Summer Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpm65

PMP Project Management Professional (2025 Version) Questions and Answers

Questions 4

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

Options:

A.

Request a performance assessment for the team from the functional manager.

B.

Evaluate the current effectiveness of the team and define development needs.

C.

Allow each team member to use their individual strengths for project success.

D.

Assign team member roles and responsibilities based on past experience.

Buy Now
Questions 5

A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the

beginning of the project have changed.

What should the project manager do?

Options:

A.

Inform the team not to accept any changes, as it involves significant rework.

B.

Request management to update the project requirements accordingly.

C.

Request an update of only new requirements, as other changes involve rework.

D.

Inform management that the agreed-upon scope cannot be changed.

Buy Now
Questions 6

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

Options:

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.

B.

Request help from the project sponsor to get support from the sales agents.

C.

Escalate the issue to senior management to gain team buy-in

D.

Explain the change benefits to the sales agents' manager to get their support.

Buy Now
Questions 7

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

Options:

A.

Refer to the stakeholder engagement plan.

B.

Set up a conference call for all stakeholders.

C.

Refer to the communications management plan.

D.

Send an email to all stakeholders.

Buy Now
Questions 8

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

Options:

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

Buy Now
Questions 9

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

Options:

A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

C.

Include the dependency in the project schedule.

D.

Ask IT to prioritize the needed system to meet the schedule.

Buy Now
Questions 10

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

Options:

A.

Communicate the concerns to the project management office (PMO) during the weekly project reports

B.

Call for a team meeting to decide if the changes should be included

C.

Initiate the change request to modify the scope and adjust the timelines

D.

Conduct an impact analysis and present the results to the steering committee for approval

Buy Now
Questions 11

A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

Options:

A.

Redefine the communications management plan

B.

Develop an integrated change management plan

C.

Document the risk in the project risk register

D.

Review the scope defined in the project charter

Buy Now
Questions 12

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

Options:

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Buy Now
Questions 13

A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''

Options:

A.

Provide a digital transformation guide and explain that the change is unavoidable

B.

Ask the bank executives to officially announce that the project manager is leading the project

C.

Provide proper training sessions to the stakeholders so they understand the purpose of the change

D.

Hire an expert in digital transformation and assign that person as the champion for the change

Buy Now
Questions 14

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

Options:

A.

Improve the risk management strategy and risk monitoring

B.

Reach out to the project manager of the previous project for assistance

C.

Allow the team member to work through the issue as a training opportunity

D.

Share the lessons learned from the previous protect with the team member

Buy Now
Questions 15

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?

Options:

A.

Change management plan

B.

Schedule management plan

C.

Scope management plan

D.

Cost management plan

Buy Now
Questions 16

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

B.

Schedule a new meeting to evaluate the agreement and negotiate a new one.

C.

Talk with the team member and explain that once the meeting ended, the agreement must be respected.

D.

Meet with the team member and search for the root cause of their behavior.

Buy Now
Questions 17

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

Options:

A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior

B.

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately

C.

Request a meeting with the disruptive team member and help to resolve the issue

D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly

Buy Now
Questions 18

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Buy Now
Questions 19

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

Options:

A.

Work with the sponsor to revise the product vision.

B.

Create a definition of ready (DoR) for the backlog items.

C.

Discuss the issue with the service request manager.

D.

Refine the product backlog items with the stakeholders.

Buy Now
Questions 20

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

Options:

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

Buy Now
Questions 21

A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.

What should the project manager do next?

Options:

A.

Continue production processes and plan to discuss changes at the next annual target review meeting.

B.

Begin a marketing campaign to sell alternative packaging after the 12-month period ends.

C.

Inform management of the new law as an opportunity to expand market share and share the proposed products

D.

Organize a meeting with all stakeholders and review the stakeholder engagement plan

Buy Now
Questions 22

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

Options:

A.

Ask the new product owner to explain the importance of the project.

B.

Email the team a detailed outline of the business requirements.

C.

Review the project charter with the team.

D.

Facilitate a discussion of the vision for the project.

Buy Now
Questions 23

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?

Options:

A.

Issue log

B.

Lessons learned register

C.

Stakeholder engagement plan

D.

Risk register

Buy Now
Questions 24

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

Buy Now
Questions 25

A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?

Options:

A.

Identify and escalate any identified risks to the facilitator to handle

B.

Update the risk register during every iteration with any open concerns

C.

Use regular feedback loops through daily standups iteration demos and retrospectives

D.

Focus on developing a working deliverable instead of documenting risks

Buy Now
Questions 26

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

Options:

A.

Escalate the issue to the project sponsor, as the decision to add the component brings

many benefits even though it will be disruptive to the production line.

B.

Lead a root cause analysis workshop with the design team to identify the failures that

led to the decision to add a component that was not compatible with the production

line.

C.

Meet with the operations manager to explain the background for the change and

understand the operation manager's concerns about the change.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that the

project may deliver late and over budget due to manufacturing difficulties.

Buy Now
Questions 27

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

Options:

A.

Send the project charter to all stakeholders for information.

B.

Send an email to all stakeholders directing them to approach the project manager

directly.

C.

Review the stakeholder engagement plan and inform the stakeholders.

D.

Review the change management plan and ask the change control board (CCB) to be

involved.

Buy Now
Questions 28

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

Options:

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

Buy Now
Questions 29

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

Options:

A.

Develop a schedule that ensures people with personal differences work separately.

B.

Use an approach to the project that does not involve colocation.

C.

Meet with the team and agree on expectations from team members.

D.

Invite the functional managers of the different units to address their personal differences.

Buy Now
Questions 30

A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time

What kind of conflict resolution did the project manager apply in this situation?

Options:

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Collaborate/problem solve

D.

Force/direct

Buy Now
Questions 31

A project team has been together for a long time and has been led by three different

project managers. Lately, the performance of one of the team members has been declining

and has affected the project delivery.

What should the current project manager do to ensure that team performance is improved and

sustained?

Options:

A.

Liaise with the functional managers to replace the team member.

B.

Engage with the team member and draw up a development plan.

C.

Organize quarterly team-building events.

D.

Request that a new team member be added to the team

Buy Now
Questions 32

A project manager is leading a project that is implementing an assembly line.

During the quality review meeting, a team member reports an issue stating that the product

being developed has discrepancies with the one requested by the customer.

What should the project manager do?

Options:

A.

Ensure the current solution is in place to enable future usability.

B.

Run a root cause analysis to identify the quality breach and update the quality

management plan.

C.

Check that the product meets the requirements established by the customer.

D.

Make a proposal of new specifications and submit it to the customer for approval.

Buy Now
Questions 33

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

Options:

A.

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.

Develop a communications management plan for each category in the stakeholder register.

C.

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.

Postpone the recommendation since the organization does not currently have a defined agile methodology.

Buy Now
Questions 34

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?

Options:

A.

Identify the problem's root causes and define the ground rules with all project team members to minimize interferences.

B.

Recommend to the project team members that they should improve their planning and make their stories smaller.

C.

Reunite with the project team members affected and tell them not to reduce the team's capacity.

D.

Hire a coach to help all project teams to improve their abilities to solve problems on their own.

Buy Now
Questions 35

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

Options:

A.

Work with the team and others in the network to assess and prioritize the obstacles.

B.

Engage with the external stakeholders and the other division of the organization to

resolve the issues.

C.

Escalate the obstacles to the project sponsor for assistance with resolution.

D.

Determine a change response to identify and resolve the obstacles to move the project

forward.

Buy Now
Questions 36

During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.

In order to reach a consensus and have a successful project completion, what should the

project manager do first?

Options:

A.

Analyze the bounds of the negotiation for agreement with both parties.

B.

Identify and satisfy both parties' underlying wants.

C.

Comply with the customer's request to achieve the project mandate.

D.

Initiate a change request to accommodate the revised cost of goods

Buy Now
Questions 37

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

Options:

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

Buy Now
Questions 38

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

Options:

A.

Become a servant leader by supporting team collaboration and removing impediments

B.

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

C.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

D.

introduce new communication tools to the project team members

Buy Now
Questions 39

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

Options:

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

Buy Now
Questions 40

A project has been running for 2 months and now requires approval for a supplier to

begin some execution tasks. The project team has evaluated several suppliers and selected

their top two preferred suppliers. The project sponsor requested that another supplier who has

lower costs be added to the list. However, the project manager is aware that this supplier

does not always fulfill the project requirements.

What should the project manager do?

Options:

A.

Set up a requirements review session and obtain agreement for selection criteria.

B.

Recommend to the team to add the sponsor's preferred supplier to the list.

C.

Choose the sponsor's preferred supplier for the project to avoid conflict between the

team and sponsor.

D.

Recommend to the sponsor to review the results of the team's supplier evaluation.

Buy Now
Questions 41

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

Options:

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

Buy Now
Questions 42

A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?

Options:

A.

Request that the vendor provides a manual with all required knowledge

B.

Implement retrospectives with the vendor to gather the required knowledge

C.

Submit a change request to extend the vendor's contract to provide formal training for the team

D.

Conduct daily knowledge transfer standups to ensure that the team is properly trained

Buy Now
Questions 43

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

Options:

A.

Update the stakeholder engagement assessment matrix

B.

Update the communications management plan to include informal requests

C.

Ask the team member to develop a dashboard to fulfill the request.

D.

Tell the team member to route the request through the project manager

Buy Now
Questions 44

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?

Options:

A.

Document the issue in the issue log and escalate to the project sponsor

B.

Inform the project sponsor and suggest canceling the project

C.

Review the project goals and eat criteria m the project charter

D.

Ask the leader of research and development to decide on next steps

Buy Now
Questions 45

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

Options:

A.

Ensure all three teams deliver independently without interactions so that they remain

focused and meet customer requirements.

B.

Implement communication techniques and ensure the teams follow a relay pattern of

handing off work from one team to the other.

C.

Use a fishbone analysis to resolve problems and iron out communication issues

between the teams.

D.

Maintain localized teams to circumvent the challenges of delay or any other

unforeseen risks that might prevent progress.

Buy Now
Questions 46

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.

Update the project management plan in order to get back on track.

B.

Ensure the team receives continuous feedback from customers users.

C.

Submit a change request to adjust the project scope.

D.

Ensure the team understands all additional project requirements.

Buy Now
Questions 47

An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?

Options:

A.

Create a team incentive program with prizes, allowing the team members to work overtime to find defects.

B.

Reduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.

C.

Hire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.

D.

Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

Buy Now
Questions 48

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

Options:

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

Buy Now
Questions 49

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

Options:

A.

Document the new stakeholders' concerns in the meeting minutes.

B.

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.

Use social media environments to share the project information

D.

Use the project management information system (PMIS) to share information.

Buy Now
Questions 50

A project manager writes to the receiving organization to inform them that all

acceptance activities are completed with success and it is time to initiate handover. The

receiving manager replies that the team will not be ready for the handover procedure for

another two weeks.

What should the project manager do?

Options:

A.

Deliver to the receiving manager on time, who can then make a knowledge transfer to

their team.

B.

Inform the project sponsor of the two-week delay and replan activities to minimize

delays.

C.

Request that the receiving manager issue a change request to prolong the project by

two weeks.

D.

Issue an internal change request to secure the resources for an additional two weeks.

Buy Now
Questions 51

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Buy Now
Questions 52

A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?

Options:

A.

Inform the project steering committee of this constraint.

B.

Inform the project team and create a spike for the next Iteration.

C.

Inform the legal department that the project scope will be updated.

D.

Inform the product owner that the project will continue as planned.

Buy Now
Questions 53

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Options:

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Buy Now
Questions 54

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Buy Now
Questions 55

During the early phases of a project, mitigation actions were not executed in a

timely manner; therefore, the project schedule was impacted. Several project stakeholders are

now frustrated with the delays.

What should the project manager have done to manage the issue?

Options:

A.

Identified and reported the issue

B.

Monitored and controlled the issue

C.

Identified the appropriate response and had it implemented

D.

Communicated any identified action to impacted stakeholders

Buy Now
Questions 56

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

Options:

A.

Schedule team-building activities to encourage collaboration among the team

B.

Coach the team members to resolve the gaps in understanding

C.

Conduct a kick-off meeting and communicate the goals and objectives of the project

D.

Continue the meetings and communicate the goals and objectives to resolve the gaps

Buy Now
Questions 57

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?

Options:

A.

Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively

B.

Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training

C.

Make sure all stakeholders have access to the system and know where to find project artifacts

D.

Send the project schedule via email to the stakeholders who need that information

Buy Now
Questions 58

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

Options:

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

Buy Now
Questions 59

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.

Call a team meeting to discuss team members' strengths and weaknesses

C.

Establish rules and regulations for team members with consequences if the goals are not reached

D.

Establish team behavior and develop an understating of how to work together

Buy Now
Questions 60

A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.

What should the project manager do?

Options:

A.

Assign the marketing executive's tasks to another project team member

B.

Review the executive's declining performance with human resources (HR)

C.

Show empathy and praise the marketing executive's strengths

D.

Make the marketing executive accountable for their work and output

Buy Now
Questions 61

An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.

What should the agile leader do?

Options:

A.

Reassign the task to another team member and require the team member to complete training

B.

Use the retrospective meeting to remind the entire team that they must complete all deliverables in each sprint

C.

Review the definition of done (DoD) with the team so that everyone understands what the team must deliver in this sprint.

D.

Speak directly with the team member about improvements and commit to an agreed-upon time frame.

Buy Now
Questions 62

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

Options:

A.

Ask human resources (HR) to coordinate another activity.

B.

Reassess the team situation and provide a proper solution.

C.

Inform HR about the situation and ask for support.

D.

Meet with the team to explain that conflicts must be addressed and solved.

Buy Now
Questions 63

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

Options:

A.

Meet with each stakeholder individually to gather input to the product backlog and

begin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learned

and complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for the

product backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Buy Now
Questions 64

During the setup of an agile project, the product owner expressed clear interest in

having features released during product development over having the product completed in

one year. What should the project manager do?

Options:

A.

Promote a productive environment where everybody can work without interruptions

from the rest of the team members.

B.

Create a reward system recognizing group contributions to get people motivated and

improve performance.

C.

Facilitate sprint planning sessions with a focus on defining the minimum viable product

(MVP).

D.

Design a set of metrics including velocity, which is a good measure of value delivered.

Buy Now
Questions 65

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's

performance?

Options:

A.

Results of the MoSCoW assessment

B.

Cost-benefit analysis

C.

Return on investment (ROI) analysis

D.

Earned value analysis (EVA)

Buy Now
Questions 66

The main project stakeholder was fired and replaced by another stakeholder. The

new stakeholder reviewed the project scope and requested numerous changes, arguing that

the stakeholder's team is unhappy with the results to date.

What should the project manager do?

Options:

A.

Put the new requirements in the backlog with high priority and implement the

requested changes.

B.

Put the new requirements in the backlog and submit a formal change request for

approval.

C.

Put the new requirements in the backlog and let the product owner check their value

and priority.

D.

Put the new requirements in the backlog with low priority and implement the requested

changes.

Buy Now
Questions 67

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

Options:

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

Buy Now
Questions 68

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

Options:

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

Buy Now
Questions 69

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

Options:

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.

Stakeholders who are supporting the project in order to obtain additional resources.

Buy Now
Questions 70

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

Options:

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Buy Now
Questions 71

A project manager is working on a highly complex project. During the execution of

the project, the local government changed certain environmental regulations, which could

potentially delay the project.

What immediate action should the project manager take?

Options:

A.

Update the issue log.

B.

Update the project baseline.

C.

Update the risk management plan.

D.

Update the change request log.

Buy Now
Questions 72

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

Options:

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

Buy Now
Questions 73

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

Options:

A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to compliance

regulations.

B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.

C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.

D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.

Buy Now
Questions 74

A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team

What should the project manager do first to ensure the project is compliant?

Options:

A.

Meet with the team to discuss compliance concerns

B.

Review the organizational process assets (OPAs) for compliance topics

C.

Review the compliance strategy and version history

D.

Meet with the project sponsor to discuss their compliance concerns

Buy Now
Questions 75

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

PMP Question 75

Options:

Buy Now
Questions 76

The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete

the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility

activities that must commence immediately.

How should the project manager get these funds approved?

Options:

A.

Wait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.

B.

Continue with the preliminary activities and inform the investment committee at the next monthly meeting.

C.

Exclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.

D.

Submit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.

Buy Now
Questions 77

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting

with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?

Options:

A.

Submit a change order request with the new project objective to the project management office (PMO).

B.

Initiate a crashing routine to gain extra time for the added feature.

C.

Communicate the results and negotiate the needed resources and time with the stakeholder.

D.

Ask the project team to work overtime in order to accommodate the new changes.

Buy Now
Questions 78

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?

Options:

A.

Performed a stakeholder analysis when the sponsor joined the project

B.

Held a governance meeting to review the project increment

C.

Conducted a product iteration review with the new project sponsor

D.

Escalated the issue to ensure the increment would be approved

Buy Now
Questions 79

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.

What should the project leader do?

Options:

A.

Report the impediment to the functional manager.

B.

Identify the impediment and associated risks at the daily standup.

C.

Escalate the impediment and associated risks to the business sponsor.

D.

Identify the impediment during the retrospective

Buy Now
Questions 80

A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.

What should the project manager do?

Options:

A.

Allow collaboration to smooth out communication between team members.

B.

Add collaboration tools to the communications management plan.

C.

Escalate these communication challenges to the project sponsor.

D.

Organize a team meeting to resolve the communication challenges.

Buy Now
Questions 81

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

Options:

A.

Prioritize which backlog activities should be kept.

B.

Work on the backlog activities with fewer story points.

C.

Ask for more resources to clear the backlog activities.

D.

Assign an owner for each backlog activity and track progress.

Buy Now
Questions 82

A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?

Options:

A.

Set up a meeting with the team to discuss and determine the project's challenges.

B.

Propose a revised project schedule to the sponsor as the delays have affected the time lines.

C.

Schedule a meeting with the sponsor to express the team's frustrations about the data.

D.

Meet with the data suppliers to explain the critical timing requirements of the project.

Buy Now
Questions 83

During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain

feedback from on project deliverables. What should the project manager do?

Options:

A.

Share a template with the stakeholder to receive feedback on deliverables.

B.

Ask the project sponsor to arrange a meeting with the stakeholder.

C.

Use networking skills to approach the stakeholder.

D.

Update the stakeholder engagement plan for the stakeholder.

Buy Now
Questions 84

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

Options:

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Buy Now
Questions 85

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

Options:

A.

Ask the members to be more proactive and share ideas with each other.

B.

Set up a daily virtual meeting with the development team.

C.

Plan a monthly virtual meeting to align and to review the plans.

D.

Review the issue with the project sponsor and ask for support.

Buy Now
Questions 86

In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in

conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

Options:

A.

Anticipate, alert, and follow the risk management process.

B.

Detect, track, and follow the issue management process.

C.

Promote, inspire, and follow the stakeholder engagement process.

D.

Discuss, educate, and follow the communications management process.

Buy Now
Questions 87

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

Options:

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

Buy Now
Questions 88

During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project

manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?

Options:

A.

Stop the project until someone in the organization can identify all the new requirements and how they impact the project.

B.

Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reaction

time.

C.

Agree with the project team that the new requirements will be applied to the next project, not the one already under development.

D.

Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.

Buy Now
Questions 89

During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?

Options:

A.

Review the project time line and find opportunities to reduce the project schedule.

B.

Review the budget with the project sponsor and ask for an increase to the budget

C.

Review the backlog and find opportunities to reprioritize the work and reduce the project scope

D.

Review the resource management plan and find opportunities to reduce project costs.

Buy Now
Questions 90

A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

Options:

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

Buy Now
Questions 91

In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The

discussion has intensified and the team members are not able to agree.

What should the project manager do next?

Options:

A.

Remove one of the team members from the project to improve team dynamics.

B.

Make a decision based on expert judgment as a project manager.

C.

Consider the view of each team member about the issue in order to reach consensus.

D.

Remove both team members since they are not productively adding to the team.

Buy Now
Questions 92

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

Options:

A.

Risk register information

B.

Higher-level activities completed

C.

Milestones status report

D.

Resource breakdown structure (RBS)

Buy Now
Questions 93

A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.

How should the project manager respond to this request?

Options:

A.

Ask the team member to review the lessons learned on facilitation from previous projects.

B.

Suggest that the team member facilitate an upcoming iteration and review the outcomes in the iteration retrospective.

C.

Engage their functional manager to determine if there is alignment to their development plan before agreeing.

D.

Add new elements to the project backlog to account for the training needs of the team member.

Buy Now
Questions 94

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

Options:

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

Buy Now
Questions 95

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?

Options:

A.

Inform the project sponsor about the problem faced by the team.

B.

Ask the product owner to write the specifications for the related user story.

C.

Organize an early retrospective with the team to analyze the problem.

D.

Facilitate a problem-solving session with the team to analyze the problem.

Buy Now
Questions 96

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?

Options:

A.

Ask the project management office (PMO) to support and review all deliverables.

B.

Log the issue in the risk register and the issue log.

C.

Assign a technical writer to the project.

D.

Develop a standard for document quality control.

Buy Now
Questions 97

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?

Options:

A.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

B.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

C.

Delegate authority to the team members and ask them to submit weekly status reports instead.

D.

Ask senior management for permission to hold in-person team meetings once each week.

Buy Now
Questions 98

A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even

though reports have been sent on a weekly basis.

What should the project manager do to ensure all stakeholders are receiving proper information about the project?

Options:

A.

Hold a steering committee meeting with all stakeholders to provide a comprehensive update on the project progress.

B.

Create daily progress reports and send them to all stakeholders.

C.

Include stakeholders in the weekly status meetings with the team.

D.

Assess all of the project stakeholders and document their preferred communication method and frequency.

Buy Now
Questions 99

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Buy Now
Questions 100

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?

Options:

A.

Communicate with the industry's regulatory authority to grant the company an exception

B.

Escalate the issue to the company's CEO who has experience with the regulations.

C.

Comply with the regulatory requirements and work to compress the project schedule.

D.

Hire a third party who is an expert on the industry's regulations to work out the details.

Buy Now
Questions 101

A medium-sized company has been exploring new marketing tactics with regard to launching a new product. New product creation is no small task. In the end, it was too big

of an expenditure for the company to undertake.

What should the project manager do in the future when working on new product projects?

Options:

A.

Make use of kanban boards so all stakeholders have a clear view of the project and provide their help accordingly.

B.

Increase the contingency reserve and prepare the team for applying fast-failing techniques when the estimates veer from the initial plan.

C.

Adopt a chain management approach, developing products based on the same platform and infrastructure.

D.

Train the team to first find the minimum viable product (MVP) that will deliver value to the customer.

Buy Now
Questions 102

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)

Options:

A.

Review the issue with project sponsor and submit a change request

B.

Report the issue to the product manager and business segments

C.

Analyze the business benefits criteria and assumptions

D.

Discuss the issue with the operations team to assess expense overruns

E.

Schedule a project review meeting to analyze the root cause

Buy Now
Questions 103

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

Options:

A.

Submit a change request to transfer the risk to a third party in case it becomes an issue.

B.

Remove the user stories associated to that risk and avoid the impact to the project deliverables.

C.

Assign a qualified team member to be the risk manager for the project.

D.

Ask the team to monitor the risk and provide an alert if it becomes an issue.

Buy Now
Questions 104

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.

Ask one of the more experienced team members to support the team member with the task.

B.

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.

Ask the experienced team members to produce a manual on how to complete the task.

D.

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Buy Now
Questions 105

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

Options:

A.

Apply a predictive project management approach.

B.

Evaluate and decide on a phased project management approach.

C.

Implement an adaptive project management approach.

D.

Use a hybrid model to combine predictive and adaptive life cycles.

Buy Now
Questions 106

A company made several changes recently, which resulted in a positive change in

the company culture. A project manager was just assigned to report to a new project

supervisor whose leadership style is about getting things done quickly regardless of employee

and operational impacts. Some employees are complaining about this.

What should the project manager do?

Options:

A.

Clarify expectations by explaining the company culture with the supervisor.

B.

Ask senior management to move the supervisor to a different project.

C.

Revisit the company's organizational culture.

D.

Instruct the employees to listen to the supervisor.

Buy Now
Questions 107

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

Options:

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

Buy Now
Questions 108

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?

Options:

A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources

B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted

C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline

D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements

Buy Now
Questions 109

A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.

What should the project manager do?

Options:

A.

Suggest to the team lead how to deal with this team member and discuss the situation with the engineer.

B.

Organize a meeting with all of the project stakeholders and inform them about the new risk and its impact on the project.

C.

Organize a meeting with the project team and discuss the situation and its impact on project delivery.

D.

Suggest to the engineer how to work efficiently with the lead and discuss the situation with the lead's functional manager.

Buy Now
Questions 110

During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager

react to ensure the project remains successful?

Options:

A.

Focus the discussion on recovery and ways to get back on track.

B.

Act in a way to highlight the criticality of the situation.

C.

Punish the team member for providing negative data that will affect the team's morale.

D.

Thank the team member for raising this issue, log it, and move on to the next topic.

Buy Now
Questions 111

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

Options:

A.

The organizational process assets (OPAs) have been updated.

B.

The contractual deliverables of the project have been accepted.

C.

It The handover and deliverable acceptance have been completed.

D.

The lessons learned sessions have been conducted.

Buy Now
Questions 112

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

Options:

A.

Map the lessons learned against work breakdown structure (WBS) components.

B.

Archive the survey responses with project artifacts for future projects.

C.

Use the information to restart the project.

D.

Evaluate the information collected on areas of improvement.

Buy Now
Questions 113

A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?

Options:

A.

Ensure that the project artifacts are kept up-to-date and shared with the stakeholders.

B.

Invite the stakeholders to the daily standup to clarify any questions about the project artifacts.

C.

Escalate the stakeholders' project artifacts concerns to the project management office (PMO) for resolution.

D.

Send an agile report to the stakeholders, which includes the list of the project artifacts.

Buy Now
Questions 114

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

PMP Question 114

Options:

Buy Now
Questions 115

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience

performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

Options:

A.

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work,

B.

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product

C.

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.

D.

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.

Buy Now
Questions 116

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

Options:

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Buy Now
Questions 117

A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.

What should the project manager do to help the team and the customer?

Options:

A.

Manage the risks associated with the proposed approach.

B.

Assist the team with identifying the minimum viable product (MVP) to validate assumptions.

C.

Coordinate with the business unit to get detailed requirements.

D.

Work closely with the marketing team on market research and product segments

Buy Now
Questions 118

A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the

team member's emotional situation has affected the rest of the team's performance.

How should the project manager handle this situation?

Options:

A.

Help all team members learn to deal with their emotions by building a culture of empathy.

B.

Separate the key team member and replace them while they emotionally recover.

C.

Meet with the team to discuss how to handle the performance problem.

D.

Ask the human resources (HR) department for their support providing emotional help.

Buy Now
Questions 119

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

Options:

A.

Finish to start

B.

Start to start

C.

Start to finish

Buy Now
Questions 120

A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.

What should the project manager do in this situation?

Options:

A.

Assess the impact of the stakeholder and engage properly.

B.

Escalate the stakeholder issue to the project sponsor.

C.

Develop a specific communications strategy for this stakeholder.

D.

Use interpersonal skills to gain stakeholder engagement.

Buy Now
Questions 121

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?

Options:

A.

Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.

B.

Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.

C.

Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.

D.

Schedule a meeting with the project team member's functional manager and request the functional manager's support.

Buy Now
Questions 122

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

Options:

A.

Request marketing to launch an advertising campaign for the product that is currently in stock.

B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.

C.

Explore if the materials could be supplied locally and obtained on time.

D.

Meet with the engineering team to manufacture the materials in-house.

Buy Now
Questions 123

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

Options:

A.

30/40

B.

40/70

C.

30/70

D.

40/30

Buy Now
Questions 124

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

Options:

A.

Review the adaptive tools' impact and obtain agreement from the functional manager.

B.

Follow the functional manager's recommendation to implement only predictive tools in the project.

C.

Make the decision on which project approach to use that would best fit the project.

D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

Buy Now
Questions 125

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

Options:

A.

Indicate that on the new technology is the functional manager's responsibility.

B.

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.

Consult with the organizational change management specialist as to what the training plan includes.

D.

Document the skill requirements for the product to determine what training is needed.

Buy Now
Questions 126

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

Options:

A.

Update the project charter with the new requirement.

B.

Add a risk to the risk register.

C.

Add it to the issue log as an ongoing issue.

D.

Review and validate the scope management plan.

Buy Now
Questions 127

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a

previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions.

B.

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

D.

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Buy Now
Questions 128

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

Options:

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.

Limit to one kick-off meeting in the project's first phase in order to control the budget.

Buy Now
Questions 129

A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?

Options:

A.

Start working on the resource management plan in order to identify the best team for the project.

B.

Utilize expert judgment and organizational process assets (OPAs) to estimate the effort and budget.

C.

Review the competitor's app to understand the functionalities that the project scope should consider.

D.

Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Buy Now
Questions 130

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?

Options:

A.

Reschedule the project taking this new information into account.

B.

Refer to the project's resource management plan.

C.

Ask the project sponsor for external resources.

D.

Create a change request to be validated by the project sponsor.

Buy Now
Questions 131

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Buy Now
Questions 132

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?

Options:

A.

Ask the team to focus only on the goal, not on ad hoc meetings.

B.

Coach the project owner about the implications of unplanned meetings.

C.

Discuss the issue with the project owner at the retrospective meeting.

D.

Escalate the situation to management because it is affecting the team.

Buy Now
Questions 133

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

Options:

A.

Engage the functional managers to describe the project's impact to the team members directly.

B.

Provide team members with specific and clear instructions on the project objectives and tasks.

C.

Communicate the project's impact and plans to engage the project team throughout the project.

D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

Buy Now
Questions 134

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

Options:

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Buy Now
Questions 135

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

Options:

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Buy Now
Questions 136

A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?

Options:

A.

After full development is completed

B.

When a major feature is completed

C.

At the end of each and every iteration

D.

When the sponsor approves the increment

Buy Now
Questions 137

When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a

result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?

Options:

A.

Come to the meeting with suggested ground rules

B.

Ask all team members to send new ideas prior to the meeting

C.

Extend the meeting to allow everyone to speak

D.

Set expectations for contributions ahead of the meeting

Buy Now
Questions 138

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.

Suggest that the team member ignore the disruptive team member and focus only on the work.

B.

Encourage both team members to meet as soon as possible and resolve the problem

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Report the disruptive team member to the human resource (HR) department.

Buy Now
Questions 139

A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.

The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?

Options:

A.

Utilize a uniform communication structure across all groups.

B.

Define and direct communication to influential stakeholders.

C.

Describe the four groups in the project stakeholder matrix.

D.

Develop and define a communication strategy for stakeholders.

Buy Now
Questions 140

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

PMP Question 140

Options:

Buy Now
Questions 141

In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

Options:

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

C.

Send a detailed report to each steering committee member ahead of the meeting.

D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

Buy Now
Questions 142

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team's collaboration approach?

Options:

A.

Meet with the human resources (HR) department to ask for team support.

B.

Follow the process of the most successful team in the organization.

C.

Compare the team's velocity with other teams in the organization.

D.

Focus on the team's engagement during the next retrospective meeting.

Buy Now
Questions 143

An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.

How should the project manager improve team dynamics?

Options:

A.

Require that all team members be physically present for the weekly project review.

B.

Offer the team member an incentive to stay until the end of the project.

C.

Replace the team member with someone who has similar qualifications and is located closer.

D.

Set up a weekly video conference to monitor the progress of the team member's work.

Buy Now
Questions 144

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

Options:

A.

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

Buy Now
Questions 145

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Buy Now
Questions 146

A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has

identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?

Options:

A.

Investigate the reasons for the disagreement to understand the gap among the stakeholders and search for consensus.

B.

Discuss the situation with the stakeholders to evaluate other adaptive tools for the project.

C.

Schedule training sessions for the stakeholders on the benefits of the adaptive tools.

D.

Update the risk register and escalate the disagreement to the project sponsor and distribute the status to the team.

Buy Now
Questions 147

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?

Options:

A.

Improve the videoconferencing system to provide better availability and quality in order to increase communication.

B.

Have team ambassadors from each location travel to the other in order to facilitate communication and minimize issues.

C.

Facilitate a meeting with both teams so that they can agree on the issues and propose solutions that work for both teams.

D.

Move working windows so that team members can have increased overlap for the handover of status and issues to their counterparts.

Buy Now
Questions 148

A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned

cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.

What should the project manager have done to avoid this situation?

Options:

A.

Captured and reviewed all of the project work and related costs regularly

B.

Notified all vendors about the invoicing and nonpayment deadlines

C.

Reviewed the total committed cost against the cost invoiced at project closing

D.

Involved the finance team and discussed the issue with the vendor

Buy Now
Questions 149

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.

What should the project manager, who is responsible for this project, do to mitigate this risk?

Options:

A.

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

B.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

C.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

D.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

Buy Now
Questions 150

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

Options:

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,

B.

Send emails with information about the project deliverables on the first day of the project.

C.

Connect with every location and check their preferred methods of communication.

D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

Buy Now
Questions 151

A project team needs to follow regulatory compliance guidelines that are mandatory for the project. What should the project manager do to ensure compliance adherence?

Options:

A.

Assess compliance when there is time in the project.

B.

Assign a project team member to ensure compliance.

C.

Review compliance adherence at the end of the project.

D.

Include compliance within the development tools.

Buy Now
Questions 152

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical

complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?

Options:

A.

Tell the client about the chance for the potential delay.

B.

Work with the project team to evaluate the potential delay.

C.

Do not disclose the likelihood of a delay as it is yet to happen.

D.

Ask the project sponsor to inform the client in the next update.

Buy Now
Questions 153

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

Options:

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Buy Now
Questions 154

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource's refusal?

Options:

A.

Speak directly with the resource.

B.

Communicate with their supervisor.

C.

Organize a team meeting.

D.

Speak with their colleague.

Buy Now
Questions 155

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.

Keep the project focused and executed in silos for better outcomes.

B.

Report the concern to the agile project management office (PMO),

C.

Inform the product owner of the concern so that i can be addressed.

D.

Open up to the team to work collaboratively to achieve the outcomes.

Buy Now
Questions 156

A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.

Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three)

Options:

A.

Prioritize stakeholders based on the project phase and need.

B.

Develop a stakeholder impact influence matrix to determine the level of engagement

C.

Perform a stakeholder assessment to align with the project objectives.

D.

Include all stakeholders in the stakeholder engagement plan and provide the same level of communication.

E.

Classify and rank stakeholders based on their positions in the organization.

Buy Now
Questions 157

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile

practices, which are relevant to the project.

What should the project manager do in order to gain buy-in from the different stakeholders?

Options:

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.

B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.

C.

Ask the project management office (PMO) to get buy-in from the stakeholders, because agile is an approach that differs from their previous

ways of working.

D.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.

Buy Now
Questions 158

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

Buy Now
Questions 159

A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as

something that will work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

Options:

A.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver

value incrementally.

B.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the

project.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the end

of the project.

D.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

Buy Now
Questions 160

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?

Options:

A.

Request the team to work more for on-time delivery.

B.

Request the team to focus on doing better planning.

C.

Request the replacement of certain team members.

D.

Request management for a high-performing team.

Buy Now
Questions 161

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

Options:

A.

Verified applicable budget inputs related to this project

B.

Assigned the same project resources to this project

C.

Estimated a budget for the project's quality management

D.

Determined a budget reserve for this project

Buy Now
Questions 162

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?

Options:

A.

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.

B.

Create a salience model to determine if the employee will have influence on the project.

C.

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.

D.

Assess the influence and power of the employee to see if the employee will add value.

Buy Now
Questions 163

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

Options:

A.

Use a burndown chart to provide transparency.

B.

Use a kanban board to increase accountability.

C.

Use a product backlog to manage changes.

D.

Use a burnup chart to provide transparency.

Buy Now
Questions 164

A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its

competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?

Options:

A.

Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step.

B.

Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays.

C.

Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step.

D.

Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company’s industry.

Buy Now
Questions 165

A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?

Options:

A.

Schedule status meetings with all stakeholders to allow their participation in all project discussions and reports.

B.

Analyze both internal and external stakeholders and develop a customized engagement strategy for each stakeholder.

C.

Involve only the internal stakeholders, as the external stakeholders should not have access to confidential information.

D.

Classify all high-risk stakeholders and request that the project sponsor communicate directly with them.

Buy Now
Questions 166

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?

Options:

A.

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.

B.

Review the terms of reference of the steering committee to include the vendor management head.

C.

Work with the sponsor on a communications management plan to obtain support from the vendor management head.

D.

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.

Buy Now
Questions 167

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?

Options:

A.

Seek to understand the sentiments of each team member and then work with them to address their concerns.

B.

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.

C.

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.

D.

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.

Buy Now
Questions 168

A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing.

What should the project manager do?

Options:

A.

Ask the stakeholders to develop all of the project artifacts so the project team can continue their scheduled activities.

B.

Create the project management plans with the project team and share the documents with the stakeholders.

C.

Continue working on scheduled tasks to avoid delaying the project and leave the development of project artifacts for later.

D.

Adapt the project management plans and documents from previous executed projects in order to save time.

Buy Now
Questions 169

An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery

What should the project lead do?

Options:

A.

Escalate the problem to the product owner.

B.

Ask the PMO to review the framework

C.

Request the PMO to define a new framework.

D.

Plan a brainstorming session with the project team

Buy Now
Questions 170

A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?

Options:

A.

Project sponsors

B.

Other project managers

C.

Business unit managers

D.

Program managers

Buy Now
Questions 171

After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.

What should the scrum master do?

Options:

A.

Ask the product owner to update the stakeholders' contact information at every meeting to address any changes.

B.

Update the stakeholder's information and inform them that they must make the team aware of any changes.

C.

Consider it a loss since the stakeholder should have ensured the contact information was up to date.

D.

Check the stakeholder register and ensure that every stakeholder's information is correct and current.

Buy Now
Questions 172

A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.

How should the project manager continually evaluate the effectiveness of the virtual team's engagement?

Options:

A.

Collect feedback from the team to discuss alternatives to enhance the communication.

B.

Conduct individual meetings to create a trusting environment with team members.

C.

Establish periodic face-to-face meetings and address the communication topic.

D.

Hold meetings in accordance with the team members’ preferences and availability.

Buy Now
Questions 173

Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.

What should the project manager do to obtain agreement from both companies and acceptance from marketing?

Options:

A.

Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.

B.

Create a special release 4 weeks after the current release to deliver the new feature in its entirety.

C.

Add the new feature to the list for the next release and continue working on the current release.

D.

Stop the current release work for 4 weeks in order to work and deliver the new feature completely.

Buy Now
Questions 174

A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?

Options:

A.

Define the project management plan.

B.

Estimate the resources needed for the activities.

C.

Consult subject matter experts (SMEs) to review the schedule.

D.

Estimate the cost of each activity.

Buy Now
Questions 175

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project.

What should the project lead do?

Options:

A.

Ask that estimations be provided only by senior developers.

B.

Allocate more time for estimation in the sprint planning.

C.

Review and update the estimations in the daily standup.

D.

Recommend a different estimation method in the retrospective.

Buy Now
Questions 176

A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no

longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects,

and there is no capacity for any developer to take on additional work.

What should the project manager do next to fulfill this resource need?

Options:

A.

Determine resource allocation options based on project priority.

B.

Apply changes to the existing resource allocations and inform the development manager.

C.

Meet with the sponsor to determine how to rebaseline the schedule.

D.

Inform the sponsor of the situation and request an extension of the target completion date.

Buy Now
Questions 177

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

Options:

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

Buy Now
Questions 178

Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?

Options:

A.

Sign the contract as per the original terms but allow the successful bidder to submit a new contract price.

B.

Amend the contract terms and sign a revised contract with the successful bidder.

C.

Retender the entire scope because the terms of the contract have changed significantly.

D.

Discuss the new terms with the successful bidder to assess its impact on the contract price.

Buy Now
Questions 179

During a project review session with key stakeholders, a senior manager raises a concern that the product being shown is not meeting the client's expectations. The project manager has noticed that although the team is meeting project deadlines, there are a large number of open quality issues that have not been addressed.

What should the project manager do?

Options:

A.

Meet with the project stakeholders to review the scope and ask for a time extension to address the quality issues.

B.

Work with the project team to identify the gaps and address the critical issues based on defined outcomes.

C.

Advise the team to continue moving forward because meeting the milestones is more important and the issues can be fixed later.

D.

Ask the team to reprioritize and focus on fixing the quality issues that were identified by the stakeholders during the meeting.

Buy Now
Questions 180

A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool's scalability to support their business needs.

How should the project manager resolve this conflict and reach a consensus?

Options:

A.

Escalate this to senior management and ensure that the team's acceptance is achieved.

B.

Communicate to the two teams that the tool has won per the selection process and they need to accept the outcome.

C.

Ignore the conflict as the tool is selected per the proposal guidelines and the project is complete.

D.

Discuss the outcome of the proposal process and the ranking, then influence the team for acceptance.

Buy Now
Questions 181

A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important natural reserve was impacted and prior consultation was not done by the project team.

What should the project manager verify first?

Options:

A.

Stakeholder engagement plan

B.

Risk management plan

C.

Business case

D.

Cost-benefit analysis

Buy Now
Questions 182

A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?

Options:

A.

Reject the request as being too late and leading to major scope creep.

B.

Submit the request to the change control board (CCB) for a decision.

C.

Negotiate with the project sponsor on the possible alternatives.

D.

Determine the possible impact of this change on all aspects of the project.

Buy Now
Questions 183

A new project manager has been assigned to an ongoing project because of the promotion of their predecessor. The new project manager needs to understand the levels of decision-making authority on the team.

Which document should the incoming project manager review?

Options:

A.

Resource management plan

B.

Communications management plan

C.

Information management plan

D.

Stakeholder engagement plan

Buy Now
Questions 184

A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary.

What should the project manager have done before the beginning of the project?

Options:

A.

Conducted a survey to determine if the team was willing to adopt agile ceremonies on the current project.

B.

Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.

C.

Discussed with the product owner and requested assistance by requiring the adoption of agile ceremonies.

D.

Discussed with the project sponsor about convincing the team to adopt the agile ceremonies as part of their routine.

Buy Now
Questions 185

An email arrives shortly after the beginning of a sprint. It is from a key project stakeholder who is unfamiliar with agile approaches and has a serious complaint about future work that has been scheduled. The stakeholder is insisting that a future work package be removed from the backlog entirely, claiming that it is unnecessary.

What should the project manager do?

Options:

A.

Address the stakeholder's request at the daily standup and ask for the team's opinion.

B.

Discuss the stakeholder's request at the next retrospective meeting.

C.

Invite the stakeholder to the backlog refinement meeting to discuss their request.

D.

Alter the backlog to accommodate the stakeholder's request.

Buy Now
Questions 186

A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.

How should the project manager communicate with the local community?

Options:

A.

Social media

B.

Email

C.

Meetings

D.

Newspapers

Buy Now
Questions 187

A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?

Options:

A.

Quality process

B.

Quality management plan

C.

Organizational process assets (OPAs)

D.

Project charter

Buy Now
Questions 188

Construction work is preventing the project team members from entering the building where their offices are located.

What should the project manager do next?

Options:

A.

Inform the authorities so that they are aware of the situation and can take appropriate action.

B.

Continue business as usual since the construction work is not related to the project.

C.

Select the next action to be taken according to the risk management plan.

D.

Communicate with the stakeholders about the construction and ask for direction.

Buy Now
Questions 189

Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.

What should the project manager do next to address this issue?

Options:

A.

Halt all processes until procurement and implementation of solutions are completed.

B.

Place a hold on activities until the team can resume the work on-site.

C.

Ask the team members to proceed independently while examining needs and alternatives.

D.

Obtain and implement the sponsor's recommendations for a solution.

Buy Now
Questions 190

A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.

What should the project manager do first?

Options:

A.

Meet with the team to define together a plan that would help them deliver despite the budget cuts.

B.

Work with the team to understand what can motivate them to try and complete the project.

C.

Remind the team of their commitment with the client and the need to adapt to the client's needs.

D.

Call the sponsor and ask for a meeting to clarify the scope before working any further on the project.

Buy Now
Questions 191

A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

PMP Question 191

Options:

Buy Now
Questions 192

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

Options:

A.

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.

B.

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.

C.

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

D.

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.

Buy Now
Questions 193

A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for

providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available

in 2 weeks due to some unforeseen problems.

What should the project manager do next?

Options:

A.

Apply the terms and conditions of the contract with penalties.

B.

Issue a change request to reflect the anticipated date for training.

C.

Help the customer find an alternative location to start the training.

D.

Update the project schedule with the new date for training.

Buy Now
Questions 194

A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule, with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.

What should the project manager do first?

Options:

A.

Review the project schedule and ask for the contingency reserve to crash the project.

B.

Meet the project team and stakeholders to identify the root cause of the issue and develop a solution.

C.

Review the lessons learned register with the former project manager in a private meeting.

D.

Meet the project team to assert authority and reassign the project tasks for a timely delivery.

Buy Now
Questions 195

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

Options:

A.

Ask the other project manager to change the delivery methodology.

B.

Request that the other project manager develop a work breakdown structure (WBS).

C.

Participate in the other project's daily standup meetings.

D.

Align with the other project manager's high-level project time lines.

Buy Now
Questions 196

The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?

Options:

A.

Requirements traceability matrix

B.

Risk management plan

C.

Project scope statement

D.

Requirements management plan

Buy Now
Questions 197

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.

Incremental delivery and frequent backlog refinement based on user feedback

C.

Iterative development and collection of frequent feedback from project team members

D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Buy Now
Questions 198

A project manager notices that the project team is encountering product issues while coding client-specific developments. The project manager foresees delays to the project's timeline because of these product issues.

Which methods should the project manager use to communicate project delays and other difficult messages to stakeholders?

Options:

A.

Oral feedback, project meetings, and reporting

B.

Project meetings and reporting

C.

Project meetings and oral feedback

D.

Written feedback, project meetings, and reporting

Buy Now
Questions 199

There is a conflict on an agile project about following organizational processes, many of which do not add any value to the project. To resolve this, which one of the following

should be regarded with the highest priority?

Options:

A.

Needs of the customer

B.

Needs of the project manager

C.

Needs of the agile lead

D.

Needs of the organization

Buy Now
Questions 200

A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.

What should the project manager do?

Options:

A.

Reach out to the stakeholder via phone to explain that all decisions have been agreed upon with their predecessor.

B.

Provide the stakeholder with a link to a file-sharing site where the supporting documents for decisions are filed.

C.

Schedule a meeting with the stakeholder to provide an overview of the project, including the agreed-upon decisions.

D.

Update the risk register with a new risk of potential project changes as a result of stakeholder misalignment.

Buy Now
Questions 201

A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.

One particular pain point is the transition to operations, where the issues usually arise.

What should the project manager do to improve this scenario?

Options:

A.

Increase the focus on backlog items that cover support requirements, as well as product manuals and operation guides.

B.

Ask the support/operation team to participate in the daily standup meetings to contribute to the project's progress.

C.

Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.

D.

Foster stakeholder participation by engaging them early on the backlog discussions.

Buy Now
Questions 202

A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of

sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.

What should the project manager do?

Options:

A.

Introduce a float.

B.

Adjust the budget.

C.

Adjust the project time line.

D.

Fast track the project.

Buy Now
Questions 203

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

Options:

A.

Recurrent team meetings are planned to control the budget against future uncertainties.

B.

Probabilistic analysis was used to develop the budget to address future uncertainties.

C.

The budget was developed by using the lessons learned from previous project data.

D.

Feedback from stakeholders will be addressed at each board meeting to adapt the budget.

Buy Now
Questions 204

A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.

What should the project manager do next?

Options:

A.

Discuss extending the mass production timeline by 3 months with the project sponsor.

B.

Meet with senior management to discuss the possibility of an extension to the project timeline.

C.

Engage a consultant to shorten the certification process to meet the schedule requirement.

D.

Assess and evaluate the certification process and understand the best and worst case scenarios.

Buy Now
Questions 205

A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project

manager is confused since the entire team is located in the same time zone and believes there are other factors at play.

What should the project manager do next?

Options:

A.

Rectify ground rule violations.

B.

Review performance formally.

C.

Examine the team's virtual needs.

D.

Implement new options.

Buy Now
Questions 206

A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings

among team members. The project sponsor has allocated a monetary award.

How should the project manager utilize the award?

Options:

A.

Meet with the team members and ask them how to spend the reward.

B.

Arrange a luncheon for all team members and include team-building sessions.

C.

Draft a points system to allocate a portion of the money for each resource.

D.

Allocate the reward to the team leaders to spend on the team as they see fit.

Buy Now
Questions 207

A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. As of now, the earned value (EV) is 145 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day.

What is the estimate at completion (EAC)?

Options:

A.

334 person/day

B.

285 person/day

C.

310 person/day

D.

315 person/day

Buy Now
Questions 208

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

Options:

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Buy Now
Questions 209

During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.

What should the project lead do?

Options:

A.

Communicate to the stakeholders that the project has to be delayed for two weeks.

B.

Ask the project team to accept the shorter estimate as it is important to keep a good relationship with the product owner.

C.

Decide what should be the time estimate and proceed with the planning meeting.

D.

Educate the product owner that the project team members are the most appropriate group for assessing the effort.

Buy Now
Questions 210

A project team Is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.

What should the project manager do?

Options:

A.

Discuss with the team how the project objectives can be met.

B.

Request that the sponsor increase the bonus for high performers.

C.

Schedule a team-building activity to boost the team's morale.

D.

Organize a team meeting to remind the team of the ground rules.

Buy Now
Questions 211

A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team's effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.

How should the project manager handle the situation?

Options:

A.

Review validation and control procedures.

B.

Discuss reducing interruptions with the sponsor.

C.

Perform stakeholder requirements activities.

D.

Approach the sponsor about using an agile approach.

Buy Now
Questions 212

A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of

the team members were stressed due to over commitments.

What should the project manager do?

Options:

A.

Help the team members by organizing regular stress-relieving and team- building sessions.

B.

Request additional resources to continue delivering value while reducing team stress.

C.

Support the team during the planning phase to only commit to what they are able to deliver.

D.

Ask individual team members to plan staggered leave to avoid becoming stressed.

Buy Now
Questions 213

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

Options:

A.

Update the lessons learned report and the risk log to reflect that this risk has materialized.

B.

Revise the project management plan and move the task to a time when the technical resource will be available.

C.

Consult the risk register for an appropriate planned risk response and implement.

D.

Review the business requirement with stakeholders and exclude the task assigned to the technical resource.

Buy Now
Questions 214

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of

completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next

milestone. This change can be perceived as poor performance by the current assignees.

What should the project manager do?

Options:

A.

Organize a team meeting and inform the team members that, as the person accountable for delivery, they decided to change the task allocation.

B.

Ask the less experienced team member privately to stop working on the task and inform another team member that the work has been reassigned.

C.

Ask the more experienced team member privately to take the task and inform the other team members that work has been reassigned.

D.

Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation.

Buy Now
Questions 215

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

Options:

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

Buy Now
Questions 216

A customer initiated a minor scope change and expects this to be completed without delays or additional costs. The project manager believes that they have adequate

authorization to make the decision themselves but is not quite sure.

What should the project manager do next?

Options:

A.

Use the project contingency and implement the change without charging the customer, since the customer's satisfaction is top priority.

B.

Exploit this change opportunity and calculate the cost, risk, and time, then add a reasonable margin and submit to the customer.

C.

Use the Perform Integrated Change Control process and submit this to the change control board (CCB) for approval.

D.

Keep the change pending and decide to take this up as part of final settlement at the end of the project.

Buy Now
Questions 217

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Buy Now
Questions 218

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project

execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.

What should the project manager have done to prevent this from happening?

Options:

A.

Ensured the stakeholder anticipated obstacles to achieving financial closure on the remaining funds.

B.

Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.

C.

Ensured the stakeholder who was providing additional funds remained interested in the project.

D.

Ensured the project team monitored and reviewed the project risk register periodically.

Buy Now
Questions 219

A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.

What should the project manager do?

Options:

A.

Recommend that the team use industry-accepted guidelines.

B.

Contact the chief information officer (CIO) and request the enterprise development guidelines.

C.

Contact the previous team and ask for a copy of their guidelines.

D.

Recommend that the team develop their own guidelines.

Buy Now
Questions 220

A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.

What should the project manager have done to avoid this situation?

Options:

A.

Asked the project sponsor to review the budget

B.

Updated the budget before moving to another stage of the project

C.

Added enough budget to cover all uncertainties

D.

Used past projects as a reference during budget estimations

Buy Now
Questions 221

A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process

What should the project manager do?

Options:

A.

Update the communications management plan to satisfy the client's request

B.

Request the client to attend the daily meetings with the project team

C.

Encourage the client to interact with the protect collaboration platform

D.

Ask the product owner to frequently communicate with the stakeholders

Buy Now
Questions 222

A project is starting with a team that is located all over the world. None of the team members have worked together before. The project goal is ambitious with an aggressive timeline.

What should the project manager do?

Options:

A.

Ask for financial support to set up a physical meeting for the team.

B.

Create a virtual room for the team to facilitate their collaboration.

C.

Schedule quarterly in-person meetings to enhance the team's relationships.

D.

Facilitate a virtual session with the team to start planning as soon as possible.

Buy Now
Questions 223

A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.

What should the project manager do?

Options:

A.

Acknowledge the impediments and facilitate their resolutions.

B.

Note the impediments and escalate them to the product owner.

C.

Note the impediments and work on addressing them later.

D.

Assign actions to all stakeholders and oversee their implementation.

Buy Now
Questions 224

The project sponsor wants to obtain quick feedback from end users for a product under development. The roadmap is extensive and will not be completed for quite some time.

What should the project manager do?

Options:

A.

Advise the stakeholders that they will need to wait until development is completed in order to get actual end-user feedback.

B.

Hire additional resources to accelerate the schedule and deliver the product faster in order to get actual end-user feedback.

C.

Advise the stakeholders to share images of the finished product in order to obtain valuable feedback from end users.

D.

Work with the stakeholders to determine the minimum requirements needed to get valuable end-user feedback and revise the project schedule.

Buy Now
Questions 225

A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project

manager use to manage these risks using an agile approach?

Options:

A.

Develop an agile risk matrix to track, assess, and evaluate the uncertainty of the project.

B.

Implement a scrum risk retrospective to analyze the risks at the end of the project.

C.

Assign an agile risk manager to better understand and track the project risks.

D.

Evaluate the risks constantly and reprioritize work as the project progresses.

Buy Now
Questions 226

A project team has been working together for about 2 years. One of the team members has consistently shown high performance and stood out among their peers during the execution of the project.

How should the project manager recognize high performance?

Options:

A.

Thank the team member privately to avoid conflict among the team members.

B.

Acknowledge the high-performing team member in the next team meeting.

C.

Choose a reward for the team member that aligns with their personal goals.

D.

Ask the sponsor to approve a bonus for the high-performing team member.

Buy Now
Questions 227

A project manager's project relies on services from a department that has a new leader. Since the new leader was appointed, the services from their department have been slow which threatens the project's delivery deadline.

What should the project manager do?

Options:

A.

Add the issue to the issue log and communicate the issue in the next regular report to project stakeholders.

B.

Escalate the issue to the project sponsor notifying them of the slow services from the department.

C.

Send all service requests to the department earlier in the project to lessen the impact on the delivery date.

D.

Arrange a meeting with the leader to explain the project's needs and understand the leader's perspective.

Buy Now
Questions 228

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

Options:

A.

Time and materials (T&M) with an agile approach

B.

Cost reimbursable contract with a predictive approach

C.

Fixed-price contract with a predictive approach

D.

Memorandum of understanding (MOU) with an agile approach

Buy Now
Questions 229

A project to develop an enterprise resource system for a university is in the planning phase. The project has internal stakeholders such as operational departments, students, and academic staff, as well as global stakeholders who receive the information from the university on a regular basis. All the stakeholders have very different expectations and needs from the system.

What should the project manager do to ensure effective communication?

Options:

A.

Plan to implement a united communication platform, where all information about the project will be shared and updated regularly.

B.

Ensure all the information about the project implementation is provided to all of the different stakeholders in a unified communication format.

C.

Define communication target groups and provide information, messages, channels, and the frequency of communication for each group.

D.

Arrange an information session for all of the stakeholders about the plans for handling their various communication needs.

Buy Now
Questions 230

A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.

What should the project manager do first?

Options:

A.

Evaluate the cost of the additional requested work.

B.

Evaluate the impact and submit a change request.

C.

Discuss the requested change with the sponsor.

D.

Discuss the requested change with the team.

Buy Now
Questions 231

While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere. What

should the project manager do to ensure a smooth delivery of the product?

Options:

A.

Involve the client in risk identification.

B.

Agree with the client on acceptance criteria.

C.

Involve the client in a performance gap analysis.

D.

Agree with the client on a new project charter.

Buy Now
Questions 232

A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.

What should the project manager do?

Options:

A.

Proceed with the direction given by the director for the regulatory liaison, as they are the subject matter expert (SME).

B.

Follow the CEO's directive, as they are the highest authority in the company and are the ultimate decision maker.

C.

Meet with the CEO and the director to discuss and register it as a major risk if agreement cannot be made.

D.

Schedule final testing activities in parallel with the regulatory approval activities to compensate for lost time.

Buy Now
Questions 233

At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.

What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?

Options:

A.

Facilitate a conflict discussion and find a win-win situation for both parties so that they can continue to work together.

B.

Allocate additional key resources and document who will be held accountable for the various aspects of the team's workflow.

C.

Clarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).

D.

Set up a group discussion after each requirement is discussed to understand the dependencies that can impact workflow.

Buy Now
Questions 234

A project manager has an engineering team mostly comprised of new hires. The project manager has to carefully predict in which stage of the project they will need to spend most of their time to ensure the team is properly integrated and performing well.

In which stage of the project would the project manager need a greater effort to lead them?

Options:

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Buy Now
Questions 235

A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.

What should the project manager do first?

Options:

A.

Host a requirements workshop and ask the stakeholders to prioritize the requirements based on critical needs.

B.

Review the requirements and determine which of them can be removed, then advise the stakeholders of the changes.

C.

Meet with the sponsor to obtain their feedback regarding critical requirements in the view of senior management.

D.

Reach out to the sponsor and request additional budget and capacity in order to complete the project.

Buy Now
Questions 236

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

Options:

A.

Facilitate the meeting so anyone can share their ideas and is heard during the session.

B.

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.

C.

Discuss the product owner's recommendations with the team and implement the agreed-on solutions.

D.

Discuss the recommendations with the test manager and request better quality control.

Buy Now
Questions 237

A project manager is leading a project team that consists of five team members. One of the team members, a senior technical staff member, always criticizes the ideas of other members during team meetings. However, this senior technical member is not performing well on their own daily tasks. Other team members are frustrated and have become silent in meetings.

What should the project manager do?

Options:

A.

Reduce the team meeting frequency and seek input separately from team members.

B.

Ask human resources (HR) to reassign the senior technical staff member.

C.

Encourage other team members to provide one another with their valuable ideas.

D.

Provide feedback to bring the team members' focus back to the performance of their daily tasks.

Buy Now
Questions 238

A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager

do to get this information?

Options:

A.

Organize a one-on-one conversation with each stakeholder.

B.

Request stakeholders articulate their motivations at the kick-off meeting.

C.

Email project objectives to all stakeholders and ask for endorsement.

D.

Identify each stakeholder's motivations from the business case.

Buy Now
Questions 239

A highly critical project is in jeopardy due to missing professional resources. What should the newly assigned project manager do first?

Options:

A.

Find available professionals within the organization to fill the gaps.

B.

Allocate funding for seeking external professionals to fill the gaps.

C.

Determine the possibility for team members to split up the required tasks.

D.

Request additional budget for team training for the missing expertise.

Buy Now
Questions 240

A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.

Which tool should the project manager use?

Options:

A.

Retrospective meetings

B.

Daily meetings

C.

Kanban board

D.

Gantt chart

Buy Now
Questions 241

PMP Question 241

An agile team has sized all of the features for the release. Using the table above, how many sprints will it take to complete this release if the team is expecting to have a

velocity of 10 story points per sprint?

Options:

A.

1

B.

95

C.

6

D.

4

Buy Now
Questions 242

A project manager is leading a project in a heavily regulated industry. Match the considerations on the left with the correct compliance plan categories on the right.

PMP Question 242

Options:

Buy Now
Questions 243

A project manager is assigned to a major system integration project that is currently in the execution phase. The project relies heavily on the presence and availability of certain products and services, which are provided at various periods throughout the project phases by selected third-party vendors.

What should the project manager do to ensure the successful execution of the project?

Options:

A.

Perform procurement control checks throughout the project

B.

Activate the mitigation plan for the procurement risks

C.

Oversee the selection process for the vendor to procure the needed products and services

D.

Ask the procurement department to select the vendor using established processes

Buy Now
Questions 244

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)

Options:

A.

Develop the project management plan based on the requirements requested by the customer.

B.

Develop the application as requested by the customer, based on the approved project requirements.

C.

Plan a minimum viable product (MVP) to get early feedback from the customer.

D.

Facilitate a focus group to assess the functionality before development.

E.

Use an agile approach to deliver the product based on sprints.

Buy Now
Questions 245

As part of its growth strategy, management is providing all of its ongoing projects with junior employees and is requesting experienced team members to mentor them. The experienced employees argue that the mentoring program will not add value to their projects and will limit their ability to deliver.

How should the project manager handle this situation?

Options:

A.

Recommend to management that the junior employees should receive formal training and courses.

B.

Schedule time with all of the project team members since it is the role of the project manager to mentor the team.

C.

Allocate specific time for experienced team members to mentor the junior employees.

D.

Assign an instructor to mentor the junior employees so that the experienced team members can focus on project tasks.

Buy Now
Questions 246

A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.

What should the project lead do?

Options:

A.

Use Pareto techniques to identify the knowledge required by the majority of the team.

B.

Recommend putting the project temporarily on hold and focus on onboarding and training.

C.

Develop a training curriculum and schedule training delivery throughout the project.

D.

Document the processes and organize a week-long, off-site meeting with the project team.

Buy Now
Questions 247

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

Options:

A.

Increase the team capacity to finish the project on time.

B.

Register an issue and escalate it to the project sponsor.

C.

Invite the stakeholders to discuss a new prioritization.

D.

Estimate the impact and consult with the product owner.

Buy Now
Questions 248

To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.

How should these issues be resolved?

Options:

A.

Individual team members should discuss solutions to resolve the issues after the Scrum is concluded.

B.

The scrum master should ensure the appropriate escalation to resolve the issues.

C.

The product owner owns the open issues until they are resolved.

D.

Individual team members need to submit service desk tickets to resolve the issues.

Buy Now
Questions 249

The project team is conducting iteration planning and having difficulty evaluating a new technology that will be used in this iteration. What should the project lead do?

Options:

A.

Hire an external subject matter expert (SME) to help with design and implementation.

B.

Coach the team to determine a path forward to achieve an efficient solution.

C.

Provide technical guidance on complexity assessment.

D.

Guide the team with estimating the time required.

Buy Now
Questions 250

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a

low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that

this could be a high risk for the project.

Which action should the project manager take?

Options:

A.

Facilitate a supportive level of engagement for this stakeholder.

B.

Ask the project sponsor for advice as it might be possible to work with another stakeholder.

C.

Perform a qualitative risk analysis using a probability and impact matrix.

D.

Ensure the key information is accurate and monitor the situation as the project progresses.

Buy Now
Questions 251

Drag the items on left side to the matching term within the correct project approach on the right side.

PMP Question 251

Options:

Buy Now
Questions 252

A team has been working for some time on a project with incremental deliveries. The project manager noticed that one of the team members is less engaged in team meetings, yet delivers promptly. While discussing the source of demotivation, the team member informed the project manager that this is due to a feeling of lack of skills in dealing with new tasks.

How should the project manager address the issue?

Options:

A.

Create a self-paced learning plan with the team member during working hours, with checkpoints on learning progress.

B.

Review which tasks the team member would feel more motivated to work on, then assign those tasks to the team member.

C.

Replace the team member with a resource from another team who already has the requisite training and skills needed.

D.

Discuss growth and development needs with the team member and provide learning opportunities accordingly.

Buy Now
Questions 253

In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery.

What should the project manager do to help this team member?

Options:

A.

Assign another senior team member to coach the team member.

B.

Empower the team member to make decisions.

C.

Mentor the team member on a regular basis.

D.

Address the team member's performance accordingly.

Buy Now
Questions 254

Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.

What should the project manager do?

Options:

A.

Assess the benefit of using new technology versus old technology.

B.

Hire project resources with experience using the new technology.

C.

Propose training for the project team in batches on the new technology.

D.

Request incentives for the team to use the new technology.

Buy Now
Questions 255

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

Options:

A.

Give the change to the scrum master to investigate how much additional effort the change will require.

B.

Tell the customer that the requirement change will be put into the next project phase if management approves.

C.

Validate the requirement change with the product owner and development team before redefining the scope.

D.

Escalate to management for approval since the change was not included in the original requirements.

Buy Now
Questions 256

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?

Options:

A.

Modify the project schedule to accommodate the delays in the purchase of services.

B.

Request that the purchasing tasks be outsourced through an existing purchasing vendor.

C.

Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.

D.

Ask the project team to keep developing other tasks that do not depend on the purchase of services.

Buy Now
Questions 257

Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.

How should the project manager approach the situation?

Options:

A.

Intervene in the deliberation process and weigh in on which approach would be better to use.

B.

Deliberate with the team moving the item to the product backlog and taking up the next item in the list.

C.

Stop the deliberation process and ask the team to take a vote using the nominal group technique.

D.

Allow the team to continue deliberating until the team reaches a consensus on the desired approach.

Buy Now
Questions 258

A healthcare company is in the process of deploying an innovative healthcare solution globally. The project team has completed a limited release.

The stakeholders have raised concerns about global healthcare guidelines and risks.

What should the project manager do next?

Options:

A.

Evaluate lessons learned from similar projects prior to deployment.

B.

Perform a qualitative risk analysis on the identified project risks.

C.

Review compliance and regulatory requirements with stakeholders.

D.

Conduct a feasibility analysis of deploying the solution globally.

Buy Now
Questions 259

An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.

What should the project manager do?

Options:

A.

Provide mentoring to the CFO, who is a key stakeholder in the project, and clarify the benefits of an agile approach.

B.

Ask the CEO to intervene by asking for support from the executive board to accelerate the company's transformation.

C.

Apply influence with other key stakeholders on the board to mitigate any risks that may be generated by the CFO's position on the matter.

D.

Submit a report to all key stakeholders on the cost-benefit analysis of the new approach and detail how the company will save money.

Buy Now
Questions 260

A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.

What should the project manager do to avoid these situations?

Options:

A.

Review the risk management plan.

B.

Review the resource management plan.

C.

Review the communications management plan.

D.

Review the stakeholder engagement plan.

Buy Now
Questions 261

A project manager is looking for ways to keep the budget on track throughout the project life cycle.

What should the project manager do to ensure that happens?

Options:

A.

Evaluate and test all budget variances.

B.

Baseline the project budget and schedule.

C.

Prioritize high-cost tasks and monitor them.

D.

Use metrics to track the cost performance.

Buy Now
Questions 262

A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).

What should the project manager do to avoid the same problem in future projects?

Options:

A.

Review the responsibility matrix at the customer kick-off meeting.

B.

Rely on internal SMEs for expert input on implementing the user stories.

C.

Include a contractual penalty for delays created by the customer.

D.

Require customer SMEs to attend at least half of the daily meetings.

Buy Now
Questions 263

During a progress review meeting, the project sponsor requests a complete revamp of the product roadmap to meet the strategic objectives based on market conditions. This change will result in a completely new product.

What should the project manager do first?

Options:

A.

Put the current project work on hold and revisit the scope based on the impacts.

B.

Perform a root cause analysis to assess which deliverables can be reused by the team.

C.

Discuss with the team and implement the revisions that were requested by the sponsor.

D.

Update the business case and seek sponsor approval on the modified project scope.

Buy Now
Questions 264

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Buy Now
Questions 265

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.

Call for a team meeting to identify the root cause for the declining performance

B.

Estimate the baseline impacts and submit a change request.

C.

Implement compression techniques to bring the project back on track.

D.

Review the resource management plan and organizational assets

Buy Now
Questions 266

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

Options:

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Buy Now
Questions 267

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

Options:

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

Buy Now
Questions 268

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?

Options:

A.

Empower team members to participate in decision-making and take ownership of actions.

B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.

C.

Encourage team members to network so that they know each other's cultural backgrounds.

D.

Provide a relaxed work schedule policy and encourage team members to work from home.

Buy Now
Questions 269

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.

Conducted agile training for all employees ranging from the project teams through

mid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets

(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determined

the future state.

D.

Hired a third-party agile delivery team to do the implementation.

Buy Now
Questions 270

Match the project situation on the left to the meeting on the right where the situation could occur.

PMP Question 270

Options:

Buy Now
Questions 271

An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.

Which ceremony should be used in developing this register?

Options:

A.

Sprint plans

B.

Retrospective results

C.

Sprint report

D.

Project status report

Buy Now
Questions 272

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

Options:

A.

Ask the team to work on the complaint raised by the clients.

B.

Escalate the issue raised by the clients to the project sponsor,

C.

Develop a solution with the team to identify the inventory level.

D.

Work with the team and the product owner to define the next steps.

Buy Now
Questions 273

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

Options:

A.

Explore the minimum requirements of the product and their feasibility.

B.

Explain the resource constraints of the project to management.

C.

Outsource the management of the product to an external team.

D.

Conduct a detailed risk analysis to highlight the risks in the project.

Buy Now
Questions 274

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured the project repository is up to date.

B.

Updated the job descriptions for all team roles.

C.

Provided specialist training for all team members.

D.

Made an effort to reemploy the senior project team member.

Buy Now
Questions 275

A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?

Options:

A.

Evaluate the engagement needs of stakeholders.

B.

Distribute weekly status emails to stakeholders.

C.

Engage the sponsor on the behavior of stakeholders.

D.

Conduct weekly update meetings with stakeholders.

Buy Now
Questions 276

An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

Options:

A.

Go back to the customer and explain that they cannot implement the feature completely in one iteration.

B.

Reduce the scope of the feature to fit into one iteration and deliver it to the customer

C.

Ask the customer to simplify the feature so that it can be implemented in one iteration

D.

Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations

Buy Now
Questions 277

After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project

How should the project manager handle this situation?

Options:

A.

Comply with the project sponsor's request to not archive the project artifacts.

B.

Consult with the project management office (PMO) for guidance on project artifacts.

C.

Archive the project artifacts on the project manager's local computer for future reference.

D.

Document the project sponsor's instructions as the archived project artifacts.

Buy Now
Questions 278

In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.

What should the project manager do to manage this conflict?

Options:

A.

Schedule a meeting with the team member and their manager to discuss the issue.

B.

Talk to the project sponsor about the team member's attitude.

C.

Schedule a one-on-one meeting with the team member to talk about it and get their

cooperation.

D.

Find another person to replace this team member.

Buy Now
Questions 279

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.

C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.

D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

Buy Now
Questions 280

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?

Options:

A.

Ask for additional team members to maintain the velocity

B.

Implement a checkpoint in the iteration to verify if the team is on track

C.

Conduct a focused retrospective to help the team to discover the root cause

D.

Ask the team to have a lower commitment for the next iteration

Buy Now
Questions 281

A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.

What should the project manager do?

Options:

A.

Hold separate retrospective meetings for both the vendor team and the internal team.

B.

Schedule a preliminary meeting with the account manager from the vendor and the test manager.

C.

Establish a clear agenda for the meeting and remind the vendor and internal teams that the scope is to improve the process.

D.

Invite the procurement manager and a representative from the vendor to manage the current tense relationship.

Buy Now
Questions 282

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.

Which release strategy should the project manager recommend?

Options:

A.

A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity

B.

An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country

C.

A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues

D.

A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time

Buy Now
Questions 283

In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement

How should the project manager respond to the suggestion?

Options:

A.

The change should be considered and immediately added to the product backlog.

B.

The change should be considered and presented to the project sponsor for approval

C.

The change should be considered because it will help the team work more efficiently

D.

The change should not be considered because it adds no value to the end customer

Buy Now
Questions 284

The team architect resigned from the company. The new architect points out a

design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?

Options:

A.

Review the scope management plan.

B.

Update the design with changes.

C.

Request an architecture review.

D.

Update the quality management plan

Buy Now
Questions 285

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)

Options:

A.

Sprint charter

B.

Burndown chart

C.

Company mission and vision

D.

Product backlog

E.

Sprint goal

Buy Now
Questions 286

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

Options:

A.

Create a product backlog

B.

Perform sprint reviews with the team

C.

Assess the previous project velocity

D.

Reduce the story size by splitting stories

Buy Now
Questions 287

A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.

Which evaluation practice should the project lead use to obtain accurate usage data?

Options:

A.

Send out a questionnaire to all users regarding the most useful features.

B.

Embed a feedback form into the system for users to respond.

C.

Interview a sampling of users to obtain the usage data.

D.

Build the functionality in the software to collect the operational usage data.

Buy Now
Questions 288

Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?

Options:

A.

Reaffirm the required project obligations directly with the team member. oy

B.

Ask the team member to explain the reason for the absences.

C.

Assess the impact of the team member's absence on the task involved.

D.

Send a formal letter to the team member stating that their absences are noted.

Buy Now
Questions 289

A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the

scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,

among other critical blockers.

What should the project manager do?

Options:

A.

Request an additional resource to assist in solving all of the impediments listed by the team.

B.

Determine and agree when a situation becomes an impediment to be solved by the scrum master.

C.

Request the team review and prioritize the open impediments to resolve all of them as soon as possible.

D.

Push back, explaining that a self-organized team should address all of the problems to get the work done.

Buy Now
Questions 290

Close to the end of a project, a customer claims that some deliverables have not

been met and starts initiating change requests. What should the project manager do next?

Options:

A.

Refer to the requirements traceability matrix.

B.

Revise the project scope baseline.

C.

Escalate the change request to the project sponsor.

D.

Review the approved project charter.

Buy Now
Questions 291

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Buy Now
Questions 292

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

Options:

A.

Increase the sprint duration to allow the team more time

B.

Prioritize the contents of the backlog and remove some stories

C.

Create a change request to modify the gate review goals

D.

Use the standup meeting to assess impediments and problems

Buy Now
Questions 293

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

    Approved Work Package Cost Estimates: US$9,500

    Contingency reserves: $500 %

    Management reserves: 10% of contingency reserves

    Percent complete of the project: 50%

    Planned percent of the project: 40%

    Actual costs of the project: US$4,500

What is accurate about the project status?

Options:

A.

The actual work is 25% more than the planned work.

B.

The project cost is 10% lower than planned.

C.

The actual work is 25% less than the planned work.

D.

The project cost is 10% higher than planned.

Buy Now
Questions 294

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

Options:

A.

Schedule a meeting with the previous project manager

B.

Submit a change request to the change control board (CCB)

C.

Schedule training for project team members

D.

Conduct an earned value analysis (EVA)

Buy Now
Questions 295

The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.

What should the project manager do first in this situation?

Options:

A.

Meet with the project sponsor as soon as possible to discuss the matter further

B.

Update the issue log to make the project team aware and to develop a strategy

C.

Create a stakeholder engagement plan to help the team formulate a response

D.

Provide the specifications to the project sponsor with some information removed

Buy Now
Questions 296

A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.

What should the project manager tell the team members to focus on?

Options:

A.

Reducing cost for the customer

B.

Delivering value to the customer

C.

Working together as a team

D.

Finishing the project on schedule

Buy Now
Questions 297

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Buy Now
Questions 298

A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)

Options:

A.

High-level product backlog

B.

Key performance indicators (KPls)

C.

Product vision

D.

Schedule performance indexes (SPIs)

E.

Product roadmap

Buy Now
Questions 299

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then share

it with the project sponsor.

B.

Share the organization's decision with the team and make plans to adopt an agile

approach in the upcoming project.

C.

Make a request to human resources for new team members who have agile

experience.

D.

Ask the project sponsor to change the approach back to predictive as that is the

team’s strength.

Buy Now
Questions 300

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.

What should the project manager do to help move the project forward?

Options:

A.

Review documents provided by other teams, such as lessons learned and the risk matrix.

B.

Attend the Scrum of Scrums to identify roadblocks and manage dependencies.

C.

Study the technology to assist the team in decision-making if progress slows.

D.

Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.

Buy Now
Questions 301

During a meeting for product review, a key stakeholder announces that because they are receiving adequate information about the project they will not attend any further meetings. What should the project manager do?

Options:

A.

Log this as an issue in the issue log and address it with the project sponsor.

B.

Ignore the stakeholder as the product is almost complete.

C.

Explain that the needs will be updated in the stakeholder engagement plan.

D.

Inform the stakeholder that changes can happen in this project.

Buy Now
Questions 302

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

Options:

A.

Report the violation to the change control board (CCB) and seek comprehensive

approval for these modifications.

B.

Update the change management plan to define the level of control required for

these types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no action

because the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

Buy Now
Questions 303

A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?

Options:

A.

Contact the functional managers to request substitutes for the conflicting team members.

B.

Send a warning to both team members indicating that if the issue continues, both will be removed from the project.

C.

Schedule a meeting with both team members to understand the issue and facilitate a solution that satisfies both parties.

D.

Escalate both team members to their respective functional managers and let them take the appropriate actions

Buy Now
Questions 304

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

Options:

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

Buy Now
Questions 305

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

Options:

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

Buy Now
Questions 306

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns

that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.

Which action should the project manager take to procure the vehicles?

Options:

A.

Ask the technical team to revise the requirements, even if it requires extra budget.

B.

Arrange a meeting with the client to request additional time to find a new supplier.

C.

Review the existing service contracts to find an option to help procure the vehicles.

D.

Procure the vehicles from another supplier and report the change to the change control board (CCB) later.

Buy Now
Questions 307

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

Options:

A.

Contact the human resource (HR) department for a solution.

B.

Speak with the key team member to clarify the situation.

C.

Conduct a meeting with the team to deliberate on a decision.

D.

Suspend the team member until further notice.

Buy Now
Questions 308

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

Options:

A.

Follow the change management process and work with procurement if needed

B.

Engage an arbitrator to resolve any conflict while handling the new requirement

C.

Add the change to the next sprint to meet the customer's needs

D.

Allocate resources to work on the new feature immediately to complete the request

Buy Now
Questions 309

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

Options:

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

Buy Now
Questions 310

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

Options:

A.

Assess the impact of the new requirements and initiate the change request process.

B.

Work with the product manager and the rest of the team to update the project backlog.

C.

Assess the impact and communicate the updated product roadmap to the stakeholders.

D.

Follow the change management plan to update the risk register so It accounts for the added scope.

Buy Now
Questions 311

In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.

What should the project manager have done to prevent this situation from occurring?

Options:

A.

Analyzed the sponsor's communication requirements.

B.

Confirmed that the portal is providing adequate information.

C.

Verified that the project team is following the communications management plan.

D.

Ensured the sponsor had the necessary skills to use the portal.

Buy Now
Questions 312

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Options:

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

Buy Now
Questions 313

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

Options:

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

Buy Now
Questions 314

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?

Options:

A.

Risk log

B.

Change log

C.

Backlog

D.

Issue log

Buy Now
Questions 315

A project manager is assigned to a strategic communication project that involves

subject matter experts (SMEs), interns, and new recruits. The project manager discovers

that the project is not gaining much traction due to knowledge gaps from the interns. The

budget for training is exhausted and the project needs to be delivered without delay.

Which two actions should the project manager take? (Choose two)

Options:

A.

Identify the sources and specifics of the knowledge gap from the interns and new

recruits.

B.

Hire more SMEs and inform the human resources manager to lay off the

nonperforming interns and new recruits.

C.

Initiate a project change request for additional budget to train the interns and new

recruits.

D.

Ignore the issues with the project and try to deliver the project successfully without

asking for training funds.

E.

Put the interns and new recruits into groups and assign a SME as a mentor.

Buy Now
Questions 316

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

Include knowledge transfer sessions between the project and operations teams at every stage.

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure.

Buy Now
Questions 317

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

Options:

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

Buy Now
Questions 318

One of the service providers on a complex project has been facing resource

availability problems over the last six months. However, the service provider has assured the

project manager that the deliverables will be on time.

How should the project manager address this situation?

Options:

A.

Update the issue log.

B.

Perform a qualitative risk analysis.

C.

Perform a root cause analysis.

D.

Implement a risk response plan.

Buy Now
Questions 319

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

Buy Now
Questions 320

The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors

What should the project manager do?

Options:

A.

Review the assumption log and project management plan for changes.

B.

Identify adequate change management tools to conduct the project

C.

Establish a change control board (CCB) with key stakeholders.

D.

Allow key stakeholders to make some changes to deliver the product faster

Buy Now
Questions 321

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

Options:

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

Buy Now
Questions 322

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Buy Now
Questions 323

A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.

What should the team member do?

Options:

A.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.

B.

Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.

C.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).

D.

Inform the scrum master so that the change can be discussed directly with the stakeholder.

Buy Now
Questions 324

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Buy Now
Questions 325

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

Options:

A.

Project stakeholders and the team

B.

External subject matter experts (SMEs) and the team

C.

Project sponsor and the team

D.

Project sponsor and the external SMEs

Buy Now
Questions 326

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

Options:

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Buy Now
Questions 327

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.

Reschedule the project execution date.

B.

Continue project execution using the current blueprints from the client.

C.

Escalate this issue to the project sponsor

D.

Consult with the client to determine if project execution should be continued.

Buy Now
Questions 328

A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.

How should the project manager ensure project success?

Options:

A.

Enforce the project manager's authority over the contracting partner delivering to the council. by

B.

Engage a third-party consulting firm to oversee the project's implementation.

C.

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.

D.

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.

Buy Now
Questions 329

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

Options:

A.

Give the new team member time to contribute until they ask for help and support.

B.

Assign the new team member tasks so that the team member knows on what to focus.

C.

Approach the team member to identify any issues and then plan a resolution accordingly.

D.

Review the project with the team member to ensure the project scope is understood

Buy Now
Questions 330

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

Options:

A.

Ensure that the requirements for the project are understood and that the objectives

are verified before approval of an agreement.

B.

Inform the project sponsor that once the agreement has been signed, there cannot

be any changes to the scope of the project.

C.

Notify the project sponsor that the project manager cannot be involved in the

agreement negotiation process.

D.

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Buy Now
Questions 331

A senior management team member contacts an agile project lead and mentions

that certain features the senior manager thought would be in the current release were not

included. What should the agile project lead do?

Options:

A.

Assure the senior manager that these features will be queued up in the next sprint.

B.

Meet with the team to understand why the senior manager’s features were not included.

C.

Invite the senior manager to the next planning meeting.

D.

Send the product roadmap to the senior manager.

Buy Now
Questions 332

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

Options:

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

Buy Now
Questions 333

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

Options:

A.

Iterative for the requirements analysis and delivery phases of the project

B.

Agile for all of the phases of the project, including the requirements analysis and delivery

C.

Predictive for the requirements analysis and agile for delivery of the project

D.

Predictive for the requirements analysis and delivery phases of the project

Buy Now
Questions 334

A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?

Options:

A.

Be clear with directions and assignments so people stay focused and engaged with their work.

B.

Promote an environment where everybody knows what their contribution means to the project as a whole.

C.

Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint

D.

Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.

Buy Now
Questions 335

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.

Email all stakeholders with the objectives of the project and ask for feedback.

B.

Wait for a date when all required attendees can be available onsite.

C.

Run separate meetings to accommodate everyone's schedule.

D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Buy Now
Questions 336

During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?

Options:

A.

Refine and estimate the enhancement so the size is known.

B.

Add it to the product backlog to be completed in the future.

C.

Start working on the enhancement for the customer immediately.

D.

Ask the product owner to prioritize the item with the customer.

Buy Now
Questions 337

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

Options:

A.

Escalate to the project steering committee.

B.

Invite the finance department to the next project demo.

C.

Review the project requirements.

D.

Use the currently available resources.

Buy Now
Questions 338

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

Options:

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

Buy Now
Questions 339

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?

Options:

A.

Cost oriented

B.

Deliverable oriented

C.

Customer oriented

D.

Team oriented

Buy Now
Questions 340

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

Options:

A.

Provide feedback to the team and conduct a meeting to review the team rules.

B.

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.

Provide feedback to the team and request agile training for the new member.

D.

Provide feedback to the team and coach the new team member in agile methodology.

Buy Now
Questions 341

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

Options:

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

Buy Now
Questions 342

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

Options:

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Buy Now
Questions 343

During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?

Options:

A.

Wait to start the project execution phase until all requirements and acceptance criteria are clear.

B.

Ask the customer to include all of the requirements in the project charter to officially start the project planning phase.

C.

Schedule a brainstorming session and select the top ten most important requirements.

D.

In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.

Buy Now
Questions 344

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

Options:

A.

Record it in the risk register

B.

Ask the client to help solve the problem

C.

Start procuring this material from another supplier.

D.

Engage the project team to look for alternatives to find a solution

Buy Now
Questions 345

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

Options:

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

Buy Now
Questions 346

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

Options:

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

Buy Now
Questions 347

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?

Options:

A.

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

B.

Ensure that the stakeholders who are complaining are present for the next project update meetings.

C.

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.

D.

Change the meeting time to the working time zones of the stakeholders who are complaining.

Buy Now
Questions 348

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

Options:

A.

Propose a solution redesign for the project

B.

Perform risk analysis against the issue.

C.

Revise the project's quality control measurements

D.

Develop a mitigation based on the solution design

Buy Now
Questions 349

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

Options:

A.

Cancel the meeting and create the risk register using the project documents.

B.

Continue the meeting and send the updated risk register to all stakeholders.

C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.

D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.

Buy Now
Questions 350

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?

Options:

A.

Start planning the project and then request that a PMO be implemented in the organization

B.

Request that the implementation of a PMO be executed in parallel with the project

C.

Provide project management training to only the internal team involved m the project

D.

Provide project management training to the stakeholders and explain their responsibilities

Buy Now
Questions 351

During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?

Options:

A.

Assess the stakeholder's needs and communication style and propose a tailored approach with regular status reports and progress meetings.

B.

Invite the stakeholder to the regular "show and tell" sessions so the stakeholder is aware of project progress and feedback can be gathered.

C.

Conduct stakeholder remapping, evaluate stakeholders by their level of influence and interest on the project, and communicate accordingly.

D.

Include the stakeholder on regular project communications so that decisions can be followed up closely.

Buy Now
Questions 352

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

Options:

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

Buy Now
Questions 353

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

Options:

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

B.

Document the request and escalate to upper management to consider a modification of the project charter.

C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

Buy Now
Questions 354

The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule

What should the project manager do?

Options:

A.

Conduct a meeting with the project team to discuss and address the sources of disagreement

B.

Inform the stakeholders that the project will be delayed due to previous team management

C.

Crash the project timeline to ensure the project is back on schedule

D.

Issue a change request to extend the project schedule based on identified delays

Buy Now
Questions 355

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

Options:

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

Buy Now
Questions 356

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

Options:

A.

Communicated the project charter to the procurement division

B.

Included a procurement division member on the project team

C.

Reminded the project sponsor about the procurement division's reputation

D.

Communicated the project management plan to the procurement division

Buy Now
Questions 357

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor.

B.

Review the resources required for the tasks on the critical path.

C.

Review and update the risk management plan.

D.

Allocate resources to develop the competencies of the other team members

Buy Now
Questions 358

A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner's expectations.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps

B.

Performed risk management analysis during daily scrums

C.

Reviewed the organizational process assets (OPAs) and lessons learned from similar projects

D.

Performed backlog grooming to ensure that acceptance criteria were being met

Buy Now
Questions 359

A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.

What should the project lead do?

Options:

A.

Invite the board member to the next daily standup.

B.

Invite the board member to the next sprint retrospective.

C.

Invite the board member to a separate demo.

D.

Invite the board member to the next sprint review.

Buy Now
Questions 360

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

Options:

A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration

B.

Review team capacity and reassign the functionality to additional iterations as required

C.

Determine if the team member can work from home to complete the functionality.

D.

Review the work in progress with the product owner to determine the next step

Buy Now
Questions 361

A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented

What should the project manager do?

Options:

A.

Prepare a change request and seek approval from the steering committee regarding the new project framework

B.

Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan

C.

Bring in a third party company to develop and implement a hybrid framework for this specific project.

D.

Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects

Buy Now
Questions 362

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.

Buy Now
Questions 363

A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager

has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management

competencies. The project manager explains that the exiting team members were lazy.

What should the project manager do to prevent this high turnover rate from continuing?

Options:

A.

Be more involved in the team member recruitment process to ensure qualified team members are chosen.

B.

Develop relationship skills as a leader and also develop the teams’ emotional intelligence skills.

C.

Avoid micromanaging the team, enforce stricter rules, and monitor employees.

D.

Explain to the recruiting manager that a project is temporary in nature, making it different than an operational environment.

Buy Now
Questions 364

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

Options:

A.

Create a change request to discuss with the change control board (CCB).

B.

Request additional budget for contingency.

C.

Perform a risk identification process with the project team.

D.

Consult with the project stakeholders.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Buy Now
Questions 365

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

Options:

A.

Ask the individual who is hosting the event to use private communication methods.

B.

Set up a meeting with the distracted team member to discuss any issues

C.

Add a social events section to the charter to handle these situations

D.

Ask the individual who is hosting the event to mark it as private

Buy Now
Questions 366

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

Options:

A.

Comply with the project sponsor's request to not archive the project artifacts.

B.

Document the project sponsor's instructions as the archived project artifacts.

C.

Archive the project artifacts on the project manager's local computer for future reference

D.

Consult with the project management office (PMO) for guidance on project artifacts.

Buy Now
Questions 367

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

Options:

A.

The project is an information technology project and has minimal impact to the organization

B.

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).

C.

The project scope is well defined and the requirements are prioritized

D.

The project team has a colocated space and is capable of working together

Buy Now
Questions 368

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?

Options:

A.

Decompose the item immediately and begin work.

B.

Discuss the impact of starting the item with the team.

C.

Finish the small tasks in progress before decomposing the item.

D.

Communicate the impact with the project sponsor.

Buy Now
Questions 369

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

Options:

A.

Rebaseline the project schedule to show the current status of the project.

B.

Create a benefits management plan mapped to the organization's strategic objectives

C.

Perform a project cost-benefit analysis for the stakeholders

D.

Update the deliverables map against the agreed-upon project requirements

Buy Now
Questions 370

A product owner has an idea for a new product but is struggling to define the

features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?

Options:

A.

Assess the product roadmap to see if there is another product that is more suitable for the build.

B.

Develop a minimum viable product (MVP) for assessment from a select customer group.

C.

Commission a business analyst to research similar competitor products.

D.

Complete a work breakdown structure (WBS) to assess the cost of each feature

Buy Now
Questions 371

A company just started managing a project using an agile approach Due to this change the general manager is worried about the scope definition process for upcoming projects

What should the project manager do to ensure the project scope is completely defined?

Options:

A.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk.

B.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

C.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

D.

Ask the general manager to review every requirement to ensure all projects will deliver the requested products

Buy Now
Questions 372

After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)

Options:

A.

Prepare the lessons learned from the project phase.

B.

Obtain official approval on the new process from the various countries

C.

Send a questionnaire to the project participants and seek their feedback.

D.

Refer to the communications management plan

E.

Deliver the project materials to the users and see if they have any comments

Buy Now
Questions 373

The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible

What should the project manager use to identify the risks?

Options:

A.

An analysis of shared risks between parties

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Expert judgment

D.

A risk value assessment

Buy Now
Questions 374

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?

Options:

A.

Identify the problem's root causes and define the ground rules with all project team members to minimize interferences

B.

Hire a coach to help all project teams to improve their abilities to solve problems on

their own.

C.

Reunite with the project team members affected and tell them not to reduce the team's capacity

D.

Recommend to the project team members that they should improve their planning

and make their stones smaller

Buy Now
Questions 375

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

Options:

A.

Accept the proposed replacement in order to keep procurement activities on track

B.

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.

Consult with a subject matter expert (SME) to see if the proposed change is

acceptable

Buy Now
Questions 376

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule

What can the project manager do to move the team to the norming phase?

Options:

A.

Plan social activities to help foster stronger interpersonal relationships and identify shared goals.

B.

Speak with the project sponsor about changing the team composition

C.

Figure out who is behind the issues and apply progressive disciplinary techniques.

D.

Show the team the schedule impact of their communication issues and encourage them to put their differences aside

Buy Now
Questions 377

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)

Options:

A.

Contact the team member's functional manager and invite them to the next retrospective

B.

Meet with the entire team to review the ground rules about safe environments

C.

Meet with the product owner to talk about the situation.

D.

Contact the team member to explain what information can be shared outside the team

E.

Meet with the sponsor to review the situation.

Buy Now
Questions 378

The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?

Options:

A.

Provide a link to the project's shared drive for the executive to search through for any artifacts that are of interest.

B.

Invite the executive to the project's meeting space to determine if the project information radiators meet their needs

C.

Reach out to the project management office (PMO) for status report templates and provide project updates in that format

D.

Ask the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments

Buy Now
Questions 379

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?

Options:

A.

Emphasize to the teams the importance of meeting the agreed deadlines

B.

Provide appropriate training to compensate for the mismatch.

C.

Update the project schedule to reflect the delay

D.

Accept the risk of the project missing deadlines due to the mismatch.

Buy Now
Questions 380

A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information

How should the project manager handle this situation?

Options:

A.

Apply lean manufacturing to limit the team’s work

B.

Increase retrospectives to deliver results fast

C.

Make work visible using kanban boards.

D.

Incorporate small batches of work into the project

Buy Now
Questions 381

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

Options:

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

Buy Now
Questions 382

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

Options:

A.

Check the approved list of requirements to see if there are any missing items.

B.

Work with the stakeholder to improve the requirements' acceptance criteria

C.

Review the requirements traceability matrix with the concerned stakeholder

D.

Discuss with the stakeholder which additional requirements should be added

Buy Now
Questions 383

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

Options:

A.

Guide the team member on how to resolve the conflict.

B.

Analyze the project schedule and look for alternatives.

C.

Perform crashing and/or fast tracking of the schedule.

D.

Meet the team member and try to plan a course of action together.

Buy Now
Questions 384

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

Options:

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

Buy Now
Questions 385

A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team

How can the project manager ensure knowledge transfer across the team?

Options:

A.

Ask the project team to run a deviation log review meeting with the client, highlighting that the project may not be able to go live as scheduled

B.

Ask the project management office (PMO) to provide team members with real-time visibility for deviations and facilitate team members to resolve issues

C.

Ask the SMEs to share the knowledge transfer documents with all other members by placing the documents in the project management information system (PMIS)

D.

Ask the project team to facilitate a lessons learned session during the project

closure phase to incorporate this issue

Buy Now
Questions 386

Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.

How should the project manager address this situation?

Options:

A.

Send evidence to the new stakeholder that the project's status was sent according to the schedule

B.

Suggest that the new stakeholder review the project status before the next board meeting

C.

Share the communications management plan with the new stakeholder

D.

Discuss project requirements with the new stakeholder, and update the communications management plan.

Buy Now
Questions 387

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

Buy Now
Questions 388

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?

Options:

A.

Escalate the request for additional financial resources

B.

Forward the request to the project management office (PMO) to amend the organizational process assets

C.

Ask the project sponsor to obtain approval for implementation of the new approach

D.

Analyze the requirements that will need to be addressed under the requested method

Buy Now
Questions 389

A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.

What should the project manager have done to prevent this?

Options:

A.

Monitored progress in achieving the business value throughout the project

B.

Asked for additional time to achieve the project goals and increase business value

C.

Increased the number of project resources to ensure attainment of the business value

D.

Reviewed previous projects’ lessons learned and applied them to this project

Buy Now
Questions 390

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?

Options:

A.

Clarify project benefits with the sponsor.

B.

Identify the goal of each work product

C.

Perform integration testing of each release

D.

Include the entire project team in testing

Buy Now
Questions 391

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?

Options:

A.

Understand the context and interdependencies of the process from the team members and then define improvements

B.

Continue with the process as is. and wait until the next phase to suggest any improvements

C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework

D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.

Buy Now
Questions 392

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

Options:

A.

Provided copies of the stakeholder engagement plan to all team members.

B.

Defined the roles and responsibilities of the team members.

C.

Updated the communications management plan.

D.

Established ground rules for the team

Buy Now
Questions 393

A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?

Options:

A.

Ask the product owner, who is the key stakeholder, to choose among the different ideas.

B.

Propose ideas to the group, ask everyone to vote, and then choose the most popular idea

C.

Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.

D.

Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting

Buy Now
Questions 394

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

Options:

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

Buy Now
Questions 395

A project manager has received an updated earned value analysis report The following are the key findings from the report

•Budget at completion = USS1 million

•Earned value = US$0 7 million

•Actual cost = US$0 75 million

•Cost performance index = 0 933

Based on this information, what should the project manager conclude about project performance'?

Options:

A.

The project will be completed exactly as planned

B.

The project will be easier to complete than planned

C.

The project will be difficult to complete as planned.

D.

The project will not be completed as planned

Buy Now
Questions 396

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

Options:

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Buy Now
Questions 397

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

Options:

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

Buy Now
Questions 398

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

Options:

A.

Avoid the conflict as the customer feels comfortable with using processes from

company A.

B.

Review the historical information and make the decision based on the return on

investment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with these

processes.

D.

Work with the team to analyze which processes are suitable to use and define them in

the ground rules.

Buy Now
Questions 399

A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

Options:

A.

Ask for expedited delivery of the component to mitigate the risk of schedule delays

B.

Ensure that relevant stakeholders and expectations are identified and assess the component delay

C.

Perform a detailed analysis of the release content for each component of the solution.

D.

Propose a new design of the solution to replace the external component with an internal one

Buy Now
Questions 400

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?

Options:

A.

Conduct an expert judgment evaluation.

B.

Review the quality management plan

C.

Update the lessons learned register

D.

Review the risk management plan

Buy Now
Questions 401

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of every

iteration.

B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.

C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.

D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidential

information.

Buy Now
Questions 402

A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?

Options:

A.

Implement the planned risk response to handle the issue.

B.

Review possible alternative documentation methods with team

C.

Update the risk register with the risk and proposed impact.

D.

Ask the team to fix the system to resolve the issue

Buy Now
Questions 403

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

Options:

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

Buy Now
Questions 404

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project's success?

Options:

A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution

C.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue

D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities

Buy Now
Questions 405

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

Options:

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

Buy Now
Questions 406

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

Options:

A.

Reduce the priority of project risks as all remaining risks are low-level

B.

Notify stakeholders that all high-level risks have been resolved

C.

Reevaluate identified risks and update the risk register

D.

Reclassify low-level risks as high-level risks

Buy Now
Questions 407

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?

Options:

A.

Review the project management plan

B.

Update the stakeholder engagement plan.

C.

Update the communications management plan

D.

Review the configuration management plan.

Buy Now
Questions 408

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

Options:

A.

Schedule a meeting with all stakeholders to extend the project deadline

B.

Replace the vendor with a new vendor who can offer the component on time

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Review and update the issue log and determine if any alternative components can be offered

Buy Now
Questions 409

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?

Options:

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate

Buy Now
Questions 410

A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.

What should the project manager do?

Options:

A.

Create a roles and responsibilities matrix based on the project charter and ask the sponsor to share it with all stakeholders to provide credible authority

B.

Conduct scoping workshops with the project team to create a work breakdown structure (WBS), assign tasks to various entities share this with all stakeholders, and ask the team to complete their tasks as scheduled

C.

Conduct a general meeting with all stakeholders and review and address a list of activities for each of them

D.

Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities

Buy Now
Questions 411

A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.

What should the project manager do?

Options:

A.

Speak with peers about the need for a project charter

B.

Develop the project charter and send it for approval

C.

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities

D.

Agree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan

Buy Now
Questions 412

A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email

What should the project manager do?

Options:

A.

Contact the sponsor to request direction regarding the communication tool to be used by the project team

B.

Update the communications management plan based on the product owner’s

preferences and distribute to the team

C.

Suggest to the team to start using the communication tool suggested by the product owner

D.

Request the product owner to use email because using another tool will increase the workload

Buy Now
Questions 413

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

Options:

A.

Ask the team to work overtime to complete the deliverable on time

B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.

Check the scope to verify if there is scope creep and get the project on schedule

D.

Submit a change request to the project sponsor to change the schedule

Buy Now
Questions 414

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?

Options:

A.

Move to a Kanban strategy so that work can be reallocated more easily

B.

Decrease the sprint cycle to the average repriontization request by calculating it in days

C.

Set up a meeting with the project team and ask for their opinion on what to do

D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle

Buy Now
Questions 415

A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

Options:

A.

Updated the risk management plan and registered lessons learned for the project

B.

Reorganized the team for the project based on the work breakdown structure (WBS)

C.

Maintained constant communication with the stakeholders of the other projects

D.

Used the resource management plan to identify the impacts of the other projects

Buy Now
Questions 416

The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)

Options:

A.

Discuss with the construction team alternatives on moving the new train station to another location.

B.

Publish information on the city’s website about the benefits that the new tram station will bring

C.

Have a meeting with the mayor and explain the importance of the new train station to the city.

D.

Conduct regular meetings with the neighbors to get their buy-in for the project

E.

Register this situation as a risk and develop a mitigation plan

Buy Now
Questions 417

A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.

What should the project lead do in this situation?

Options:

A.

Challenge the team to find new ways to achieve higher levels of performance to improve the situation.

B.

Speak with individual team members to determine what they would like to do to improve the situation in the team

C.

Have the team inform senior management of the situation and ask for recommendations.

D.

Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct

Buy Now
Questions 418

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?

Options:

A.

Address the lack of performance by coaching the new team member

B.

Discuss options to improve performance with the resource manager

C.

Provide performance feedback as part of the retrospective ceremony.

D.

Request a more efficient replacement resource from the project sponsor

Buy Now
Questions 419

A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful

What should the project manager do in this scenario?

Options:

A.

Develop a business case with assumptions for the new model

B.

Develop a communications management plan to inform the employees about the new business model

C.

Adopt an iterative rollout approach that delivers the highest business value earlier

D.

Develop a detailed sprint plan with clear deliverables

Buy Now
Questions 420

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion

What are two issues that these actions by the project manager could cause? (Choose two)

Options:

A.

A lot of discussions that yield no results or possibly too many results

B.

A lack of direction and motivation for the team in the workshop

C.

Lessons learned from other teams to not be considered

D.

Time management plan for the retrospective workshop to not be updated

E.

A focus on the negative and a disinterest in further improvements

Buy Now
Questions 421

As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.

What should the project manager do first to decide how to manage this project?

Options:

A.

Select a predictive development life cycle based on the team's experience

B.

Determine the most appropriate life cycle approach for the project

C.

Register all requirements into a backlog for further detailed analysis.

D.

Split the requirements, put them into two separate projects, and apply different approaches

Buy Now
Questions 422

A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project

After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?

Options:

A.

Acquire project resources from the new country to mitigate the risk of uncertainty

B.

Evaluate the environmental and regulatory factors and identify high-level risks and assumptions

C.

Identify and monitor the risks closely since the company does not have lessons learned for this country.

D.

Ensure that project sponsors are in agreement on the project deliverables and timeline during the project

Buy Now
Questions 423

A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members

What is the cause for this communication gap?

Options:

A.

The project sprint board has not been updated

B.

Daily standup meetings were not held or enforced

C.

The project status dashboard has not been updated

D.

The communications management plan has not been developed

Buy Now
Questions 424

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?

Options:

A.

Ensured the risk tolerance of the company was property updated

B.

Implemented the communications management plan properly

C.

Implemented the stakeholder engagement plan correctly.

D.

Provided a proper risk response

Buy Now
Questions 425

During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?

Options:

A.

Ask upper management for more funds and update the project budget

B.

Revise the project scope accordingly to cope with the budget changes

C.

Update the risk register and project log. and manage the budget closely.

D.

Submit a change request to accelerate the project as requested

Buy Now
Questions 426

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?

Options:

A.

Sort conflicts into two groups: positive and negative

B.

Place conflicts into categories: structural and interpersonal.

C.

Place conflicts on a shared conflict list and ensure it is visible

D.

Review conflicts during daily Scrum so they are handled in a timely manner

Buy Now
Questions 427

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

Options:

A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

Buy Now
Questions 428

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

Options:

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

Buy Now
Questions 429

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

PMP Question 429

Options:

Buy Now
Questions 430

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork

What should the project manager do to improve morale?

Options:

A.

Identify the wants and aspirations of the team

B.

Build team connections and emotional bonds

C.

Forge consensus through team participation.

D.

Set goals and push the team to achieve the goals

Buy Now
Questions 431

A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?

Options:

A.

Plan a working session focusing on the scope, vision, and mission of the initiative

B.

Start developing the project management plan based on a previous project template from the project management office (PMO).

C.

Conduct benchmarking to determine the business viability of the initiative

D.

Conduct an impact analysis of the new initiative to determine how the project should be rolled out

Buy Now
Questions 432

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

Options:

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Buy Now
Questions 433

A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond'?

Options:

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance

D.

Explain to the stakeholder that the stakeholder engagement plan requires their

attendance at all reviews

Buy Now
Questions 434

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

Options:

A.

Remove the changes to match the original requirements.

B.

Add team members to the project to avoid more schedule delays.

C.

Evaluate the impacts of the changes that were made to the project

D.

Update project documentation with the new scope

Buy Now
Questions 435

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager's next steps?

Options:

A.

Conduct a proof of concept to make sure there are no problems in the revised design

B.

Amend the design specifications and pass them to the development team for reprogramming

C.

Make a change request and get format approval from the project owner

D.

Inform the client of the problem and follow the change request process

Buy Now
Questions 436

A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?

Options:

A.

Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project

B.

Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs

C.

Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk.

D.

Host a project team meeting, then update the risk register and the project management plan

Buy Now
Questions 437

The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies

What should the project manager do?

Options:

A.

Make sure the project team is aware of all agile techniques

B.

Skip the training because the team already understands agile

C.

Ensure the team has a common understanding of agile

D.

Teach one agile methodology fully and completely

Buy Now
Questions 438

A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities

How should the stakeholder be engaged in the project?

Options:

A.

Keep the stakeholder informed and consult with them based on their needs

B.

Involve the stakeholder in governance and decision making

C.

Consult with the stakeholder and increase their level of interest

D.

The stakeholder needs to be made aware of the project progress

Buy Now
Questions 439

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

PMP Question 439

Options:

Buy Now
Questions 440

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?

Options:

A.

Schedule a meeting for the project team to review the communications management plan.

B.

Tell the rest of the project team to continue discussions with the new team member

C.

Send an email to the project team outlining the communications strategy.

D.

Mentor the new team member on the methodology the project team is using

Buy Now
Questions 441

A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right

PMP Question 441

Options:

Buy Now
Questions 442

A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.

What should the project manager do to enhance project team effectiveness?

Options:

A.

Implement team colocation to improve communication.

B.

Identify the root cause of communication issues

C.

Initiate daily communication of project progress

D.

Schedule a communications control board meeting

Buy Now
Questions 443

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

Options:

A.

Talk to the supervisor to tone down their approach and attitude.

B.

Provide a just-in-time training to the technician to improve their skill set.

C.

Use a direct, collaborative approach with the technician and supervisor.

D.

Replace the technician with a high performing resource as time is critical

Buy Now
Questions 444

A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.

What should the project manager have done to avoid this perception?

Options:

A.

Involved the business stakeholders in the sprint review

B.

Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits

C.

Implemented a closing survey for key stakeholders

D.

Confirmed that there is a communications management plan in place to make business stakeholders aware of the success

Buy Now
Questions 445

A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.

How should these conflicts be resolved?

Options:

A.

Include the executives in team retrospectives

B.

Train the executives on agile practices

C.

Negotiate with the executives and agree on a process.

D.

Request that the executives use agile practices

Buy Now
Questions 446

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

Options:

A.

Escalate the issue to the project sponsor.

B.

Review and update dependencies

C.

Schedule a retrospective.

D.

Conduct a root cause analysis.

E.

Create a risk management plan.

Buy Now
Questions 447

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?

Options:

A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project

B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,

C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable

D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits

Buy Now
Questions 448

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?

Options:

A.

Discuss approval of the change request in the next project meeting

B.

Perform a risk assessment on the required change request.

C.

Evaluate the change request against the project scope statement

D.

Ask the sponsor for more funds to cover the change request

Buy Now
Questions 449

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

Options:

A.

Update the issue log and escalate to the project sponsor

B.

Identify the lack of information as a risk and update the risk register

C.

Schedule more frequent meetings with the technical manager.

D.

Review and update the stakeholder engagement plan

Buy Now
Questions 450

A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.

Using a hybrid approach, what techniques can be used to achieve this goal?

Options:

A.

Daily Scrum and product owner quality assessments.

B.

Scrum master reviews and the quality Kanban method

C.

Paired work and the customer role method.

D.

Time-boxed iterations and standup review meetings

Buy Now
Questions 451

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?

Options:

A.

Issue log

B.

Project management plan

C.

Risk management plan

D.

Risk register

Buy Now
Questions 452

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

Options:

A.

Mark the product backlog completion status and update the communications management plan.

B.

Ensure that knowledge transfer activities are executed as planned

C.

Release the resources and plan for a project completion celebration.

D.

Hold a steering committee meeting to inform them of the project completion

Buy Now
Questions 453

A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint

What should the project manager have done to avoid this situation?

Options:

A.

Involved the key stakeholders in the decision-making process

B.

Customized stakeholder communications based on the stakeholders’ needs

C.

Analyzed the changes in stakeholder attributes

D.

Documented the project vision and objectives

Buy Now
Questions 454

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options:

A.

Ensured that all defects identified during testing were resolved before implementation

B.

Ensured that all of the required tasks identified in the scope were completed successfully

C.

Ensured that all documentation was completed post implementation before closing the project

D.

Ensured that all the required approvals were received per the organizational procedures

Buy Now
Questions 455

After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.

Which technique will help the project manager to accelerate the deliverable?

Options:

A.

Impact mapping

B.

Rolling wave planning

C.

Collective code ownership

D.

Scrum of Scrums

Buy Now
Questions 456

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?

Options:

A.

Quality

B.

Estimates

C.

Objectives

D.

Requirements

Buy Now
Questions 457

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?

Options:

A.

Communicate directly with the director and inform them of the communications management plan

B.

Communicate directly with the client stating that any scope changes must go through the project manager

C.

Review the stakeholder engagement plan and put in place any existing actions

accordingly

D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes

Buy Now
Questions 458

A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?

Options:

A.

Review constraints in the ongoing sprint planning and evaluate options for the release plan

B.

Stop the sprint and replan and prioritize the backlog to reduce resource levels

C.

Consult the resource management plan for an appropriate response

D.

Continue with existing sprint plans to ensure some of the scope will be delivered

Buy Now
Questions 459

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?

Options:

A.

Update the issue log and act to minimize the impact

B.

Update the schedule to include the delay

C.

Add the risk and the delay to the risk register

D.

Escalate to the management team for delay approval

Buy Now
Questions 460

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

Options:

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

Buy Now
Questions 461

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Buy Now
Questions 462

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?

Options:

A.

Submit a change request.

B.

Add additional resources to the project

C.

Update the scope of work.

D.

Review the risk management plan

Buy Now
Questions 463

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.

What training should the project manager choose for their team to help with this situation?

Options:

A.

Communication training

B.

Negotiation training

C.

Emotional intelligence training

D.

Agile training.

Buy Now
Questions 464

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?

Options:

A.

Ask the marketing director to participate in daily meetings

B.

Mentor the marketing director on hybrid approaches

C.

Ask the marketing team members to coach the director

D.

Tram the marketing team and keep the director informed

Buy Now
Questions 465

A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch

On what should the project manager focus?

Options:

A.

Ensuring that the team is also focused on the overall change management plan

B.

Determining and aligning performance indicators that will help in assessing successful delivery

C.

Planning for regular project updates to cover the status of critical deliverables

D.

Ensuring that the scope management plan is in place to cover all related objectives

Buy Now
Questions 466

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

Buy Now
Questions 467

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)

Options:

A.

Introduce a recognition program to motivate and reward resource performance

B.

Enhance the competencies of the project team through training, mentoring and coaching.

C.

Increase the trained staff to create back-up for resources

D.

Meet with management to discuss dividing the project into smaller projects

E.

Convince senior management to hire third-party staff

Buy Now
Questions 468

A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?

Options:

A.

Review the stakeholder register and ensure that communications are being followed in line with the communications management plan.

B.

Isolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly

C.

Review the remaining scope and rebaseline the project’s schedule to take into account delays in decision making

D.

Review the adequacy of the project's governance and ensure that an appropriate structure is in place

Buy Now
Questions 469

A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?

Options:

A.

Remove the learn member from the team and hue a more skilled one

B.

Ask the technical lead to provide more training to the team member

C.

Ask the technical lead to discuss performance directly with the team member

D.

Meet with the team member to understand the situation and provide feedback.

Buy Now
Questions 470

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations

B.

Encrypted emails

C.

Videoconferencing

D.

Chat conversations

Buy Now
Questions 471

A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on

weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.

What should the project manager do?

Options:

A.

Implement the call center with internal staff to ensure the work is performed according to the company’s culture.

B.

Work with 50% of the people internally and contract the other 50% to an outside company.

C.

Delegate the analysis to the human resources (HR) department in order to organize the call center operations.

D.

Conduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.

Buy Now
Questions 472

After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?

Options:

A.

Consult the risk and issue logs.

B.

Initiate a project change request.

C.

Create a baseline impact assessment

D.

Discuss with the project sponsor.

Buy Now
Questions 473

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

Options:

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Buy Now
Questions 474

A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation

What should the project manager do?

Options:

A.

Communicate the ground rules, principles and reporting methods to the project stakeholders

B.

Penalize the project team lead for not updating the project documentation properly.

C.

Review this issue with the team lead for possible ways to resolve this situation

D.

Issue guidance to the team member about reporting directly to the project manager

Buy Now
Questions 475

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

Options:

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Buy Now
Questions 476

During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version

How can the project manager prevent this outcome in the new project?

Options:

A.

Hire a team of external users to perform acceptance testing on the product.

B.

Define a user focus group as external stakeholders with a high influence on outcomes

C.

Hire a consultant to perform a benefit analysis as an input to the project charter.

D.

Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS

Buy Now
Questions 477

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Buy Now
Questions 478

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.

Send a formal communication regarding the missed milestone

B.

Delay sending a formal communication until the project team catches up

C.

Ask for a meeting with the sponsor to decide whether to send the formal communication

D.

Forego the formal communication and have a conversation with the supervisor

Buy Now
Questions 479

During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.

What should the project manager have done to avoid this situation?

Options:

A.

Determined the appropriate type of incentive for key team members

B.

Conducted frequent monitoring on key team members’ performance during project execution

C.

Distributed the monetary incentive according to the team members’ individual performance

D.

identified the underperforming team members and asked the human resources (HR) department to replace them

Buy Now
Questions 480

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

Options:

A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.

Perform an independent analysis to determine the stakeholders from the client's organization.

D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

Buy Now
Questions 481

A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?

Options:

A.

Meet with this team member.

B.

Review this method with the team.

C.

Accept this task-based estimation.

D.

Reject this task-based estimation.

Buy Now
Questions 482

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

Options:

A.

Record the issue then refocus the team's efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

Buy Now
Questions 483

A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

Options:

A.

Meet with the project sponsor to explain that the project cannot be completed as planned

B.

Meet with the technical lead to review the sprint plan

C.

Meet with the product owner to confirm the minimum viable product (MVP) option

D.

Meet with the project team and reprioritize the backlog

Buy Now
Questions 484

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

Options:

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Buy Now
Questions 485

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

Options:

A.

Review the project scope to align the project teams

B.

Review the resource management plan to align the project teams

C.

Review the project integration plan to align the project teams

D.

Review the work breakdown structure (WBS) to align the project teams

Buy Now
Questions 486

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

Options:

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Buy Now
Questions 487

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

Options:

A.

Resource breakdown structure

B.

Work breakdown structure (WBS)

C.

Team charter

D.

Project charter

Buy Now
Questions 488

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

Buy Now
Questions 489

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Buy Now
Questions 490

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

Options:

A.

Ask the leadership team for help obtaining the needed staff.

B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.

Check with human resources (HR) regarding the availability of staff.

Buy Now
Questions 491

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?

Options:

A.

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan

B.

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis

C.

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge

D.

Form a brainstorming team with stakeholders from all of the functional departments involved in the project

Buy Now
Questions 492

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

Options:

A.

Instruct the team members involved to resolve the issue among themselves

B.

Discuss the issue with the steering committee to determine the proper course of action.

C.

Coordinate a video conference with the offending team member to resolve the issue

D.

Reassign the offending team member to a different project

Buy Now
Questions 493

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation'?

Options:

A.

Ask the functional manager why a decision was made without consulting them

B.

Use soft skills to influence the team member to slay until the project is completed

C.

Ask the functional manager for an immediate replacement for the team member.

D.

Review the risk management plan and mitigation plan to understand the impact of this issue

Buy Now
Questions 494

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

Options:

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Buy Now
Questions 495

A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?

Options:

A.

Log a risk in the risk register and work with the new team member to mitigate it

B.

Motivate the new team member to perform.

C.

Share project documents with the new team member.

D.

Offer cross-training and mentoring to the new team member

Buy Now
Questions 496

The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.

What should the project manager do first?

Options:

A.

Update the risk register in order to add the issue.

B.

Review the issue log regarding the concern

C.

Revise the benefits management plan

D.

Assess the repository to check for inconsistencies.

Buy Now
Questions 497

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

Options:

A.

Share project updates when requested by the stakeholders.

B.

Share project updates through regular community meetings.

C.

Share the annual reports virtually and in the local newspapers.

D.

Share the project reports with the sponsor to inform community members.

Buy Now
Questions 498

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

Options:

A.

Send an email invitation to the project sponsor to attend all of the project team's weekly meetings, and hope the sponsor will find time to attend

B.

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them

C.

Continue emailing updated project status reports highlighting the key risks and

issues, and wait for the project sponsor to request a meeting

D.

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond

Buy Now
Questions 499

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Buy Now
Questions 500

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

Options:

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

Buy Now
Questions 501

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?

Options:

A.

Advise the marketing team that at this stage of the project changes to the scope are no longer accepted

B.

Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change

C.

Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion

D.

Review the change request with the project stakeholders and evaluate the impact of the scope reduction

Buy Now
Questions 502

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

Options:

A.

Facilitate a team-building meeting to help this issue

B.

Allow the team members to remain in their former individual roles

C.

Directly guide the team members on how to perform their tasks

D.

Wait until some iterations are completed to intervene

Buy Now
Questions 503

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Buy Now
Questions 504

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

Options:

A.

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.

B.

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.

C.

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,

D.

Determine what methods the team has been trained on and utilize those methods for the project.

Buy Now
Questions 505

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

Options:

A.

Laissez-faire

B.

Transactional

C.

Transformational

D.

Charismatic

Buy Now
Questions 506

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Buy Now
Questions 507

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

Options:

A.

Move the solution designer to another team.

B.

Review the process that resulted in this situation.

C.

Stop work until the design document is completed.

D.

Ask the team to document the design.

Buy Now
Questions 508

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

Options:

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

Buy Now
Questions 509

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.

Inform the design team to ensure compliance during the product design phase

B.

Inform the quality team that they need to ensure that the product is in compliance

C.

Ensure that compliance is explicitly mentioned in the relevant requirements

D.

Meet with the team and remind them of the compliance requirements

Buy Now
Questions 510

A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules

Which two actions should the project manager take with regard to schedule analysis? (Choose two)

Options:

A.

Review with subject matter experts (SMEs) to ensure they have contributed to the schedule development

B.

Evaluate the master schedule and perform fast tracking and task crashing

C.

Look (or gaps in the different schedules to determine which major risks might evolve over time

D.

Review the project schedules to ensure that all tasks end with milestones

E.

Evaluate the schedules for interdependencies to establish the critical path

Buy Now
Questions 511

A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?

Options:

A.

Ask the provider to seek options to solve the issue

B.

Add the issue to the issue log and report it at the next review meeting

C.

Review the current plan and consolidate if necessary

D.

Schedule a meeting with the provider to collaborate on the options

Buy Now
Questions 512

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager's priority in this situation?

Options:

A.

Request that the team member gel the contract signed as soon as possible

B.

Determine a mitigation strategy to move the project forward

C.

Take over contract negotiations for the team member to speed up the process

D.

Assist with the removal of impediments and blockers so that the project can continue

Buy Now
Questions 513

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

Options:

A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.

Check the ground rules of the meeting to review the initial agreement with the team members

C.

Identify one team representative to speak up during the daily meeting and share the team updates

D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

Buy Now
Questions 514

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

Options:

A.

Invite the client and product owner to all planning, review, and retrospective meetings.

B.

Accept the escalations and manage them so the working relationship with the client is

not impacted.

C.

Review and clarify roles, responsibilities, and the governance model at the next sprint

review meeting.

D.

Invite the product owner to attend all Scrum meetings and define the governance model

and escalation path.

Buy Now
Questions 515

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

Buy Now
Questions 516

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

Options:

A.

Advise the teams to follow the company’s existing project management approach.

B.

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

C.

Let a senior team member select the approach that is appropriate.

D.

Insist the teams both follow either a predictive or agile approach.

Buy Now
Questions 517

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

Options:

A.

Allow the sponsor to determine how long the planning phase should last.

B.

Allow the client ta determine how long the planning phase should last.

C.

Ask the functional manager to work with the team to finalize planning and begin building the product.

D.

Explain that more features can be planned in upcoming Iterations and begin building the product.

Buy Now
Questions 518

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

Options:

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

Buy Now
Questions 519

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

Options:

A.

Foster knowledge sharing and coaching among team members.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Seek an external expert to review the framework.

Buy Now
Questions 520

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

Options:

A.

Review and update the project schedule according to performance

B.

Review the schedule baseline and consider adopting a schedule performance indicator

C.

Develop a lime. cost, and scope tracking method exclusively for this project.

D.

Adopt a formal change management process for the project

Buy Now
Questions 521

A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?

How should the project manager reply to the product owner?

Options:

A.

The functionality is delivered early; therefore, more value is delivered.

B.

The team productivity is higher; therefore, more value is delivered,

C.

The cost is reduced: therefore, the total value delivered is higher.

D.

The risk is significantly reduced; therefore, more value Is delivered.

Buy Now
Questions 522

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.

Organize a brainstorming session with the project team to address the issue.

B.

Advise the project team on the importance of team engagement,

C.

Invest in coaching and training for all project team members.

D.

Escalate the issue with the human resource (HR) department to take action,

Buy Now
Questions 523

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

Options:

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Buy Now
Questions 524

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

Options:

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

Buy Now
Questions 525

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

Options:

A.

Ask the accounting manager to delegate a team member who can support the project.

B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

D.

Begin discussions with other functional managers and meet with the accounting manager later.

Buy Now
Questions 526

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

Options:

A.

Shared

B.

Accepted

C.

Enhanced

D.

Exploited

Buy Now
Questions 527

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

Options:

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Buy Now
Questions 528

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

Options:

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Buy Now
Questions 529

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

Options:

A.

Document the issues and extend the project delivery timeline.

B.

Convene the steering committee and inform them of the impact to the project.

C.

Prioritize the user stories with issues and have the team resolve them

D.

Update the project management plan and risk management plan.

Buy Now
Questions 530

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?

Options:

A.

Established ground rules before the discussion had started.

B.

Asked stakeholders not to voice their opinions during the meeting.

C.

Invited a high-level sponsor to the meeting to reduce the level of disagreement.

D.

Reinforced that higher-level management has the decision power.

Buy Now
Questions 531

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

Options:

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Buy Now
Questions 532

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

Options:

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Buy Now
Questions 533

A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline

What should the project manager do next?

Options:

A.

Select resources who are more experienced with the new technology

B.

Perform a root-cause analysis to measure how the new training will address the issue

C.

Include in the risk register a risk of unskilled resources for the new technology

D.

Elaborate and socialize the team charter as per the resource management plan

Buy Now
Questions 534

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Buy Now
Questions 535

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

Options:

A.

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped

B.

Review the backlogs from similar projects and understand how change requests were implemented

C.

Ask the product owner to follow the change request process to formalize new requirements

D.

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team

Buy Now
Questions 536

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Options:

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Buy Now
Questions 537

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

Options:

A.

Escalate a schedule risk to the sponsor.

B.

Conduct team-building exercises.

C.

Stop the project and perform a team skill assessment.

D.

Make sure that the team has a full understanding of the scope.

Buy Now
Questions 538

During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables

How should the project manager mitigate this risk without compromising the completion date?

Options:

A.

Review the integrated change control process to restrict the number of changes

B.

Focus on delivering incremental value through multiple smaller deliveries

C.

Request sponsor support to get buy-in from the users and stakeholders

D.

Restart the stakeholder engagement process by collecting user requirements again

Buy Now
Questions 539

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

Options:

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

Buy Now
Questions 540

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

Options:

A.

Apply a root-cause analysis on the data breaches.

B.

Ensure that all team members complete the training.

C.

Redesign the training courseware to make it interesting.

D.

Retrain the team members responsible for the breaches.

Buy Now
Questions 541

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

Options:

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Buy Now
Questions 542

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

Options:

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impact

negotiation.

Buy Now
Questions 543

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Buy Now
Questions 544

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?

Options:

A.

Postpone the required work on the project until school holidays begin

B.

Advise the school to close (or the duration of the project work

C.

Continue the work as planned and inform the school when the project team arrives on-site

D.

Liaise with the school to include nonworking project hours during school start and finish times

Buy Now
Questions 545

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

Options:

A.

Review the procurement documentation and modify requirements as needed.

B.

Study the new regulations with the team and evaluate if there is any impact on the

project variables.

C.

Update the contingency plan to take this issue into account.

D.

Meet with the stakeholders to update the risk register and risk management plan.

Buy Now
Questions 546

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

Options:

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,

D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Buy Now
Questions 547

A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery

How should the project manager avoid this situation in the future?

Options:

A.

Use the same methods until the end of the current delivery and suggest new ones during the retrospective.

B.

Refer to the policies and frameworks used at the company enterprise level and inform the project team members.

C.

Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.

D.

Agree with the project team on a suitable collaboration and make sure information is shared at all times

Buy Now
Questions 548

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

Options:

A.

Escalate the situation to the customer management team.

B.

Ask the customer to discuss these changes with the product owner.

C.

Request that the customer to meet with the team only at the weekly meeting.

D.

Ask the customer to discuss these changes with the management team.

Buy Now
Questions 549

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

Options:

A.

Appoint a dedicated product manager for the duration of the release

B.

Have the customer approve the product increment features.

C.

Ensure every user story has acceptance criteria.

D.

Track business outcomes for planned user stories.

Buy Now
Questions 550

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

Options:

A.

Meet with each team member separately and apply an appropriate approach with each one.

B.

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Assign multiple managers to the various teams and delegate all of the tasks to them.

Buy Now
Questions 551

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

Options:

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

Buy Now
Questions 552

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

Buy Now
Questions 553

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

Options:

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

Buy Now
Questions 554

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

Options:

A.

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.

B.

Direct the team to implement the benefits management plan and track achievements before the end of the project.

C.

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

D.

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.

Buy Now
Questions 555

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

Options:

A.

Tell the owner that a rough order of magnitude will be provided.

B.

Contact a subject matter expert (SME) for advice and consultation.

C.

Call a meeting with the project team to identify the most appropriate approach.

D.

Tell the owner that the task requires more time and expertise

Buy Now
Questions 556

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Buy Now
Questions 557

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

Options:

A.

Explain to the stakeholder that any modifications require additional budget

B.

Review the missed program deliverables with the project team

C.

Review the project charter for the project approval criteria

D.

Speak with the team's manager to get extra hours from the team

Buy Now
Questions 558

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

Options:

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Buy Now
Questions 559

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

Options:

A.

Evaluate demonstrated task accountability

B.

Determine the appropriate approach

C.

Analyze team member influence

D.

Identify levels of decision-making authority

Buy Now
Questions 560

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

Options:

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Buy Now
Questions 561

A project team is implementing a new solution that will be distributed worldwide. Due to a new issue that has a global impact, several government agencies are implementing new regulations that will affect the solution. The project manager must assess and prioritize the impact of these changes on the project scope/backlog.

Which analytical tool can be used by the project manager to define this scenario?

Options:

A.

Political, economic social, technological legal, and environmental (PESTLE)

B.

Strengths, weaknesses opportunities, and threats (SWOT)

C.

Valuable rare, inimitable resources, and organization (VRIO)

D.

Net present value (NPV)

Buy Now
Questions 562

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

Options:

A.

Create a quality assurance plan for the documentation.

B.

Identify the components of the project documentation.

C.

Archive only the initial and draft versions of the documents.

D.

Ensure that the documents are in an easily retrievable form.

E.

Collect the documents at the time of their creation.

Buy Now
Questions 563

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Buy Now
Questions 564

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.

B.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.

C.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.

D.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.

Buy Now
Questions 565

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal and

external resource requirements.

B.

Commit each team member's time and deliverables and aim for overall project

completion.

C.

Continue the project implementation without the site engineers to ensure the schedule

is maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Buy Now
Questions 566

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

Options:

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for the

project.

Buy Now
Questions 567

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?

Options:

A.

Inform executive management that the customer is made aware of the status during

the sprint demo.

B.

Prepare a weekly status report and share it with executive management every week.

C.

Inform executive management about agile principles and processes that are followed

in the project.

D.

Ask the team to prepare and share the status report with executive management every

week.

Buy Now
Questions 568

An agile team has started a new project. When should the project manager organize their first team retrospective?

Options:

A.

When the team completes a release of a monumental increment

B.

When the team reaches a major milestone

C.

When more than a few weeks have passed

D.

When the work is progressing well through the team

Buy Now
Questions 569

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

Options:

A.

Document this information in the risk management plan.

B.

Develop a contingency plan to prepare for possible risks.

C.

Continue executing the project using expert judgment.

D.

Review the lessons learned registers from the previous projects.

Buy Now
Questions 570

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

Options:

A.

Encourage and motivate the team with project incentives

B.

Subdivide the team to handle different aspects of the project

C.

Support the team to find and execute the minimum viable product (MVP)

D.

Organize project execution to satisfy the project sponsor s request

Buy Now
Questions 571

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?

Options:

A.

Recommend agile training programs that best suit the client project manager's schedule.

B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.

C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals

D.

Provide the client project manager with agile best practice documents and web resources.

Buy Now
Questions 572

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

Options:

A.

Send an email update to existing team members about the addition of the new team

members.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

Buy Now
Questions 573

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

Options:

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Buy Now
Questions 574

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

Options:

A.

Requirements analysis

B.

Retrospective

C.

Sprint planning

D.

Standup

E.

Backlog refinement

Buy Now
Questions 575

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

Options:

A.

Schedule meetings with all of the stakeholders to make business decisions when

needed.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders

ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all

unavailable stakeholders informed.

D.

Add time reserve in the project schedule to allow extra time for the stakeholders to

make decisions.

Buy Now
Questions 576

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options:

A.

Seek the sponsor's approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

Buy Now
Questions 577

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

Options:

A.

Assessed the technical and organizational readiness for the project and identified risks

at the beginning of the first iteration

B.

Requested the product owner's approval to add an external expert to define the

acceptance criteria

C.

Defined a clear acceptance criteria at the initiation phase and continued with the

project

D.

Increased the communications between the team member and the product owner

Buy Now
Questions 578

On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.

How should the project manager set up communications?

Options:

A.

Inform the client that all communications moving forward will go through the project manager

B.

Ensure that the communications management plan covers contractual obligations

C.

Consult the communications management plan from a recent project that has been closed

D.

Update the communications management plan to allow the subcontractors to communicate directly with the client

Buy Now
Questions 579

A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations

PMP Question 579

One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?

Options:

A.

Schedule crashing

B.

Fast tracking

C.

Earned schedule

D.

Earned value

Buy Now
Questions 580

During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?

Options:

A.

Asking and listening

B.

Being collaborative

C.

Managing expectations

D.

Building trust

Buy Now
Questions 581

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?

Options:

A.

Review the backlog to reschedule the deliverable for a later iteration.

B.

Engage with stakeholders directly to review the iteration process.

C.

Determine whether other cross-functional team members are able to take over the

work.

D.

Go to management and ask to hire a new external developer.

Buy Now
Questions 582

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

Options:

A.

A team whose members work independently and are the best subject matter experts

(SMES)

B.

A team whose members have more general aptitudes but like to work individually

C.

A team whose members have different skill sets and are spread out geographically

D.

A team whose members have more general aptitudes and can collaborate on different tasks

Buy Now
Questions 583

A project requires testing of the final product to be done at another department's

testing facility, which is known for having low availability. This situation could potentially

impact the project schedule.

What should the project manager do next?

Options:

A.

Update the risk register.

B.

Update the issue log.

C.

Update the lessons learned register.

D.

Update the project schedule.

Buy Now
Questions 584

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

Options:

A.

Review the established project benefits tracking metrics.

B.

Update the project business case document.

C.

Document the agreed-upon ownership of benefits realization.

D.

Create a project benefits management plan.

Buy Now
Questions 585

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

Options:

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.

Buy Now
Questions 586

An international client contacted a software development company to build out a

software product, and an agile project manager was assigned. At one of the review meetings,

the client complains that a feature mentioned at the initial debriefing was not implemented.

What should the project manager do?

Options:

A.

Include the mentioned feature in the prioritized requirements list.

B.

Assign a team member to immediately start working on that feature.

C.

Review the original project documentation to confirm.

D.

Treat it as a change request and assess the effect on the project's goals.

Buy Now
Questions 587

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

Options:

A.

Replan the remaining iterations according to the new installation dates

B.

Update the product backlog m order to address the delays

C.

Review the procurement agreements to address the situation

D.

Find another vendor who can fulfill the delivery dates

Buy Now
Questions 588

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Buy Now
Questions 589

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?

Options:

A.

Explain to the management team that reporting and management dashboards are not effective agile practices

B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant

C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)

D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting

Buy Now
Questions 590

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Buy Now
Questions 591

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

Options:

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Buy Now
Questions 592

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

PMP Question 592

Options:

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

Buy Now
Questions 593

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?

Options:

A.

Work on resolving the differences with the key resource and building a good working

relationship to ensure project success.

B.

Monitor the key resource closely throughout the project, but do not let the project

sponsor know about the conflict.

C.

Request that the key resource's functional manager work directly with the resource

during the project.

D.

Discuss this with the project sponsor and request that this key resource be replaced on

the project.

Buy Now
Questions 594

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

Options:

A.

Define clear guidelines on how decisions should be made under the new

organizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance of

accountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up the

team's velocity.

Buy Now
Questions 595

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

Options:

A.

Mass communication

B.

Push communication

C.

Pull communication

D.

Interactive communication

Buy Now
Questions 596

A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?

Options:

A.

An agreed-upon work method and tools that should fit the business need and project constraints

B.

A detailed mitigation plan on the risks for each work method and the tools used

C.

A consensus that everything will run as anticipated once the tools and work methods are identified

D.

A technology roadmap for creating similar deliverables in the future with the same tools

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2025 Version)
Last Update: Aug 14, 2025
Questions: 1988

PDF + Testing Engine

$209.65  $599

Testing Engine

$157.15  $449
buy now PMP testing engine

PDF (Q&A)

$139.65  $399
buy now PMP pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 18 Aug 2025