Summer Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Questions 4

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.

What type of risk response is this?

Options:

A.

Transfer

B.

Accept

C.

Mitigate

D.

Avoid 

Buy Now
Questions 5

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.

Implement the risk response strategies into the risk plan.

B.

Inform the sponsor that these risks should be added according to experience.

C.

Add the risks to the risk register and determine a contingency.

D.

Discuss and evaluate the identified risks with the project team.

Buy Now

PMI-RMP Report Card

Questions 6

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?

Options:

A.

Use the information for a risk workshop.

B.

Improve monitoring and controlling of activities.

C.

Document the issues in the lessons learned.

D.

Create an issue log to share with the team.

Buy Now
Questions 7

in a complex and critical project, a sponsor asks the risk manager to determine where the project ' s concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.

Which tool could the risk manager use to discover the project risk categories?

Options:

A.

Work breakdown structure (WBS)

B.

Affinity diagram

C.

Monte Carlo simul-ation

D.

Mind mapping

Buy Now
Questions 8

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.

How should the risk manager respond to this comment?

Options:

A.

The risk register must only be updated if a change is approved during the project.

B.

Agree on the condition that the risk register be updated if the project environment changes.

C.

Compromise by updating the risk register at the end of each phase only.

D.

Insist on continuous review and updating of the risk register during the project.

Buy Now
Questions 9

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

Options:

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

Buy Now
Questions 10

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

Options:

A.

Revisit this risk in the risk register and redefine the mitigation strategy.

B.

Activate the contingency plan to handle this risk during execution.

C.

Mark this new risk as an extremely high priority and inform all stakeholders.

D.

Ask the project sponsor for more budget to deal with this risk.

Buy Now
Questions 11

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project ' s risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

Options:

A.

Check to ensure that the risk is supported by a Monte Carlo simul-ation.

B.

Check to ensure that the risks are gathered using Delphi technique.

C.

Check for risk classification and that probability and impact are identified.

D.

Check to ensure that risk origin, triggering event, and ownership is identified.

E.

Check to ensure the risk meeting agenda and supporting documents are distributed.

Buy Now
Questions 12

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project ' s budget.

What should the project manager do next?

Options:

A.

Request a budget relief using the management reserve.

B.

Conduct a risk reassessment and reserve analysis.

C.

Review the consequences of potential changes.

D.

Coach stakeholders on risk identification practices.

Buy Now
Questions 13

The project team has correctly identified, assessed, and planned responses for a project ' s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Options:

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client

Buy Now
Questions 14

A project team is preparing a project plan for a government-funded project with multiple stakeholders, including government employees. The project sponsor requests the risk manager estimates the potential costs associated with delays that may arise from government employees, due to bureaucratic processes and other administrative factors.

How should the risk manager approach this task?

Options:

A.

Create a risk register to document all potential risks and estimated impacts, including delays due to government employees.

B.

Develop a risk response plan that includes specific mitigation strategies for government-related delays.

C.

Perform a quantitative risk analysis to determine the potential financial impact of government-related delays.

D.

Conduct a qualitative risk analysis to assess the likelihood and impact of potential delays.

Buy Now
Questions 15

A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project.

What should the risk manager do to prevent this from happening again?

Options:

A.

Document the risks and response actions in a clear manner.

B.

Communicate with the project manager on the topic.

C.

Assign owners who will be fully accountable to managing the risks.

D.

Define the response plans and take the lead in implementing them.

Buy Now
Questions 16

A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the

client ' s vendor, which apparently has been causing all of the issues.

What should the risk manager do first?

Options:

A.

Enhance risk identification.

B.

Review the contingency reserves.

C.

Create a risk response plan.

D.

Review the risk registry.

Buy Now
Questions 17

 

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

Options:

A.

Industry ' s standard procedures

B.

Current request for proposal (RFP)

C.

Company ' s historical financial reports

D.

IT infrastructure, networks, and data information

E.

Government laws and regulations 

Buy Now
Questions 18

Many customers using the global positioning system (GPS) of several automobile companies are complaining about errors due to a recent update. This update included a major technological change to mitigate emerging risks with software deployment. Upon investigation, the risk manager realized that this issue was identified as a high-risk item during risk analysis, which required secondary risk identification that was never completed.

What was missed in the risk management process that led to this incident?

Options:

A.

The identification of the business driver.

B.

The new technology ' s impact on existing controls

C.

The risk management strategy quality assurance.

D.

Project environmental factors

Buy Now
Questions 19

A project manager has requested the risk manager ' s support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.

What should the risk manager recommend?

Options:

A.

The new component should be purchased.

B.

Both options are losses to the project.

C.

Cost to expedite the execution is not worth the added risk.

D.

Perform a Monte Carlo simul-ation to quantify the impacts.

Buy Now
Questions 20

A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

Options:

A.

Develop and employ an Ishikawa diagram

B.

Analyze the assumptions and constraints

C.

Perform a review of project documents

D.

Create prompt lists for expert interviews

Buy Now
Questions 21

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

Options:

A.

Escalate the problem to the project sponsors.

B.

Execute the approved risk response plan.

C.

Negotiate with the supplier to resolve the problem.

D.

Assign a team member to update the issue leg.

Buy Now
Questions 22

There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.

What should the risk manager do to resolve this recurring situation?

Options:

A.

Review the stakeholders ' risk appetite.

B.

Revisit the risk thresholds and triggers.

C.

Update the risk response strategies.

D.

Provide coaching to the risk action owners. 

Buy Now
Questions 23

A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project.

How should the risk manager address this concern?

Options:

A.

Develop a risk breakdown structure {RBS) to identify possible risks.

B.

Develop a risk impact analysis to assess the consequences of possible risks

C.

Develop a probability and impact matrix to analyze possible risks.

D.

Create a risk register to capture and track possible risks. 

Buy Now
Questions 24

A risk manager is integrated into a team overseeing a crucial software development project. During the information gathering phase, the risk manager notices significant weaknesses in the maturity of the risk management process. The team needs to establish a more structured approach to managing risks, including the documentation of strategies, ownership structures, and details about the organization ' s project risk baseline.

What should the risk manager do?

Options:

A.

Prioritize the risk management plan.

B.

Arrange the risk mitigation plan.

C.

Create a risk action plan with risk owners.

D.

Prioritize the risk register.

Buy Now
Questions 25

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).

How many total story points is the entire initiative?

Options:

A.

72

B.

60

C.

40

D.

32

Buy Now
Questions 26

A financial service firm adheres to heavily regulated compliance legislation. During the firm ' s latest project, the Chief Financial Officer (CFO) and the Chief Information Officer (CIO) endorsed a risk-based approach. This approach ensured compliance with the legislative requirements for properly storing confidential employee salary information. The risk manager recorded this information in the project ' s risk management plan.

What is the organization ' s risk maturity level?

Options:

A.

No maturity

B.

Low maturity

C.

Medium maturity

D.

High maturity

Buy Now
Questions 27

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis. 

Buy Now
Questions 28

A project ' s design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

Options:

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

B.

Added generic construction risks to the risk register before construction began

C.

Reviewed the assumptions/exclusions register in the project charter

D.

Performed risk identification exercises for the full lifecycle of the project

Buy Now
Questions 29

A project manager is assigned to a new project and is told they need to develop the project ' s risk register. When should the project manager identify the project risks?

Options:

A.

Identify risks only at the project ' s midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Buy Now
Questions 30

A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.

What is an effect of adding the correlation to the model?

Options:

A.

Allows more risks to be included in the model.

B.

Reduces the project completion duration.

C.

Increases the standard deviation of the model.

D.

Increases the probability of correlated activities finishing on time.

Buy Now
Questions 31

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.

Advise the client that the project has exhausted contingency.

C.

Quantify the risk exposure that exceeds project contingency.

D.

Generate reports to assess and communicate the project risk level.

Buy Now
Questions 32

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.

Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Options:

A.

Work with the project team to conduct a decision tree analysis for each risk or set of related risks.

B.

Calculate the expected monetary value (EMV) of each risk and use these outputs to inform and defend project reserves.

C.

Conduct a Monte Carlo simul-ation to understand the probabilities of various risk outcomes.

D.

Use the risk breakdown structure (RBS) to calculate the total cost of mitigating all risks and ensure project reserves are adequate to cover this amount.

E.

Focus attention and resources on identified risks with the highest potential to impact the project.

Buy Now
Questions 33

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

Options:

A.

Product Manager

B.

Risk Action Owner

C.

Risk Owner

D.

Project Manager

Buy Now
Questions 34

A key hardware component failed during a large software implementation project, with significant organizational impact. The risk owner was on vacation and no one responded to this incident, thereby causing project delays.

What should have been done to prevent this situation?

Options:

A.

The project manager should have requested and mandated that no vacations be taken during critical implementation activities or until all implementation had been completed for the project.

B.

The risk manager should have anticipated this situation and planned for schedule buffers in the project schedule to accommodate the likelihood of failed hardware.

C.

The risk owner should have communicated with the project manager so that a designated stakeholder could have been assigned to accept accountability for implementing risk responses.

D.

The risk manager should have taken the responsibility of responding to this risk instead of relying on and waiting for the risk owner to return from vacation.

Buy Now
Questions 35

An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.

Ensure sufficient resources are available

B.

Revise the risk management plan

C.

Update the risk register

D.

Meet with the project ' s stakeholders

Buy Now
Questions 36

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members ' concerns about risk identification?

Options:

A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

D.

Ensure that the most knowledgeable members of the team validate risk identification processes. 

Buy Now
Questions 37

During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.

What should the risk manager do to address the new risk of increased logistics costs?

Options:

A.

Accept the increased costs as part of the project ' s risk threshold.

B.

Develop a contingency plan to cover additional logistics expenses.

C.

Switch suppliers to potentially reduce logistics expenses.

D.

Incorporate a cost-sharing arrangement with the suppliers.

Buy Now
Questions 38

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.

Perform an assumptions and constraints analysis.

B.

Use the Wideband Delphi method.

C.

Use the brainstorming technique.

D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 

Buy Now
Questions 39

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

What should the project manager do first?

Options:

A.

Include the risk in the register and communicate with the stakeholders.

B.

Communicate with the client to provide the previous shutdown plan.

C.

Review and update the project schedule.

D.

Interview the other project manager to learn more details.

Buy Now
Questions 40

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Buy Now
Questions 41

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

Options:

A.

Select the strategies with the least overall impact to resources.

B.

Select the strategies with the least financial impact.

C.

Select the strategies with the greatest overall positive influence.

D.

Select the strategies with the greatest benefit to stakeholders.

Buy Now
Questions 42

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.

What should the risk manager have done to prevent missing the milestone?

Options:

A.

Better schedule monitoring and controlling.

B.

Identify and analyze project plan assumptions.

C.

Have a detailed work breakdown structure (WBS).

D.

Use management reserves to cover delays.

Buy Now
Questions 43

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager ' s department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Options:

A.

Reformed the risk monitoring and closing process properly.

B.

Created the project work plan and budget more accurately.

C.

Educated the project team on budget change requests.

D.

Communicated better with the organization ' s CEO.

Buy Now
Questions 44

An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.

What should the risk owner do?

Options:

A.

Develop an efficient network protection solution quickly to mitigate the risk.

B.

Escalate the case to the risk manager and wait for their instructions.

C.

Conduct an analysis to determine the root cause of the failed response.

D.

Apply a work around to eliminate or mitigate the impact of the threat.

Buy Now
Questions 45

A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.

Which analytical tool should the risk manager use?

Options:

A.

Probability tree diagram

B.

Ishikawa diagram

C.

Decision tree analysis

D.

Monte Carlo simul-ation

Buy Now
Questions 46

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

Options:

A.

Add only the threats to the risk register

B.

Utilize different tools to identify the risks

C.

Plan risk responses to the threats

D.

Update the risk register with the identified risks

Buy Now
Questions 47

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

Options:

A.

Risk analysis

B.

Risk identification

C.

Risk treatment

D.

Risk evaluation

Buy Now
Questions 48

A nonprofit organization is working on a project to deliver a fundraising concert event. The concert is only a few weeks away, and the project team has completed revising the risk processes when an opportunity is identified. The key stakeholders want to capitalize on it.

What should the risk manager do?

Options:

A.

Accept the opportunity and look for options to mitigate it.

B.

Direct the team to explore the likelihood of enhancing the opportunity.

C.

Work with the team to identify a suitable owner for the opportunity.

D.

Continue to monitor and document the opportunity.

Buy Now
Questions 49

A risk manager faces resistance as they try to implement the project ' s risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

Options:

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

Buy Now
Questions 50

During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.

What should the risk manager do?

Options:

A.

Assign a risk owner and develop the risk mitigations at the next scheduled risk meeting.

B.

Continue with the project as the risk identified is inconsequential.

C.

Assign risk responsibility to the project manager to determine how to proceed.

D.

Update the project stakeholders and seek their input on the resulting secondary risk.

Buy Now
Questions 51

The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

What should the project risk manager do next to identify risks?

Options:

A.

Review the risk breakdown structure to ensure project scope is covered.

B.

Use the brainstorming technique to remove personal bias.

C.

Use expert judgment to remove ego or emotional conflict.

D.

Consider the Delphi technique to gather all stakeholder opinions.

Buy Now
Questions 52

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Buy Now
Questions 53

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.

The cost control processes is ineffective.

B.

The cost baseline is inaccurate.

C.

The actual reported costs are inaccurate.

D.

The cost related risks are effectively managed.

Buy Now
Questions 54

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

Options:

A.

Ask the team to perform an earned value analysis.

B.

Review the lessons learned from other projects.

C.

Ask the team to prepare a Monte Carlo analysis.

D.

Ask the risk expert to perform a PESTLE evaluation.

Buy Now
Questions 55

A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.

Which type of analysis should the project manager use in this instance?

Options:

A.

Check list analysis

B.

Cause and effect

C.

Specialized meeting

D.

Quantitative analysis

Buy Now
Questions 56

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Options:

A.

Issue log

B.

Change log

C.

Assumption log

D.

Risk-adjusted back log

Buy Now
Questions 57

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project ' s profitability will increase by 80%.

What type of request is the risk manager describing?

Options:

A.

A request to increase project earnings

B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment 

Buy Now
Questions 58

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

Options:

A.

Execute the security risks contingency plan.

B.

Get a report of customers affected by the risk.

C.

Identify residual and secondary risks.

D.

Coordinate a response with the risk owner.

Buy Now
Questions 59

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.

Close and communicate the results of the risk response actions.

B.

Run a workshop to analyze the effectiveness of the risk plan.

C.

Conduct a risk reserve analysis and document the results.

D.

Verify that all risk response actions have been documented. 

Buy Now
Questions 60

A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project ' s timeline. The project team is struggling to finalize the project ' s budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project ' s final cost. The project team will not be able to finalize the project ' s timeline until the budget is finalized.

What should the risk manager do?

Options:

A.

Request an extension to mitigate schedule constraints.

B.

Register the risks as vendor issues and avoid further action.

C.

Log the risk and the response strategies in the risk register.

D.

Catalog the risks as assumptions and avoid further action.

Buy Now
Questions 61

A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.

What process is this part of?

Options:

A.

Plan Risk Management

B.

Perform Qualitative Risk Analysis

C.

Perform Quantitative Risk Analysis

D.

Monitor and Control Risk

Buy Now
Questions 62

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Options:

A.

Assess the risk register to ensure the secondary risks are realistic.

B.

Assess the impact of residual and secondary risks on project objectives.

C.

Assess the change log to establish that changes were implemented.

D.

Assess the stakeholder register to determine the impact of initial risks. 

Buy Now
Questions 63

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Buy Now
Questions 64

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

Options:

A.

Risk trigger

B.

Risk escalation

C.

Risk urgency

D.

Risk time impact

Buy Now
Questions 65

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Options:

A.

Conduct a subject matter expert (SME) meeting.

B.

Perform qualitative analysis.

C.

Prioritize after quantitative analysis

D.

Prioritize the stakeholders affected.

Buy Now
Questions 66

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Buy Now
Questions 67

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.

US$68,000

B.

US$52,000

C.

US$120,000

D.

US$80,000

Buy Now
Questions 68

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

Options:

A.

Sensitivity analysis

B.

What-if scenario analysis

C.

Regression analysis

D.

Decision tree analysis

Buy Now
Questions 69

A project is underway to implement a new customer support software. During testing, the risk manager discovers that the integration with the existing customer relationship management system is more complex than initially planned, potentially delaying the project. The risk manager needs to update project documents to reflect this new information.

Which steps should the risk manager consider when updating relevant project documents?

Options:

A.

Update the issue log with relevant information as the immediate concern for key stakeholders.

B.

Assume the delay will not affect the timeline and continue with the current scheduled activities.

C.

Update the project documents after the work has been completed and formally accepted.

D.

Assess the delay with the technical team, update the schedule and risk register, and inform stakeholders.

Buy Now
Questions 70

In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?

Options:

A.

Probabilistic and quantitative risk analyses to get the overall risk score

B.

Quantitative risk analysis to get the overall risk score

C.

Probabilistic risk analysis to get the overall risk score

D.

Qualitative risk analysis to get the overall risk score 

Buy Now
Questions 71

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

Options:

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk ' s status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register. 

Buy Now
Questions 72

A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project ' s risk register to try to maximize their chances of occurrence.

What should the project team do next?

Options:

A.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

B.

Log the threats in the risk register to try to minimize the probability of occurrence.

C.

Log the threats in the risk register to try to maximize the probability of occurrence.

D.

Update the project management plan to ensure the results of the opportunities are captured.

Buy Now
Questions 73

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.

Given the project ' s complexity, what should the risk manager do?

Options:

A.

Wait until halfway through the project to identify risks, as most issues will be clear by then.

B.

Conduct the exercise with the key team members, excluding external stakeholders.

C.

Facilitate a risk identification exercise with key stakeholders, considering all factors.

D.

Focus only on identifying the most obvious risks to save time and project resources.

Buy Now
Questions 74

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

Options:

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder ' s team.

C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

D.

Add the identified risk to the risk register for future probability and impact analysis.

Buy Now
Questions 75

During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?

Options:

A.

Compare the actual data with the historical data.

B.

Compare the actual data with the subject matter expert (SME) criteria.

C.

Compare the actual data with the risk baseline.

D.

Compare the actual data with the project sponsor ' s expectation.

Buy Now
Questions 76

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis

B.

Residual impact analysis

C.

Sensitivity analysis

D.

Reserve analysis 

Buy Now
Questions 77

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

Options:

A.

Engaged the sponsor and informed them of the decision to remove the planned feature.

B.

Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.

C.

Performed proper risk identification at the project outset to ensure this risk was identified and mitigated.

D.

Created a schedule buffer in the plan to deal with unknown risks if and when they occurred. 

Buy Now
Questions 78

An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?

Options:

A.

Go for a low-risk threshold of ±5% around a cost objective.

B.

Confirm stakeholders risk thresholds based on risk appetites.

C.

Conduct risk identification to populate the risk register.

D.

Go for a high-risk threshold of ±10% around a cost objective. 

Buy Now
Questions 79

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

Options:

A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.

B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.

C.

Before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile.

D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.

Buy Now
Questions 80

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

Buy Now
Questions 81

A risk manager is preparing the risk strategy for a strategic project, which involves stakeholders based in multiple locations. What should the risk manager do at this stage?

Options:

A.

Update the risk communications plan to include all stakeholders.

B.

Define the risk processes and tools to be adopted.

C.

Update the risk register to include this stakeholder-related risk.

D.

Refine the risk assumptions and criteria to be used.

Buy Now
Questions 82

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information

B.

Conduct interviews, meetings, and focus groups

C.

Assign a different risk manager for each portfolio unit

D.

Employ brainstorming to generate spontaneous ideas

E.

Perform qualitative and quantitative risk analyses 

Buy Now
Questions 83

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

Buy Now
Questions 84

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

Options:

A.

Earned value management (EVM) variance metrics

B.

A risk burndown chart showing remaining risks

C.

The format established in the risk management plan

D.

An itemized list of remaining risks and their scores 

Buy Now
Questions 85

During project implementation, a risk manager wants to determine the effectiveness of risk response plans and which risk will have an impact on the project outcome. Which analysis should the risk manager do?

Options:

A.

Perform Pareto analysis.

B.

Perform sensitivity analysis.

C.

Perform contingency analysis.

D.

Perform qualitative analysis.

Buy Now
Questions 86

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Options:

A.

Request for a skilled facilitator to help resolve conflicts that have arise.

B.

Refer to the team’s ground rules on how to resolve conflicts.

C.

Run a sensitivity analysis to check which risks have the most impact.

D.

Use the assumption analysis techniques to validate the assumptions.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Aug 20, 2026
Questions: 333

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now PMI-RMP testing engine

PDF (Q&A)

$31.5  $104.99
buy now PMI-RMP pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 20 Aug 2026