During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.
The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?