now
Questions 204

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

Buy Now
Questions 205

During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project ' s components. What should be included in the WBS?

Options:

A.

Activity dependencies

B.

Work package risks

C.

Description of work

D.

Resource estimates

Buy Now
Questions 206

Inputs to the Plan Schedule Management process include:

Options:

A.

Organizational process assets and the project charter,

B.

Enterprise environmental factors and schedule tools.

C.

Time tables and Pareto diagrams.

D.

Activity attributes and resource calendars.

Buy Now
Questions 207

Which of the following is an input to the Direct and Manage Project Execution process?

Options:

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Buy Now
Questions 208

A project manager held a meeting and listed all team members ' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

Options:

A.

Focus groups

B.

Interviews

C.

Brainstorming

D.

Delphi technique

Buy Now
Questions 209

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

Options:

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

Buy Now
Questions 210

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?

Options:

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

Buy Now
Questions 211

During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.

What is this an example of?

Options:

A.

Monitoring the traceability matrix

B.

Managing the scope

C.

Maintaining the product backlog

D.

Managing the cost benefit

Buy Now
Questions 212

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Buy Now
Questions 213

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?

Options:

A.

Expand the scope of the project.

B.

Schedule the tasks in sequence.

C.

Increase quality review cycles.

D.

Schedule the tasks in parallel.

Buy Now
Questions 214

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Options:

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Buy Now
Questions 215

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Buy Now
Questions 216

What is the primary benefit of meeting quality requirements?

Options:

A.

Quality metrics

B.

Less rework

C.

Quality control measurements

D.

Benchmarking

Buy Now
Questions 217

Which process involves developing an approximation of the monetary resources needed to complete project activities?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Buy Now
Questions 218

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited

B.

Low to moderate

C.

Moderate to high

D.

High to almost total

Buy Now
Questions 219

A project manager is performing the procurement management process with three vendors The project team is reviewing the requests for proposal (RFPs).

What type of procurement document is the RFP?

Options:

A.

Bid document

B.

Statement of work (SOW)

C.

Source selection criteria

D.

Independent cost estimate

Buy Now
Questions 220

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 221

The following chart contains information about the tasks in a project.

CAPM Question 221

Based on the chart, what is the schedulevariance (SV) for Task 8?

Options:

A.

-2,000

B.

-1,000

C.

1,000

D.

2,000

Buy Now
Questions 222

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

Options:

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

Buy Now
Questions 223

Which of the following documents ate created as part of Project Integration Management?

Options:

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Buy Now
Questions 224

A project manager needs to request outside support......manager need to create

A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?

Options:

A.

Time and material (TandM)

B.

Cost plus fixed fee (CPFF)

C.

Fixed price

D.

Cost plus award fee (CPAF)

Buy Now
Questions 225

A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?

Options:

A.

Project Resource Management

B.

Project Quality Management

C.

Project Schedule Management

D.

Project integration Management

Buy Now
Questions 226

Which is the tool or technique that is used to obtain the list of activities from the work packages?

Options:

A.

Data analysis

B.

Leads and lags

C.

Precedence diagramming method

D.

Decomposition

Buy Now
Questions 227

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

Options:

A.

Use a lightweight cost estimation due to the nature of angile projects.

B.

Use a detailed cost estimation for agile projects.

C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.

Use a detailed work breakdown structure (WBS) to get cost estimation.

Buy Now
Questions 228

What tools or techniques can be used in all cost management processes ' ?

Options:

A.

Decision making and expert judgment

B.

Expert judgment and data analysis

C.

Data analysis and meetings

D.

Meetings and cost aggregation

Buy Now
Questions 229

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Buy Now
Questions 230

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

Options:

A.

Methodology

B.

Risk category

C.

Risk attitude

D.

Assumption analysis

Buy Now
Questions 231

An example of a group decision-ma king technique is:

Options:

A.

Nominal group technique.

B.

Majority.

C.

Affinity diagram.

D.

Multi-criteria decision analysis.

Buy Now
Questions 232

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:

A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

Buy Now
Questions 233

The following chart contains information about the tasks in a project.

CAPM Question 233

Based on the chart, what is the cost performance index (CPI) for Task 2?

Options:

A.

0.8

B.

1

C.

1.25

D.

1.8

Buy Now
Questions 234

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Buy Now
Questions 235

A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

Options:

A.

Elicit product requirements.

B.

Verify product functionality.

C.

Manage the project schedule.

D.

Allocate project resources.

Buy Now
Questions 236

In the Develop Project Team process, which of the following is identified as a critical factor for a project ' s success?

Options:

A.

Team meetings

B.

Subcontracting teams

C.

Virtual teams

D.

Teamwork

Buy Now
Questions 237

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller ' s performance. The most appropriate agreement with the supplier is:

Options:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Buy Now
Questions 238

The correct equation for schedule variance (SV) is earned value:

Options:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Buy Now
Questions 239

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Buy Now
Questions 240

How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

Options:

A.

Look at the quality metrics.

B.

Validate the scope.

C.

Review the quality checklist.

D.

Conduct a quality audit.

Buy Now
Questions 241

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

Options:

A.

Control Scope

B.

Collect Requirements

C.

Create WBS

D.

Define Scope

Buy Now
Questions 242

In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

Options:

A.

The organization

B.

The project

C.

The industry

D.

The product

Buy Now
Questions 243

An input of the Create WBS process is:

Options:

A.

requirements documentation.

B.

scope baseline.

C.

project charter.

D.

validated deliverables.

Buy Now
Questions 244

What is a tool or technique used in the Control Quality process?

Options:

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

Buy Now
Questions 245

A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?

Options:

A.

Business analyst, project manager, and sponsor

B.

Business analyst, project manager, and stakeholders

C.

Business analyst and project manager

D.

Only the business analyst

Buy Now
Questions 246

What can a project manager review to understand the status of a project?

Options:

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Buy Now
Questions 247

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Buy Now
Questions 248

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

Options:

A.

To the project management plan.

B.

To the risk register.

C.

In the scope verification processes.

D.

And their impact to the project in terms of time, cost, and risk.

Buy Now
Questions 249

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Buy Now
Questions 250

In an interactive communication model, how is the sender ensured that the message was understood by the receiver?

Options:

A.

The receiver decodes the message

B.

The receiver responds to the message with feedback.

C.

The receiver transmits the message

D.

The receiver acknowledges their receipt of the message

Buy Now
Questions 251

What should a project manager use to determine how much money is needed to complete a project?

Options:

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Buy Now
Questions 252

The process of prioritizing risks for further analysis or action is known as:

Options:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

Buy Now
Questions 253

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.

What are the four elements of a RACI chart?

Options:

A.

Recommend, approve, coordinate, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, accountable, consult, and inform

D.

Responsible, accountable, coordinate, and inform

Buy Now
Questions 254

Which of the following is an example of an internal factor that influences the outcome of the project?

Options:

A.

Legal restrictions

B.

Financial considerations

C.

Commercial database

D.

Geographic distribution of facilities

Buy Now
Questions 255

During which process group is the quality policy determined?

Options:

A.

Initiating

B.

Executing

C.

Planning

D.

Controlling

Buy Now
Questions 256

What tools or techniques are necessary to create the project management plan?

Options:

A.

Meetings and data analysis

B.

Expert judgment and data gathering

C.

Interpersonal skills and change control

D.

Data analysis and expert judgment

Buy Now
Questions 257

Which of the following are outputs of define scope process in project scope management

Options:

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project Scope statement and project documents updates

D.

Scope baseline and project documents updates

Buy Now
Questions 258

The purpose of developing a project scope management plan is to:

Options:

A.

Manage the timely completion of the project.

B.

Ensure that the project includes all of the work required.

C.

Make sure the project will satisfy the needs for which it was begun.

D.

Reduce the risk of negative events in the project.

Buy Now
Questions 259

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

Options:

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Buy Now
Questions 260

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Buy Now
Questions 261

Change requests are processed for review and disposition according to which process?

Options:

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Buy Now
Questions 262

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

Options:

A.

Define Activities

B.

Direct and Manage Project Work

C.

Develop Project Management Plan

D.

Develop Project Charter

Buy Now
Questions 263

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

Options:

A.

Risk burnup and control chart

B.

Customer satisfaction index and workload

C.

Average burndown and velocity

D.

Average velocity and cycle time

Buy Now
Questions 264

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Buy Now
Questions 265

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

Options:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Buy Now
Questions 266

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

Options:

A.

risk management plan

B.

human resource management plan

C.

scope management plan

D.

procurement management plan

Buy Now
Questions 267

Perform Integrated Change Control is the process of:

Options:

A.

Reviewing, approving, and managing all change requests

B.

Facilitating change management, manuals, or automation tools

C.

Comparing actual results with planned results in order to expand or change a project

D.

Documenting changes according to the change control system by the change control board

Buy Now
Questions 268

Plan Communications Management develops an approach and plan for project communications based on stakeholders ' needs and requirements and:

Options:

A.

Available organizational assets

B.

Project staff assignments

C.

Interpersonal skills

D.

Enterprise environmental factors

Buy Now
Questions 269

During which process of Project Cost Management does a project manager produce the cost baseline?

Options:

A.

Estimate Costs

B.

Control Schedule

C.

Determine Budget

D.

Develop Project Charter

Buy Now
Questions 270

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?

Options:

A.

Withdraw/avoid

B.

Smooth /accommodate

C.

Collaborate/problem solve

D.

Compromise/ reconcile

Buy Now
Questions 271

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

Options:

A.

BAC

B.

EAC

C.

ETC

D.

WBS

Buy Now
Questions 272

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Options:

A.

Portfolio

B.

Process

C.

Project

D.

Program

Buy Now
Questions 273

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

Options:

A.

The influence of the stakeholders increases, the cost of changes increases.

B.

The influence of the stakeholders decreases, the cost of changes increases.

C.

The influence of the stakeholders increases, the cost of changes decreases.

D.

The influence of the stakeholders decreases, the cost of changes decreases.

Buy Now
Questions 274

Which defines the portion of work included in a contract for items being purchased or acquired?

Options:

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Buy Now
Questions 275

The Define Scope process is in which of the following Process Groups?

Options:

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Buy Now
Questions 276

What can a requirements traceability matrix enable regardless of the project methodology being used?

Options:

A.

Creation of a solid business case

B.

Investigation of the viability of a new product

C.

Identification of missing and superfluous requirements

D.

Evaluation of solution and system performance

Buy Now
Questions 277

During a virtual kick-off session, the project sponsor highlights the significance of the project to the company. What message should be conveyed to the team in this meeting?

Options:

A.

Bonuses based on accomplishment criteria

B.

New working contract with more benefits

C.

Promotion opportunities with this project

D.

Assignment of key roles and responsibilities

Buy Now
Questions 278

A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

Options:

A.

Early requirements gathering

B.

Feedback analysis

C.

Progressive elaboration

D.

Requirements documentation

Buy Now
Questions 279

The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?

Options:

A.

Monitor Communications

B.

Plan Communications Management

C.

Manage Communications

D.

Manage Stakeholder Engagement

Buy Now
Questions 280

Which organizational process asset can make an impact on the outcome of a project?

Options:

A.

Political climate

B.

Leadership style

C.

Financial data repository

D.

Organizational structure types

Buy Now
Questions 281

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

Options:

A.

A risk urgency assessment.

B.

The scope baseline.

C.

Work performance information.

D.

Procurement audits.

Buy Now
Questions 282

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

Options:

A.

2.0

B.

45

C.

0.5

D.

15

Buy Now
Questions 283

The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?

Options:

A.

Organizational structure type, Key stakeholders, and protect funds

B.

Rules. policies and norms

C.

Project management software, resources availability and risk checklist

D.

Governance elements, team policies, and organizational goals

Buy Now
Questions 284

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Questions 285

What is a tailoring consideration for Project Scope Management ' ?

Options:

A.

Life cycle approach

B.

Continuous improvement

C.

Validation and control

D.

Project complexity

Buy Now
Questions 286

The product scope description is used to:

Options:

A.

Gain stakeholders ' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Buy Now
Questions 287

The process for performing variance analysis may vary, depending on:

Options:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Buy Now
Questions 288

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take to account for risk management n this environment’

Options:

A.

Occasionally identify evaluate, and classify risks

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Buy Now
Questions 289

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Buy Now
Questions 290

What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?

Options:

A.

Project Management

B.

Program Management

C.

Portfolio Management

D.

Operations Management

Buy Now
Questions 291

Which is an enterprise environmental factor?

Options:

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

Buy Now
Questions 292

Which risk response strategy is common for both positive and negative risks?

Options:

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Buy Now
Questions 293

What is the key benefit of the Monitor Stakeholder Engagement process?

Options:

A.

Ensures that the informational needs of the project and its stakeholders are met through implementation and the development of artifacts

B.

Ensures that the project includes all the work required and only the work required—to complete the project successfully

C.

Increases the probability and/or impact of positive risks, and decreases the probability and/or Impact of negative risks or issues

D.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves

Buy Now
Questions 294

What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?

Options:

A.

Sensitivity analysis

B.

Simulation

C.

Decision tree analysis

D.

Influence diagram

Buy Now
Questions 295

What specific quality considerations should be examined while completing Quality Management plan?

Options:

A.

Risk registerB Stakeholder engagement

B.

Continuous improvement

C.

Standards and regulatory compliance

Buy Now
Questions 296

The project manager is looking at a precedence diagram.... the duration of this task?

The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

What is the outcome of the duration of this task ' ?

Options:

A.

The task will be completed on time.

B.

The task will not be completed on time.

C.

Activity A is not a critical path task

D.

The precedence diagram cannot be used to provide answers for duration calculations

Buy Now
Questions 297

Due to organizational changes, a new product owner joins a project The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

What process should the project manager review with the product owner?

Options:

A.

Acquire Resources

B.

Plan Resource Management

C.

Estimate Activity Resources

D.

Control Resources

Buy Now
Questions 298

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

Options:

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 299

What does ’verified’ in verified deliverable represent?

Options:

A.

The correctness of a deliverable

B.

The completeness of a deliverable

C.

The deliverable requirements

D.

The customer acceptance of a deliverable

Buy Now
Questions 300

What is the difference between verified and accepted deliverables?

Options:

A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.

B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.

C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.

D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.

Buy Now
Questions 301

The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?

Options:

A.

Technical project management skills

B.

Time management skills

C.

Strategic and business management skills

D.

Leadership skills

Buy Now
Questions 302

According to the PMI Talent Triangle. leadership skills relate to the ability to:

Options:

A.

understand the high-level overview of the organization

B.

tailor traditional and agile tools for the project

C.

work with stakeholders to develop an appropriate project delivery

D.

guide, motivate, and direct a team to reach project goals

Buy Now
Questions 303

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

Options:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Buy Now
Questions 304

Where are key project deliverables documented?

Options:

A.

Project management plan

B.

Requirements traceability matrix

C.

User acceptance criteria

D.

Work breakdown structure (WBS)

Buy Now
Questions 305

The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager ' s disposal?

Options:

A.

Resource leveling and fast tracking

B.

Fast tracking and crashing

C.

Crashing and applying leads and lags

D.

Scheduling tools and applying leads and lags

Buy Now
Questions 306

The following is a network diagram for a project.

The free float for Activity H is how many days?

Options:

A.

4

B.

5

C.

10

D.

11

Buy Now
Questions 307

The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?

Options:

A.

Project charter and stakeholder engagement plan

B.

Risk management plan and stakeholder engagement plan

C.

Communications management plan and stakeholder engagement plan

D.

Project charter and communications management plan

Buy Now
Questions 308

Which baselines make up the performance measurement baseline?

Options:

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Buy Now
Questions 309

A tool and technique used during the Define Scope process is:

Options:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

Buy Now
Questions 310

An input to the Collect Requirements process is the:

Options:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Buy Now
Questions 311

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

Options:

A.

Discuss the processes and deliverables needed to meet the project objectives with the team.

B.

Integrate hybrid approach processes and deliverables to meet the short delivery time line.

C.

Identify the processes and deliverables for only the current phase first.

D.

Follow organizational methodology and produce all required deliverables.

Buy Now
Questions 312

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Buy Now
Questions 313

A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?

Options:

A.

Resource management plan and lessons learned register

B.

Resource management plan and cost baseline

C.

Resource management plan and procurement management plan

D.

Resource management plan and preassignment

Buy Now
Questions 314

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Buy Now
Questions 315

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

Options:

A.

Predictive

B.

Adaptive

C.

A mix

D.

Agile

Buy Now
Questions 316

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.

What should the business analyst do?

Options:

A.

Organize a workshop with the sponsor and major stakeholders.

B.

Engage a consultant that is familiar with the community needs.

C.

Ask the project coordinator to facilitate some of the workshops.

D.

Invite both internal and external stakeholders to the workshops.

Buy Now
Questions 317

A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?

Options:

A.

Extend an iteration review invite to the new stakeholder.

B.

Perform qualitative risk analysis.

C.

Engage with the new stakeholder.

D.

Allow team members to share project status reports.

Buy Now
Questions 318

Which activity involves ensuring that the composition of a projects configuration items is correct?

Options:

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Buy Now
Questions 319

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

Options:

A.

Control chart

B.

Flowchart

C.

Checksheet

D.

Pareto diagram

Buy Now
Questions 320

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Buy Now
Questions 321

The Verify Scope process is primarily concerned with:

Options:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

Buy Now
Questions 322

For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?

Options:

A.

3 days

B.

5 days

C.

7 daysD .10 days

Buy Now
Questions 323

A project team has missed a milestone.

Which response strategy should be implemented?

Options:

A.

Communications

B.

Stakeholder

C.

Contingent

D.

Risk

Buy Now
Questions 324

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Buy Now
Questions 325

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

Options:

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

Buy Now
Questions 326

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

Options:

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Buy Now
Questions 327

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Options:

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Buy Now
Questions 328

The review of a seller ' s progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

Options:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Buy Now
Questions 329

Which format can a network diagram take?

Options:

A.

Flow chart

B.

Control chart

C.

Affinity diagram

D.

Cause-and-effect diagram

Buy Now
Questions 330

What is the main purpose of Project Quality Management?

Options:

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Buy Now
Questions 331

Reserve analysis is a tool and technique used in which process?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Buy Now
Questions 332

What does leadership involve?

Options:

A.

Working with others through discussion or debate to guide them from one point to another

B.

Directing another person from one point to another using a known set of expected behaviors

C.

Working with a person using expert judgment to develop the technical deliverables

D.

Directing another person to develop the necessary expertise to establish technical deliverables

Buy Now
Questions 333

Which type of analysis would be used for the Plan Quality process?

Options:

A.

Schedule

B.

Checklist

C.

Assumption

D.

Cost-Benefit

Buy Now
Questions 334

The primary purpose of the stakeholder register is to:

Options:

A.

Record stakeholder issues on the project

B.

Maintain lessons learned earlier in the project

C.

Maintain a list of all project stakeholders

D.

Document change requests and their status

Buy Now
Questions 335

Which tools and techniques should a project manager use when estimating costs?

Options:

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

Buy Now
Questions 336

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Buy Now
Questions 337

Which Process Group includes the Manage Stakeholder Engagement process?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating

Buy Now
Questions 338

Which of the following Process Groups covers all nine Project Management Knowledge Areas?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Planning

D.

Initiating

Buy Now
Questions 339

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

Options:

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

Buy Now
Questions 340

Which enterprise environmental factors are considered during Estimate Costs?

Options:

A.

Market conditions and published commercial information

B.

Company structure and market conditions

C.

Commercial information and company structure

D.

Existing human resources and market conditions

Buy Now
Questions 341

A project manager needs information to finish their work on the project charter for a clinical trial.

Which procedure is used to obtain the requirements information?

Options:

A.

Forecasting

B.

Simulations

C.

Elicitation

D.

Quantitative analysis

Buy Now
Questions 342

A business manager wants to start a project to launch a new product. How should the manager initiate the project?

Options:

A.

Ask a small team to produce a prototype of the product before full-scale development.

B.

Assign a project manager to the project and ask them to document the project scope.

C.

Prepare a detailed business case to document project objectives and success criteria.

D.

Discuss the project requirements with the team for alternative products in the market.

Buy Now
Questions 343

What can a project1 manager review to understand the status of project?

Options:

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Buy Now
Questions 344

Which three of the following are key traits of a project leader? (Choose three)

Options:

A.

Rely on control.

B.

Focus on near-team goals.

C.

Convey trust and inspire trust in other team members.

D.

Challenge the status quo and do things differently.

E.

Focus on the horizon.

Buy Now
Questions 345

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

Options:

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Buy Now
Questions 346

Which tool is used to develop technical details within the project management plan?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Buy Now
Questions 347

The project manager needs to review the templates in use. The templates are part of the:

Options:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

Buy Now
Questions 348

Which of the following is a goal of the project charter?

Options:

A.

Detail requirements for the project tasks.

B.

Empower the project manager to manage the project.

C.

List all tasks the team should perform in the project.

D.

Develop a business case to support the project.

Buy Now
Questions 349

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

Options:

A.

Authority

B.

Role

C.

Competency

D.

Responsibility

Buy Now
Questions 350

Analogous cost estimating relies on which of the following techniques?

Options:

A.

Expert judgment

B.

Project management software

C.

Vendor bid analysis

D.

Reserve analysis

Buy Now
Questions 351

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Close Project or Phase

D.

Perform Integrated Change Control

Buy Now
Questions 352

Which item is a formal proposal to modify any document, deliverable, or baseline?

Options:

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Buy Now
Questions 353

Lessons learned are created and project resources are released in which Process Group?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Buy Now
Questions 354

Which are required to create the schedule management plan?

Options:

A.

Scope baseline, work breakdown structure (WBS), estimated costs, and milestone list

B.

Resource management plan, organizational process assets, activity list, and business case

C.

Enterprise environmental factors, organizational process assets, project charter, and project management plan

D.

Activity list, project statement of work, project charter, and communications management plan

Buy Now
Questions 355

A new project manager is assigned to a high-visibility project. The project manager starts with the requirements analysis process. Who should the project manager onboard to assist with the requirements traceability matrix or analysis?

Options:

A.

Systems analyst

B.

Business analyst

C.

Project sponsor

D.

Technical consultant

Buy Now
Questions 356

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:

A.

Procurement statement of work

B.

Purchase order

C.

Source selection criteria

D.

Bidder conference

Buy Now
Questions 357

The following is a network diagram for a project.

CAPM Question 357

The free float for Activity E is how many days?

Options:

A.

2

B.

3

C.

5

D.

8

Buy Now
Questions 358

Which tool uses an algorithm based on historical data to calculate cost?

Options:

A.

Three-point estimating

B.

Parametric estimating

C.

Analogous estimating

D.

Relative estimating

Buy Now
Questions 359

In which Project Management Process Group is the project charter developed?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Buy Now
Questions 360

Variance and trend analysis is a tool and technique used in which process?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

Buy Now
Questions 361

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Buy Now
Questions 362

Which of the following is an output from Control Scope?

Options:

A.

Change requests

B.

Variance analysis

C.

Accepted deliverables

D.

Requirements documentation

Buy Now
Questions 363

Which action should the project manager take after the team finishes executing the scope?

Options:

A.

Verify the deliverables to ensure that they are correct and meet the customer ' s satisfaction.

B.

Accept all the deliverables and deliver them to the customer for final acceptance.

C.

Conduct a joint session with the customer, change the deliverables, and then request approval.

D.

Check that all change requests were implemented and release deliverables to the customer.

Buy Now
Questions 364

Which process in Project Time Management includes reserve analysis as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Buy Now
Questions 365

Who identifies project requirements in the early phase of the project?

Options:

A.

Business analyst, product team, and key stakeholders

B.

Project manager, business analyst, and key stakeholders

C.

Project manager, business analyst, and project sponsor

D.

Project sponsor, business analyst, and key stakeholders

Buy Now
Questions 366

What tool or technique can improve a products final characteristics?

Options:

A.

Design for X (DfX)

B.

Problem solving

C.

Process analysis

D.

Risk report

Buy Now
Questions 367

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Buy Now
Questions 368

The primary benefit of the Plan Schedule Management process is that it:

Options:

A.

provides guidance to identify time or schedule challenges within the project.

B.

tightly links processes to create a seamless project schedule.

C.

guides how the project schedule will be managed throughout the project.

D.

creates an overview of all activities broken down into manageable subsections.

Buy Now
Questions 369

When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?

Options:

A.

Iterative scheduling with backlog

B.

On-demand scheduling

C.

Life cycle scheduling with backlog

D.

Defining Iterative activities

Buy Now
Questions 370

A project manager has just consolidated the project risk management plan and sent it to the sponsor. The sponsor wants to reduce the likelihood of a specific risk.

Which approach should the project manager take?

Options:

A.

Escalate

B.

Mitigate

C.

Avoid

D.

Transfer

Buy Now
Questions 371

A quality management plan describes how the project and product scopes are managed in accordance with which of the following items?

Options:

A.

Product sponsor ' s expectation of organizational quality

B.

Historical quality standards and past organizational projects

C.

Organizational quality policies, stakeholder expectations, and historical data

D.

Organizational quality policies, standards, and methodologies

Buy Now
Questions 372

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

Options:

A.

Feedback analysis

B.

Stakeholder analysis

C.

Communication management plan

D.

Stakeholder management plan

Buy Now
Questions 373

What should be the frequency for meetings when transitioning from Scrum to Kanban?

Options:

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

Buy Now
Questions 374

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities. What are the four elements of a RACI chart?

Options:

A.

Recommend, accountable, consult, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, approve, coordinate, and inform

D.

Responsible, accountable, coordinate, and inform

Buy Now
Questions 375

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Options:

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Buy Now
Questions 376

Which document can help a project manager to leverage historical project information?

Options:

A.

Lessons learned register

B.

Schedule baseline

C.

Work performance data

D.

Deliverable acceptance forms

Buy Now
Questions 377

Which tool or technique is used in the Develop Project Management Plan process?

Options:

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Buy Now
Questions 378

What are the objectives of Initiation processes?

Options:

A.

Initiation processes are performed in order to develop the project charier and Identify stakeholders.

B.

Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.

C.

Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders ' goals.

D.

Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

Buy Now
Questions 379

The number of potential communication channels for a project with 5 stakeholders is:

Options:

A.

10.

B.

12.

C.

20.

D.

24.

Buy Now
Questions 380

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan

B.

Stakeholder register

C.

Risk log

D.

Communications management plan

Buy Now
Questions 381

Which of the following is TRUE about most project life cycles?

Options:

A.

Staffing level is highest at the start.

B.

The stakeholders ' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Buy Now
Questions 382

The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?

Options:

A.

Accepted deliverables

B.

planning packages

C.

Verified deliverables

D.

Work packages

Buy Now
Questions 383

Which of the following is an example of facit knowledge?

Options:

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Buy Now
Questions 384

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

Options:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Buy Now
Questions 385

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

Options:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Buy Now
Questions 386

Match each dimension of the communications management plan to its corresponding focus.

CAPM Question 386

Options:

Buy Now
Questions 387

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

Options:

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

Buy Now
Questions 388

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 389

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

Options:

A.

portfolio

B.

program

C.

selection

D.

sub portfolio

Buy Now
Questions 390

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

Options:

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.

Buy Now
Questions 391

An element of the project scope statement is:

Options:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Buy Now
Questions 392

Completion of the product scope is measured against the product:

Options:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Buy Now
Questions 393

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

Options:

A.

Least cost

B.

Qualifications only

C.

Sole source

D.

Fixed budget

Buy Now
Questions 394

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Buy Now
Questions 395

To ensure stakeholder satisfaction; identified stakeholder needs should all be

Options:

A.

Vetted

B.

Ranked from greatest to least

C.

Qualified

D.

Documented in the stakeholder engagement plan

Buy Now
Questions 396

Which of the following factors within a company cloud trigger the creation of a project?

Options:

A.

Need to lower production costs to remain competitive

B.

Need to submit a warranty claim for a faulty product

C.

Need to submit the monthly production report

D.

Need to define next month ' s production goals

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Apr 30, 2026
Questions: 1320

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now CAPM testing engine

PDF (Q&A)

$31.5  $104.99
buy now CAPM pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 01 May 2026